Control charts
Short answer
A control chart plots process data over time with a mean and ±3σ control limits to distinguish common cause variation from special causes. A point outside limits or seven consecutive points on one side signals an out-of-control process needing investigation.
What do you mean by control charts?
A control chart is a graph used to study how a process changes over time. Data are plotted in time order, with a central line (average) and upper and lower control limits (usually ±3 standard deviations) that show the expected variation of a stable process. It is one of the seven basic quality tools, developed by Walter Shewhart.
Parts
Value
* (out of control)
UCL --------------------------------- upper control limit
* *
CL --*---*-*---*---*---*--*--------- centre line (mean)
* *
LCL --------------------------------- lower control limit
1 2 3 4 5 6 7 8 9 10 ... sample / time
Purpose
- Determine whether a process is in control (stable, with only random/common causes) or out of control (special causes present).
- Monitor the stability of project processes, such as defects per build, response time or schedule variance.
- Prevent defects by detecting trends early.
- Decide whether corrective action is needed.
Interpretation
- A point outside the control limits means an assignable cause that needs investigation.
- Rule of seven: seven consecutive points on one side of the mean show a non-random pattern (trend) even if they are within limits.
- Trends or cycles indicate a problem.
- Control limits differ from specification limits (the customer's requirement). A process may be in control but still not meet specifications.
Types
| Type | Data |
|---|---|
| X-bar and R chart | Variable data (measurements) |
| p-chart | Proportion defective |
| c-chart / u-chart | Number of defects per unit |
Steps to prepare
- Select the characteristic to measure.
- Collect samples at regular intervals.
- Calculate the mean and standard deviation; set UCL = mean + 3σ, LCL = mean − 3σ.
- Plot and interpret.
Example: A team plots the number of bugs found per release. A point above the UCL after a new library was introduced shows a special cause, which leads to a review of the library.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Pareto charts · ICT Project Management, chapter 10
- Integrated change control · ICT Project Management, chapter 7
- Project scope control · ICT Project Management, chapter 7
- Schedule development and control · ICT Project Management, chapter 8
- Test life cycle in quality control · ICT Project Management, chapter 10
- Constructing and interpreting X-bar and R charts · Metrology, chapter 15
- Quality control of concrete at site · Concrete Technology and Masonry Structure, chapter 5 · asked 11×
- Case study: current control and recommendation · Instrumentation II, chapter 10 · asked 3×
- Project control and control cycle steps · Project Engineering, chapter 4 · asked 3×