EVA parameters and their interpretation

Short answer

Earned Value Analysis integrates scope, time, and cost by comparing earned value with planned value and actual cost. Parameters are BAC, PV, EV, AC; variances SV=EV-PV, CV=EV-AC; indices SPI=EV/PV, CPI=EV/AC; forecasts EAC=BAC/CPI, ETC=EAC-AC, VAC=BAC-EAC. Positive SV/CV and indices above 1 mean ahead/under budget; below 1 mean behind/over.

What is Earned Value Analysis? Mention the different parameters of Earned Value Analysis and their interpretation.

Earned Value Analysis

EVA is a project control technique that measures project progress by comparing the budgeted value of the work done (earned value) with the planned value and with the actual cost. It integrates scope, time and cost, and gives variances, indices and forecasts of the final cost and time.

Parameters and interpretation

TermOther nameMeaning
BACBudget at completionTotal approved budget of the project
PVBCWS (planned value)Budgeted cost of the work scheduled up to the date
EVBCWP (earned value)Budgeted cost of the work actually completed = % complete x BAC
ACACWP (actual cost)Actual money spent for the work done up to the date
ParameterFormulaInterpretation
Schedule variance SVEV−PVEV - PVPositive: ahead; zero: on time; negative: behind schedule
Cost variance CVEV−ACEV - ACPositive: under budget; zero: on budget; negative: over budget
Schedule performance index SPIEV/PVEV/PV> 1 ahead; = 1 on time; < 1 behind. E.g. 0.8 means only 80 % of the planned work is done
Cost performance index CPIEV/ACEV/AC> 1 efficient; = 1 on budget; < 1 over budget. E.g. 0.8 means Rs 0.80 of value is earned for each Rs 1 spent
Estimate at completion EACBAC/CPIBAC/CPIForecast of the final cost
Estimate to complete ETCEAC−ACEAC - ACCost still to be spent
Variance at completion VACBAC−EACBAC - EACExpected underrun or overrun at the end
Forecast durationplanned duration / SPIExpected completion time