- 2065 Shrawan (old course) · 8 marks
EVA; 125 cu.m concrete in 10 days
Short answer
PV = Rs 3,75,000, EV = Rs 4,00,000, AC = Rs 3,75,000; SV = Rs 25,000, CV = Rs 25,000, SPI = 1.067, CPI = 1.067. The project is ahead of schedule and under budget.
Explain earned value analysis. When 125 cub.m. of concrete is to be done in 10 days at the cost of Rs 1,250,000, at the end of the third day 40 cub.m. of concrete was completed with expenses of Rs 3,75,000. Find EVA and comment on the performance.
Earned value analysis
EVA is a project control technique that integrates scope, time and cost. It compares the planned value (PV), the earned value (EV) and the actual cost (AC) at a reporting date to find the schedule and cost variances and to forecast the final cost and duration. It is based on the budgeted cost of work scheduled (BCWS), the budgeted cost of work performed (BCWP) and the actual cost of work performed (ACWP).
| Term | Meaning |
|---|---|
| PV (BCWS) | Planned value: budgeted cost of work scheduled up to the date |
| EV (BCWP) | Earned value: budgeted cost of work actually completed |
| AC (ACWP) | Actual cost spent for the work completed |
| SV = EV - PV | Schedule variance (positive = ahead) |
| CV = EV - AC | Cost variance (positive = under budget) |
| SPI = EV/PV | Schedule performance index (>1 ahead) |
| CPI = EV/AC | Cost performance index (>1 under budget) |
| EAC = BAC/CPI | Estimate at completion |
Numerical
- BAC = Rs 12,50,000 for 125 m³ in 10 days (Rs 10,000/m³)
- At day 3: planned = 30 % of the work (37.5 m³); done = 40 m³ (32 %); expenses = Rs 3,75,000
Calculation
Comment
- Schedule: SV is positive and SPI = 1.067, so the project is ahead of schedule. The work done is 106.7 % of the planned work. At this rate the concreting will take about 9.4 days instead of the planned 10 days.
- Cost: CV is positive and CPI = 1.067, so the project is under budget. Each Rs 1 spent gives Rs 1.07 of work.
- Forecast: if the present cost trend continues, the final cost will be Rs 11,71,875 against the budget of Rs 12,50,000 (variance at completion = Rs 78,125 saving).
Answer: SV = Rs 25,000, CV = Rs 25,000, SPI = 1.067, CPI = 1.067; the project is ahead of schedule and under budget.
Both schedule and cost are favourable. Controlling statements: continue the present method, maintain productivity and quality, keep records, and watch for later risks.
The planned concrete by day 3 was 37.5 m³, but 40 m³ was placed, so the work is ahead. The actual unit cost is Rs 9,375/m³ against the budget of Rs 10,000/m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA; 10 days, 100,000, day 6, spi and cpi · Project Engineering, chapter 4
- Cost control need; earned value; EVA approach · Project Engineering, chapter 4
- Earned value analysis for performance control · Construction Management, chapter 7 · asked 6×
- EVA numerical with five activities at day 5 · Construction Management, chapter 7
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- EVA numerical with bar schedule (A to F) · Construction Management, chapter 7