- 2078 Bhadra · 8 marks
EVA; parking meters installation
Short answer
Based on BAC Rs 20,00,000 at Rs 2,000 per meter, planned 25 meters/day, review at day 18: PV = 25×18×2000 = Rs 9,00,000, EV from 400 meters installed = Rs 8,00,000, AC = Rs 10,00,000. SV = –Rs 1,00,000, CV = –Rs 2,00,000, SPI = 0.89, CPI = 0.80, EAC = Rs 25,00,000. Project is behind schedule and over budget.
A company has signed a fixed cost contract to install 1000 new parking meters at a cost of Rs 20,00,000. Old parking meters have to be removed from their stands and replaced with new ones. The cost of doing this is Rs 2000 per meter. It is estimated that 25 meters are installed each day. On the review date at day 18 only 400 meters have been installed and it was found that the actual cost of work performed equals Rs 10,00,000. Find out all the parameters of earned value analysis and comment on the performance status of this project.
Given data
- Fixed contract: 1000 meters at Rs 20,00,000, i.e. Rs 2,000 per meter, so .
- Planned rate = 25 meters/day, so the planned duration = 1000 / 25 = 40 days.
- Review at day 18: meters installed = 400; .
Calculation
Comment
- Schedule: SV = -1,00,000 and SPI = 0.89, so the project is behind schedule; only 89 % of the planned work is done. If the same rate continues, the duration becomes 45.0 days against 40 days planned.
- Cost: CV = -2,00,000 and CPI = 0.80, so the project is over budget; each rupee spent has earned Rs 0.80 of work.
- Forecast: EAC = Rs 25,00,000 against BAC = Rs 20,00,000, i.e. a final overrun of Rs 5,00,000.
Only 400 meters are installed against 450 planned (50 meters behind), and the actual cost per meter installed is 10,00,000 / 400 = Rs 2,500 against the budgeted Rs 2,000 (25 % higher). At the present rate the installation needs about 45 days instead of 40 days. Action: add installation crews, check why the cost per meter is high (rework, transport, idle labour) and control it, since the contract is fixed-cost and the overrun is borne by the company.
Answer: PV = Rs 9,00,000; EV = Rs 8,00,000; AC = Rs 10,00,000; SV = Rs -1,00,000; CV = Rs -2,00,000; SPI = 0.89; CPI = 0.80; EAC = Rs 25,00,000; behind schedule and over budget.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA; 60 days, 25% work, Rs 12,00,000 · Project Engineering, chapter 4
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4
- EVA application; 35 days, Rs 8,00,000 spent · Project Engineering, chapter 4
- EVA; BCWS 9,50,000, BCWP 8,00,000, ACWP 10,00,000 · Project Engineering, chapter 4
- EVA; 10 days, 50 labour days at Rs 1000 · Project Engineering, chapter 4 · asked 2×
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4
- ESL of new machine; when to replace old · Engineering Economics, chapter 5
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- Painting on new and old woodwork · Building Technology, chapter 9 · asked 2×
- Filter definition and denormalization from ωold to ωnew · Filter Design, chapter 1