Dummy activity and float definitions

Short answer

A dummy activity is a zero-duration, zero-resource arrow used only to maintain logic. Total float is the maximum delay an activity can have without delaying the project (LST – EST). Free float is the delay allowed without affecting the earliest start of any successor. Independent float is the delay possible when all predecessors finish as late as possible and successors start as early as possible.

Define the terms dummy activity, total float, free float and independent float.

Example network used below (days): A = 4 and B = 3 are start activities; C = 5 and D = 2 follow A; E = 3 follows C and D; F = 4 follows B. Project duration = 12 days.

(1) --A(4)--> (2)
(1) --B(3)--> (3)
(2) --D(2)--> (4)
(2) --C(5)--> (5)
(3) --F(4)--> (6)
(4) - - dummy - -> (5)
(5) --E(3)--> (6)
ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A404040000
B303585050
C549490000
D246793303
E39129120000
F4378125500

Dummy activity

A dummy activity is an imaginary activity with zero duration and zero resource, shown by a dashed arrow, used to maintain correct logic or give unique event numbers (the dashed arrow (4)-(5) in the example keeps E dependent on both C and D).

Total float

Total float is the time by which an activity can be delayed without delaying the project completion date. TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT. Example: B has TF = 8 - 3 = 5 days; critical activities have TF = 0.

Free float

Free float is the time by which an activity can be delayed without affecting the earliest start of any succeeding activity. FF=min⁡(EST of successors)−EFTFF = \min(EST\ \text{of successors}) - EFT. Example: D has FF = 9 - 6 = 3 days (E starts at 9).

Independent float

Independent float is the time by which an activity can be delayed even when all its predecessors finish as late as possible and its successors start as early as possible; it affects neither predecessors nor successors. IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max(0,\ \min(EST\ \text{of successors}) - \max(LFT\ \text{of predecessors}) - D). Example: D has IndF = 9 - 4 - 2 = 3 days; B has IndF = 3 - 0 - 3 = 0.

(Interfering float = TF - FF is the part of the total float that is shared with the successors; e.g. B: 5 - 0 = 5 days.)