Total float and independent float

Short answer

Total float is the maximum delay allowed without delaying project completion (LST–EST). Independent float is the delay possible when all predecessors finish as late as possible and successors start as early as possible, calculated as max(0, min(EST of successors) – max(LFT of predecessors) – D). For activity D with duration 2, TF = 3 days and IndF = 3 days.

Explain total float and independent float.

Total float

Total float (TF) is the maximum time by which an activity can be delayed without delaying the completion of the project. It is shared with the other activities on the same path.

TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT

Independent float

Independent float (IndF) is the time available for an activity when its predecessors finish at their latest time and its successors start at their earliest time. Using it affects no other activity, so it is the safest float.

IndF=max⁡(0, min⁡(ESTsucc)−max⁡(LFTpred)−D)IndF = \max\left(0,\ \min(EST_{succ}) - \max(LFT_{pred}) - D\right)

Example

Example network (days): A = 4 and B = 3 are start activities; C = 5 and D = 2 follow A; E = 3 follows C and D; F = 4 follows B. Project duration = 12 days.

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A404040000
B303585050
C549490000
D246793303
E39129120000
F4378125500

Activity D: TF=9−6=3TF = 9 - 6 = 3 days. Its predecessor A is critical (LFT = 4) and its successor E starts at 9, so IndF=9−4−2=3IndF = 9 - 4 - 2 = 3 days: D can move 3 days without affecting any other activity. Activity B: TF=8−3=5TF = 8 - 3 = 5 days but IndF=3−0−3=0IndF = 3 - 0 - 3 = 0, since F starts as soon as B finishes; the float is shared with F.

Total floatIndependent float
EffectMay reduce float of other activitiesDoes not affect any other activity
ValueLarger or equalSmaller or equal (never more than TF)
BasisLFT - EFTSuccessor EST - predecessor LFT - D

✓ Answer checked by Claude Opus 5.5 (high effort)

All Project Engineering chapter 3 questions →