- 2074 Chaitra · 4 marks
Total float and independent float
Short answer
Total float is the maximum delay allowed without delaying project completion (LST–EST). Independent float is the delay possible when all predecessors finish as late as possible and successors start as early as possible, calculated as max(0, min(EST of successors) – max(LFT of predecessors) – D). For activity D with duration 2, TF = 3 days and IndF = 3 days.
Explain total float and independent float.
Total float
Total float (TF) is the maximum time by which an activity can be delayed without delaying the completion of the project. It is shared with the other activities on the same path.
Independent float
Independent float (IndF) is the time available for an activity when its predecessors finish at their latest time and its successors start at their earliest time. Using it affects no other activity, so it is the safest float.
Example
Example network (days): A = 4 and B = 3 are start activities; C = 5 and D = 2 follow A; E = 3 follows C and D; F = 4 follows B. Project duration = 12 days.
| Activity | D | EST | EFT | LST | LFT | TF | FF | Int.F | Ind.F |
|---|---|---|---|---|---|---|---|---|---|
| A | 4 | 0 | 4 | 0 | 4 | 0 | 0 | 0 | 0 |
| B | 3 | 0 | 3 | 5 | 8 | 5 | 0 | 5 | 0 |
| C | 5 | 4 | 9 | 4 | 9 | 0 | 0 | 0 | 0 |
| D | 2 | 4 | 6 | 7 | 9 | 3 | 3 | 0 | 3 |
| E | 3 | 9 | 12 | 9 | 12 | 0 | 0 | 0 | 0 |
| F | 4 | 3 | 7 | 8 | 12 | 5 | 5 | 0 | 0 |
Activity D: days. Its predecessor A is critical (LFT = 4) and its successor E starts at 9, so days: D can move 3 days without affecting any other activity. Activity B: days but , since F starts as soon as B finishes; the float is shared with F.
| Total float | Independent float | |
|---|---|---|
| Effect | May reduce float of other activities | Does not affect any other activity |
| Value | Larger or equal | Smaller or equal (never more than TF) |
| Basis | LFT - EFT | Successor EST - predecessor LFT - D |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Dummy activity and float definitions · Project Engineering, chapter 3
- CPM network, 9 activities with successors · Project Engineering, chapter 3
- CPM network, 10 activities with successors · Project Engineering, chapter 3
- CPM network, 10 activities (A=4 to J=9) · Project Engineering, chapter 3
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3