Short answer

A project proposal outlines the idea, objectives, plan, cost, and benefits to gain approval. The technical proposal describes the methodology and team, while the financial proposal states the price. For construction, the client awards the lowest evaluated responsive bid; for consulting, QCBS combines technical (80%) and financial (20%) scores to select the highest combined score.

Define project proposal. Differentiate between technical proposal and financial proposal. How does the client evaluate the proposal for awarding the contract of construction and consulting works?

Project proposal

A project proposal is a written document that presents the idea, objectives, plan, cost and expected benefits of a proposed project to convince the client, funder or approving authority to accept and finance it.

Technical vs financial proposal

BasisTechnical proposalFinancial proposal
ContentUnderstanding of the work, methodology, work plan, team, equipment, experiencePrices, rates, bill of quantities, total cost, payment terms
Question answeredHow will the work be done and can the bidder do it?How much will it cost?
EvaluationScored on technical meritCompared on price
SubmissionUsually sealed separately and opened firstOpened only for bidders who pass the technical stage
Prepared byEngineers and expertsEstimators and accountants

Evaluation by the client

In Nepal, evaluation follows the Public Procurement Act, 2063 and the Public Procurement Rules, 2064.

Construction works (bids):

  1. Opening and preliminary examination: completeness, bid security, signed forms.
  2. Technical (qualification and responsiveness) evaluation against criteria such as experience, financial capacity, equipment and personnel, on a pass or fail basis.
  3. Financial evaluation of the bids that pass: arithmetic correction and comparison of prices.
  4. Award to the lowest evaluated substantially responsive bidder.

Consulting services (proposals):

  1. The technical proposal is opened first and scored on the firm's experience, methodology and work plan, and key staff (points are given, with a minimum technical pass mark).
  2. The financial proposals of technically qualified consultants are then opened.
  3. A combined score is worked out under Quality and Cost Based Selection (QCBS), for example with 80% weight to technical and 20% to financial. The consultant with the highest combined score is invited for negotiation and contract. Other methods include least cost selection and quality based selection.