Quality; QA vs QC; site engineer steps

Short answer

Quality is meeting requirements. QA prevents defects via processes; QC detects them via testing. A site engineer controls quality by studying drawings, preparing a quality plan, approving materials, inspecting formwork/reinforcement, supervising concreting, testing (slump, cubes), documenting, correcting defects, and coordinating.

Define quality. Differentiate between quality assurance and quality control. As a site engineer what steps would you follow to control quality?

Quality

Quality is the degree to which a set of inherent characteristics of a product or service meets the requirements: the specified standards, the client's needs and fitness for use. In construction, quality means the work follows the drawings, specifications and codes and is safe, durable and functional.

Quality assurance and quality control

BasisQuality assurance (QA)Quality control (QC)
MeaningPlanned system of activities to give confidence that quality requirements will be metOperational techniques to check that the work meets the requirement
FocusProcess; prevents defectsProduct; detects defects
NatureProactiveReactive
WhenBefore and during the workDuring and after the work
ResponsibilityWhole organisation and managementSite and testing team
ToolsQuality plan, audits, procedures, trainingInspection, tests (cube test, slump, compaction), checklists
ExampleSetting the method statement and approving materialsTesting concrete cubes at 7 and 28 days

Steps by a site engineer to control quality

  1. Study the drawings, specifications, BOQ and codes before starting; clarify doubts with the designer.
  2. Prepare a quality plan and method statements, with checklists for each activity.
  3. Approve materials: check source, samples and test reports of cement, steel, aggregate and sand before use; reject bad materials.
  4. Check setting out and levels, formwork, reinforcement (size, spacing, cover) before concreting.
  5. Supervise the work: control mix proportion, water-cement ratio, mixing, placing, compaction and curing.
  6. Test: slump test, cube test, density test, etc., on the frequency in the specification; keep records.
  7. Check workmanship with trained and skilled workers and keep the work as per the approved method.
  8. Document daily reports, inspection records and photographs; issue non-conformance reports.
  9. Correct defects at once (rework or repair) and find the cause so that it does not happen again.
  10. Coordinate with the client, consultant and contractor and hold regular quality meetings.