- 2073 Bhadra · 4 marks
Detailed specification of stone masonry in 1:6 mortar
Short answer
Stone mansonry with hard durable stone in1:6 cment sand mortar. Stones laid on full bed with filled jointes; through stones at1.5–2 m intervals. Joint thickness ≤20 mm. Curing7 days. Measured in m³.
Write down the specification for stone masonry work in 1:6 mortar.
Detailed specification: stone masonry in cement sand mortar 1:6
Scope: Constructing random rubble/coursed rubble stone masonry in cement sand mortar 1:6 in foundations and walls as per drawings.
Materials
- Stone: hard, sound, durable, free from cracks, weathering, soft veins and dirt; locally available (e.g. granite, limestone or river boulders), compressive strength not less than 5 N/mm² and water absorption below 5%. Stones are generally not less than 150 mm thick, with a length not more than three times the height. Face stones are dressed to the line; stones are cleaned and wetted before use.
- Mortar: cement sand 1:6 by volume, with clean coarse sand, fresh OPC/PPC and potable water, mixed uniformly and used within 30 minutes.
Workmanship
- The foundation bed is cleaned and levelled; the first course is laid with the largest stones.
- Stones are laid on their natural bed in a full bed of mortar; joints are fully filled, and spalls (chips) are used to fill the gaps so that no voids remain. The hearting is packed with smaller stones and mortar.
- The stones are laid with good bond, and vertical joints are staggered. Bond (through) stones are provided at 1.5–2 m intervals in each course. In walls up to 600 mm thick, a through stone runs across the full thickness; in thicker walls, a set of two or more bond stones overlapping each other by at least 150 mm is used.
- Joints are not more than 20 mm thick for rubble work; corners and jambs are built of selected, dressed stones.
- The work is raised evenly, by not more than 1 m per day, and brought to level at about 600 mm height intervals.
- The face is kept plumb, checked with a plumb bob and line.
- Faces to be plastered or pointed are raked 15–20 mm deep while the mortar is green.
Curing: Wet curing for at least 7 days, with protection from rain and sun.
Measurement and payment: in cubic metres of finished masonry, with no deduction for openings below 0.1 m². The rate includes materials, scaffolding, curing and all labour.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Detailed specification of brick work in 1:4 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of brick work in 1:6 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of cement sand mortar 1:4 · Construction Management, chapter 12 · asked 2×
- Detailed specification of cement sand mortar 1:6 · Construction Management, chapter 12 · asked 2×
- Types of specification: general and detailed · Construction Management, chapter 12 · asked 7×
- Detailed specification of RCC M20 column · Construction Management, chapter 12
- Materials for 5 m³ stone masonry 1:6 · Estimating and Costing, chapter 4
- Types of stone masonry · Building Technology, chapter 3 · asked 5×
- Types of stone masonry and characteristics · Design of Timber and Masonry Structures, chapter 4
- Masonry work, materials for 20 cum brickwork · Building Technology, chapter 3