Delay and cost overrun due to management failure

Short answer

Yes, delay and cost overrun are largely due to management failures: poor planning, late design, delayed decisions and payments, weak supervision and coordination. Construction is also affected by physical, economic, political, social, technological and organisational environments.

The construction projects face delay and cost over-run mainly due to management failures. Do you agree with this statement? Explain in brief. Discuss on different construction environment which affects a construction project.

Yes, in most cases I agree. Studies of Nepali and international projects show that delay and cost overrun are caused mostly by weak management rather than by technical difficulty. Typical management failures:

  • Poor planning and scheduling; unrealistic programme, no resource-loaded schedule.
  • Incomplete or late design and drawings, frequent variations.
  • Delays in client decisions, land acquisition, approvals and payments.
  • Poor contractor selection (lowest bid without capacity) and weak site supervision.
  • Shortage of labour, materials or equipment; late procurement.
  • Weak monitoring and control, no corrective action on early warnings.
  • Poor coordination among the client, consultant and contractors, and cash-flow problems.
  • Weak risk management.

Some delays are external (strikes, weather, landslides, fuel shortage), but better management reduces their effect.

Construction environments affecting a project

EnvironmentExamples
Physical / naturalTerrain, climate, monsoon, floods, earthquake, geology
EconomicInflation, price of materials, interest rate, availability of finance
Political / legalGovernment policy, laws, permits, strikes, instability
Social / culturalCommunity acceptance, local labour, compensation, resettlement
TechnologicalAvailable methods, equipment, skilled labour
OrganisationalClient, contractor, consultant capacity and relations
Physical site conditionsAccess, utilities, storage space, neighbouring structures