Hydro versus thermal: techno-economic and environmental

Short answer

Hydro has 85-92% efficiency, fast start, excellent load following, zero fuel cost, low O&M, long life, but high capital and long construction. Thermal has 30-40% efficiency, slow start, firm output, high fuel and O&M cost, shorter life, and causes air and thermal pollution. Hydro is clean but capital intensive.

Compare the operational characteristics of the hydroelectric power plant and thermal power plant considering factors such as techno-economic, environmental and so on.

A hydroelectric plant converts the potential energy of stored or flowing water into electricity, while a thermal plant burns fuel to make steam that drives a turbine.

Technical comparison

AspectHydroelectric plantThermal plant
Energy sourceWater; renewableCoal, oil, gas; exhaustible
Efficiency85–92%30–40%
Starting timeFew minutesSeveral hours
Load followingExcellent; peak loadPoor; base load
Operating rangeWideNarrow (above about 40–50%)
ReliabilitySeasonal (RoR), firm with storageFirm if fuel is available
LocationFixed by river and head; remoteFlexible, near load
TransmissionLong linesShort lines
AuxiliariesFewMany (boiler, coal and ash handling, cooling)
Life50–100 years25–30 years

Economic comparison

AspectHydroelectric plantThermal plant
Capital costHigh (dam, tunnel, powerhouse)Lower
Construction timeLong (4–10 years)Shorter (3–4 years)
Fuel costNilHigh; most of running cost
O&M costLow; few staffHigh; many staff
Cost per kWh over lifeLowHigh, rises with fuel price
RiskGeology, hydrology, sedimentFuel price and supply

Environmental and social comparison

AspectHydroelectric plantThermal plant
Air pollutionNone in operationCO₂, SO₂, NOx, particulates
WasteNoneFly ash, bottom ash
Water impactChanges river flow, fish migration, sedimentThermal pollution of cooling water
LandSubmergence by reservoir; resettlementLand for plant, coal yard, ash pond
Other benefitsIrrigation, flood control, drinking water, tourismEmployment in mining
ClimateSmall GHG (some methane from reservoirs)Large GHG emission

Remarks

Hydro has high initial cost but very low running cost, long life and clean operation; thermal is cheaper and quicker to build but expensive to run and polluting. For Nepal, with large hydro potential and no fossil fuel, hydro is the main option, with thermal only as standby.