- Asked 2/21
- 2077 Chaitra · 8 marks
- 2075 Bhadra · 6 marks
Schematic of a PROR hydropower plant
Short answer
A PROR plant uses a diversion dam with pondage for a few hours of storage, allowing peaking operation. Key components: intake with trash rack, desander, headrace tunnel, surge tank, penstock, powerhouse with turbine and generator, tailrace, transformer, and switchyard.
Draw a schematic diagram of PROR type hydropower plant showing all the necessary components and describe each of them.
A Peaking / Pondage Run-of-River (PROR) plant is a run-of-river scheme with a small daily storage (pondage) behind the diversion dam. Water is stored during low-demand hours and used to generate full power during peak hours. It combines the low cost of ROR with peaking capability.
Schematic
River ->[ Diversion dam + radial gates ]-> Spillway
| Pondage (few hours storage) |
+------------------------------+
| |
[Intake + trash rack] Riparian
| release
[Gravel trap / Desander]
|
Headrace tunnel -------> [Surge tank]
|
Penstock / shaft
|
+----------[ Powerhouse ]----------+
| MIV -> Turbine -> Generator |
| Governor, Exciter, Control room |
+----------------------------------+
| |
Tailrace Transformer
| |
River Switchyard -> Line
Description of components
- Diversion dam/weir: Concrete or rockfill structure across the river that raises the water level and creates the pondage. Gates control water level.
- Pondage: Small reservoir that stores water for a few hours (e.g. 4–6 h) so that the plant can run at full capacity during the evening peak.
- Spillway and undersluice: Spillway passes flood flow safely; undersluice flushes sediment from the pondage.
- Intake: Admits the design discharge into the water conductor; has a trash rack to stop debris and gates for closing.
- Desander (settling basin): Settles sand and silt so that turbine runners are not eroded.
- Headrace tunnel/canal: Conveys water from intake to surge tank at a gentle slope.
- Surge tank: Vertical shaft that absorbs water hammer when turbines close suddenly and supplies water when load increases.
- Penstock/pressure shaft: Steel or lined pipe that carries water under high pressure to the turbines; branches into each unit.
- Powerhouse: Building housing main inlet valves, turbines (Francis/Pelton depending on head), generators, governors, excitation, control and protection equipment, cranes and auxiliaries.
- Turbine: Converts the energy of water into mechanical rotation.
- Generator: Synchronous machine converting mechanical power to electrical; excitation and AVR control voltage.
- Tailrace: Channel or tunnel that returns water to the river.
- Transformer and switchyard: Step up the generator voltage (e.g. 11 kV to 132 kV) and connect the plant to the transmission line with breakers, isolators and arresters.
- Auxiliary systems: Station service transformer, DC battery, diesel generator for black start, cooling water, fire protection, SCADA.
Examples in Nepal: Kaligandaki A (144 MW), Middle Marsyangdi (70 MW), Upper Tamakoshi (456 MW) are PROR plants.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Reservoir type hydropower plant schematic · Power Plant Design, chapter 3
- PROR environmental impact and schematic · Power Plant Design, chapter 3
- ROR versus PROR hydropower plants · Power Plant Design, chapter 3
- Hydropower plant components and functions · Power Plant Design, chapter 3 · asked 2×
- Sketch of a medium head PROR plant · Power Plant Design, chapter 3 · asked 2×
- High dam hydropower project components · Power Plant Design, chapter 3
- Combined plant components and T-s diagram · Power Plant Equipment, chapter 8 · asked 4×
- Schematic diagram of rural gravity scheme · Water Supply Engineering, chapter 1 · asked 5×
- Layout of hydropower scheme components · Hydro Power, chapter 5
- Steady state operation of hydropower plant · Power Plant Equipment, chapter 1