Chapter 3 · 8 hours
Hydro Power Plant Design
IOE past exam questions
Past questions and answers
32 questions set from this chapter, 11 of them more than once. Most asked first.
- Asked 4 times
- 2081 Shrawan · 6 marks
- 2079 Shrawan · 6 marks
- 2078 Kartik · 6 marks
- 2075 Bhadra · 4 marks
Assume that you have identified a suitable hydropower site for electricity generation. Discuss the steps/stages how would you proceed to own, build that project and finally sell power to Nepal Electricity Authority.
Answer
To develop a hydropower project in Nepal as an Independent Power Producer (IPP), one must obtain licences from the Department of Electricity Development (DoED) under the Electricity Act 2049 (1992) and Electricity Regulation 2050, sign a Power Purchase Agreement (PPA) with NEA, and then finance, build and operate the plant.
Steps / stages
- Site identification and desk study: Check maps, hydrology data and existing licences to confirm the site is free.
- Company registration: Register a company at the Office of the Company Registrar (needed to hold licences).
- Survey licence: Apply to DoED for a survey licence (valid up to about 5 years) with a pre-feasibility report and fee. For large projects (above 200 MW) the Investment Board Nepal (IBN) is the approving body.
- Feasibility study: Hydrological, topographical, geological and sediment studies; optimise design discharge (e.g. Q40–Q45), head, installed capacity, layout; cost estimate and financial analysis.
- Environmental study: IEE or EIA as per the Environment Protection Act 2076 and Rules, with public hearing and approval from the concerned ministry.
- Grid connection: Apply to NEA for a connection agreement; NEA does a grid impact/connection study and fixes the substation and voltage of connection.
- Power Purchase Agreement (PPA): Sign the PPA with NEA (Power Trade Department) at the posted rates (separate wet- and dry-season rates per kWh with limited annual escalation), fixing the required commercial operation date (RCOD).
- Generation licence: Apply to DoED with the feasibility report, EIA/IEE approval, PPA and connection agreement; the licence is normally for up to 35 years, after which the project is handed to the government.
- Financial closure: Arrange debt (banks, typically 70%) and equity (promoters, about 30%); later issue shares to the public and to project-affected locals (IPO).
- Land and permits: Land acquisition, forest clearance, permits for explosives, roads.
- Construction: Tendering and contracts for civil, hydro-mechanical and electro-mechanical works and the transmission line to the NEA substation.
- Testing and commissioning: Wet tests, synchronisation and protection tests witnessed by NEA.
- Commercial operation (COD): Start selling energy to NEA as per the PPA; pay royalty to the government (shared with provinces and local levels).
- Operation and maintenance for the licence period, then transfer.
Site -> Survey licence -> Feasibility + EIA
-> Connection agreement -> PPA (NEA)
-> Generation licence -> Financial closure
-> Construction -> COD -> Sell to NEA
- Asked 2 times
- 2082 Shrawan · 8 marks
- 2074 Magh · 3+5 marks
List down the various components of a medium head relatively higher discharge hydropower plant and mention their functions.
Answer
A medium head (about 30–300 m), relatively high discharge plant is usually a run-of-river or pondage run-of-river scheme with a diversion weir/dam, a long large-diameter water conductor, a surge tank and a powerhouse with Francis turbines.
Layout
Reservoir/headpond
____ Intake
| |__[TR]___ Headrace tunnel _________
|Dam/| (gate) \ Surge
|weir| \ tank
|____|--> Spillway Desander [ST]
| |
+-> Riparian release Penstock |
\______|
\
[Powerhouse]
Turbine+Gen
|
Tailrace -> River
|
Switchyard -> Grid
Components and functions
A. Civil components
- Diversion weir / dam: Raises the water level and diverts flow to the intake; may create a small pondage.
- Spillway and gates: Pass flood water safely; undersluice gates flush sediment near the intake.
- Intake with trash rack: Draws the design discharge into the conveyance; the trash rack stops floating debris; gates control flow.
- Gravel trap and settling basin (desander): Remove sand and silt (particles above about 0.2 mm) to protect the turbines from abrasion — very important in Himalayan rivers.
- Headrace tunnel / canal: Carries the large discharge at a mild slope to the forebay/surge tank with low head loss.
- Surge tank (or forebay): Absorbs pressure rise (water hammer) during load rejection and supplies water during sudden load increase; protects the tunnel.
- Penstock / pressure shaft: Carries water under pressure from the surge tank to the turbines; ends in a manifold for each unit, with a valve.
- Powerhouse: Houses turbines, generators, control and auxiliary systems (surface or underground).
- Tailrace: Returns water from the draft tube to the river.
B. Mechanical components 10. Main inlet valve (butterfly/spherical): Isolates each turbine. 11. Francis turbine (suitable for medium head, high flow) with spiral casing, guide vanes and draft tube to recover kinetic energy. 12. Governor: Controls guide-vane opening to keep speed/frequency constant. 13. Cooling water, drainage, dewatering and EOT crane.
C. Electrical components 14. Synchronous generator with excitation system and AVR. 15. Generator circuit breaker, generator bus/leads, CTs and PTs. 16. Step-up (generator) transformer: Raises voltage (e.g. 11 kV to 132 kV). 17. Switchyard: Breakers, isolators, busbars, lightning arresters for connection to the transmission line. 18. Control, protection and SCADA; station auxiliary transformer; DC battery system; diesel generator for black start; earthing system.
- Asked 2 times
- 2081 Chaitra · 8 marks
- 2073 Bhadra · 4+4 marks
Make a sketch to show various components of medium head and relatively large discharge, medium size Pondage Run of River (PRoR) hydropower plant. Also, mention the functions of each component.
Answer
A Pondage Run-of-River (PRoR) plant diverts river water through a water conductor like an ROR plant, but stores water in a pondage (daily storage) during off-peak hours so that the plant can run at full output during the peak hours (typically 4–6 hours in the evening). For medium head (about 50–300 m) and relatively large discharge, Francis turbines are used.
Sketch
River
|
======[Dam/Weir + Gates]======
| Pondage (daily storage) |---> Spillway
|_____________________________|
| |
| +--> Riparian release
[Intake + trash rack]
|
[Desander / settling basin]
|
Headrace tunnel ==============\
[Surge tank]
|
Penstock |
\|
[Powerhouse: MIV, Francis,
Generator, Governor, AVR]
| |
Tailrace GSU transformer
| |
River Switchyard -> Grid
Components and functions
| Component | Function |
|---|---|
| Diversion dam / weir with gates | Raises water level, diverts water, forms pondage |
| Pondage | Stores off-peak inflow for daily peaking operation |
| Spillway, undersluice | Passes floods, flushes sediment |
| Intake with trash rack | Admits design flow; stops debris |
| Desander (settling basin) | Removes fine sediment to protect turbines |
| Headrace tunnel | Conveys large discharge to the surge tank with low loss |
| Surge tank | Controls water hammer; supplies flow during load change |
| Penstock / pressure shaft | Carries water under pressure to turbines |
| Main inlet valve | Isolates each unit |
| Francis turbine + draft tube | Converts hydraulic energy to mechanical; draft tube recovers energy |
| Governor | Controls speed/frequency and load |
| Synchronous generator + excitation/AVR | Generates power; controls voltage and reactive power |
| Generator CB, GSU transformer | Switching and step-up to transmission voltage |
| Switchyard | Connects plant to grid; isolation and protection |
| Tailrace | Returns water to the river |
| Auxiliaries | Station transformer, DC system, diesel generator (black start), cooling, crane, SCADA |
Why PRoR
It supplies the evening peak, which is valuable in Nepal, especially in the dry season (e.g. Kaligandaki A, Middle Marsyangdi are peaking ROR plants).
- Asked 2 times
- 2077 Chaitra · 8 marks
- 2075 Bhadra · 6 marks
Draw a schematic diagram of PROR type hydropower plant showing all the necessary components and describe each of them.
Answer
A Peaking / Pondage Run-of-River (PROR) plant is a run-of-river scheme with a small daily storage (pondage) behind the diversion dam. Water is stored during low-demand hours and used to generate full power during peak hours. It combines the low cost of ROR with peaking capability.
Schematic
River ->[ Diversion dam + radial gates ]-> Spillway
| Pondage (few hours storage) |
+------------------------------+
| |
[Intake + trash rack] Riparian
| release
[Gravel trap / Desander]
|
Headrace tunnel -------> [Surge tank]
|
Penstock / shaft
|
+----------[ Powerhouse ]----------+
| MIV -> Turbine -> Generator |
| Governor, Exciter, Control room |
+----------------------------------+
| |
Tailrace Transformer
| |
River Switchyard -> Line
Description of components
- Diversion dam/weir: Concrete or rockfill structure across the river that raises the water level and creates the pondage. Gates control water level.
- Pondage: Small reservoir that stores water for a few hours (e.g. 4–6 h) so that the plant can run at full capacity during the evening peak.
- Spillway and undersluice: Spillway passes flood flow safely; undersluice flushes sediment from the pondage.
- Intake: Admits the design discharge into the water conductor; has a trash rack to stop debris and gates for closing.
- Desander (settling basin): Settles sand and silt so that turbine runners are not eroded.
- Headrace tunnel/canal: Conveys water from intake to surge tank at a gentle slope.
- Surge tank: Vertical shaft that absorbs water hammer when turbines close suddenly and supplies water when load increases.
- Penstock/pressure shaft: Steel or lined pipe that carries water under high pressure to the turbines; branches into each unit.
- Powerhouse: Building housing main inlet valves, turbines (Francis/Pelton depending on head), generators, governors, excitation, control and protection equipment, cranes and auxiliaries.
- Turbine: Converts the energy of water into mechanical rotation.
- Generator: Synchronous machine converting mechanical power to electrical; excitation and AVR control voltage.
- Tailrace: Channel or tunnel that returns water to the river.
- Transformer and switchyard: Step up the generator voltage (e.g. 11 kV to 132 kV) and connect the plant to the transmission line with breakers, isolators and arresters.
- Auxiliary systems: Station service transformer, DC battery, diesel generator for black start, cooling water, fire protection, SCADA.
Examples in Nepal: Kaligandaki A (144 MW), Middle Marsyangdi (70 MW), Upper Tamakoshi (456 MW) are PROR plants.
- Asked 2 times
- 2074 Bhadra · 8 marks
- 2071 Magh · 3+5 marks
Discuss the functions and importance of various components of hydropower plant with proper schematic diagram of ROR hydropower plant.
Answer
A run-of-river (ROR) plant diverts part of the river flow through a waterway to a powerhouse without any significant storage, so its output follows the natural river flow. Each component has one job: take water in, clean it, carry it with little head loss, convert its energy, and return it to the river.
Schematic of an ROR plant
River
==|== Diversion weir + intake (trash rack, gate)
|
[Gravel trap] -> [Desander / settling basin]
|
| Headrace canal / tunnel (low slope)
v
[Forebay] or [Surge tank]
|
| Penstock (steel pipe, steep)
v
[Valve]-[Turbine]-[Generator] POWERHOUSE
| |
Tailrace GSU transformer -> Switchyard
| -> Transmission line
v
Back to river
Components, functions and importance
| Component | Function | Importance |
|---|---|---|
| Diversion weir / barrage | Raises water level and diverts flow into intake | Gives a steady water level at intake |
| Intake with trash rack and gate | Admits the design discharge, stops floating debris | Protects the waterway; gate closes for floods and maintenance |
| Gravel trap | Removes coarse gravel just after intake | Prevents canal choking |
| Desander (settling basin) | Settles fine sediment (usually particles above 0.2 mm) | Protects turbine runners from abrasion, very important in Himalayan rivers |
| Headrace canal / tunnel | Carries water at low slope to the forebay or surge tank | Most of the head is gained here, so head loss must be small |
| Forebay (canal system) | Small pond before the penstock; final settling and spill | Provides submergence and absorbs small load changes |
| Surge tank (tunnel system) | Open shaft at end of pressure tunnel | Absorbs water hammer and supplies water on sudden load increase |
| Penstock | Pressure pipe from forebay/surge tank to turbine | Converts elevation to pressure head; designed for water hammer |
| Main inlet valve | Butterfly or spherical valve before turbine | Isolates the turbine for shutdown and emergency |
| Turbine | Converts hydraulic energy to mechanical energy | Type chosen from head and discharge |
| Generator | Converts mechanical energy to electrical energy | Synchronous machine with excitation and governor |
| Governor and excitation | Control speed (frequency) and voltage | Keep the unit stable and in step with the grid |
| Transformer and switchyard | Step up voltage, switching and protection | Connect plant to the grid |
| Tailrace | Returns water to the river | Must avoid backwater that reduces net head |
Key points
- ROR plants are cheap and have small environmental impact, but output drops sharply in the dry season.
- Because Nepalese rivers carry heavy sediment, the desander and good intake design decide the life of the turbines.
- A riparian release (environmental flow) is always let past the weir for downstream life.
- Asked 2 times
- 2071 Bhadra · 2+6 marks
- 2070 Bhadra · 3+5 marks
Discuss the various components of hydropower plant? Also mention their functions.
Answer
A hydropower plant converts the potential energy of water stored at a height into electrical energy. Its components fall into three groups: civil (to collect and carry water), mechanical (to convert water energy to shaft power) and electrical (to generate and deliver power).
Reservoir/River
| Dam or weir + intake
v
Headrace (canal/tunnel) -> Surge tank/forebay
v
Penstock -> Turbine -> Generator -> Transformer -> Grid
|
Draft tube -> Tailrace -> River
Civil components
- Dam or diversion weir: creates head and/or storage and diverts water into the intake.
- Intake: entry structure with trash rack and gates; controls flow and keeps out debris.
- Gravel trap and desander: remove coarse and fine sediment to protect the turbines.
- Headrace canal or tunnel: carries water to the forebay or surge tank with minimum head loss.
- Forebay / surge tank: forebay is a small pond feeding the penstock; surge tank absorbs water hammer pressure rise and supplies water on sudden load rise.
- Spillway: passes flood water safely over or around the dam.
- Powerhouse building: houses the units, cranes and control room.
- Tailrace: returns water to the river.
Mechanical components
- Penstock: steel pressure pipe carrying water to the turbine.
- Main inlet valve: butterfly (low/medium head) or spherical (high head) valve to isolate the turbine.
- Turbine: Pelton, Francis or Kaplan, converts hydraulic energy into rotating mechanical energy.
- Governor: controls wicket gates or needle to keep speed constant as load changes.
- Draft tube: (reaction turbines) recovers kinetic energy at runner exit and allows setting above tailwater.
- Auxiliaries: cooling water, oil pressure unit, compressed air, crane, drainage and dewatering.
Electrical components
- Generator: synchronous machine coupled to the turbine; produces power at e.g. 11 kV.
- Excitation system and AVR: supply DC to the rotor and control terminal voltage and reactive power.
- Generator circuit breaker and bus: switching and isolation of the unit.
- Generator step-up transformer: raises voltage (e.g. 11/132 kV) for transmission.
- Switchyard: breakers, isolators, CTs, PTs, lightning arresters and busbars.
- Station auxiliaries: station transformer, DC battery system, diesel generator for black start.
- Protection, control and SCADA: relays, metering and remote monitoring.
- Asked 2 times
- 2079 Jestha · 10 marks
- 2072 Asoj · 8 marks
Sketch a typical layout of a medium head hydroelectric power station fitted with Francis turbine. Briefly describe the main elements.
Answer
A medium head station (roughly 30–300 m head) normally uses a Francis turbine, a mixed-flow reaction turbine. Water reaches the turbine under pressure through a long waterway and penstock, and leaves through a draft tube to the tailrace.
Typical layout
Reservoir / pond
~~~~~~~~~~~~~~~~~~~~~
| Dam | Intake + trash rack
| |====================\ Headrace tunnel
|_______| \
[Surge tank]
|
| Penstock
|
Valve --> +-------v------+
| Spiral casing|
| Guide vanes |
| Francis |
| runner |---Generator
+------+-------+
| Draft tube
v
Tailrace --> River
Main elements
- Reservoir or pondage and dam: stores water and creates part of the head. A spillway passes floods.
- Intake with trash rack and gates: admits water and keeps out debris; gates allow the waterway to be dewatered.
- Headrace tunnel / pressure conduit: carries water to the surge tank with a gentle slope; it is often lined to reduce friction loss.
- Surge tank: an open vertical shaft at the end of the tunnel. When the turbine gates close suddenly, the rising water level in the tank absorbs the water hammer; when load increases, it supplies water until the tunnel flow speeds up. It keeps water hammer confined to the short penstock.
- Penstock: steel pipe from the surge tank to the powerhouse; designed for static head plus water hammer. Anchor blocks and expansion joints are provided.
- Main inlet valve: usually a butterfly valve at medium head; closes in emergency.
- Spiral (scroll) casing: distributes water evenly around the runner; its area decreases along the flow so the velocity stays uniform.
- Stay vanes and guide vanes (wicket gates): stay vanes support the casing; guide vanes, moved by the governor, control the flow and direct it onto the runner at the correct angle.
- Francis runner: water enters radially and leaves axially; both pressure and kinetic energy are converted into torque. Medium specific speed (about 60–300, metric, P in kW).
- Draft tube: a diverging tube from runner exit to tailwater. It recovers kinetic energy and creates suction head so the runner can be set above tailwater; its setting is limited by cavitation (Thoma's coefficient).
- Generator: vertical-shaft synchronous generator directly coupled to the runner; its speed is fixed by .
- Governor and excitation system: control speed (frequency) and voltage.
- Powerhouse: surface or underground; contains units, EOT crane, control room and auxiliaries.
- Tailrace: channel that returns water to the river.
- Transformer and switchyard: step up the voltage and connect to the transmission line.
Example
Kaligandaki "A" (144 MW, about 115 m net head) and Middle Marsyangdi (70 MW) in Nepal use vertical Francis units with this type of layout.
- Asked 2 times
- 2079 Shrawan · 4 marks
- 2077 Chaitra · 4 marks
What is scientific method of turbine selection?
Answer
The scientific method of turbine selection chooses the turbine type from the specific speed () that the site's head, discharge and unit speed demand, and then checks it against the head range, efficiency curve and cavitation limits, rather than choosing by habit.
Steps
- Find net head and design discharge per unit from the flow duration curve (e.g. ), after deducting riparian release and head losses.
- Find unit power:
- Choose synchronous speed for the generator: (e.g. 500, 600, 750, 1000 rpm at 50 Hz).
- Compute specific speed:
- Pick the turbine type whose range contains :
| Turbine | (metric, kW) | Usual head |
|---|---|---|
| Pelton | 10–35 per jet | 50–1300 m |
| Francis | 60–300 | 10–350 m |
| Kaplan / propeller | 300–1000 | 2–40 m |
- Check with the manufacturer's head–discharge application chart, part-load efficiency, and cavitation (Thoma's and setting level).
- Adjust number of units or speed if falls in an overlap zone, and compare cost.
- Asked 2 times
- 2081 Shrawan · 4 marks
- 2074 Bhadra · 5 marks
Mention major factors governing during appropriate turbine selection.
Answer
The turbine type is selected mainly from the head and discharge of the site, then refined by speed, efficiency and site conditions.
Major governing factors
- Net head: the most important factor. High head (above ~300 m) suits Pelton; medium head (30–300 m) Francis; low head (below ~40 m) Kaplan/propeller.
- Discharge and its variation: large discharge at low head favours Kaplan; small discharge at high head favours Pelton. A river with widely varying flow needs a turbine with a flat part-load efficiency curve.
- Specific speed: combines head, power and speed into one number that fixes the runner type.
- Rotational speed: higher speed means a smaller, cheaper generator, but is limited by cavitation and runaway speed.
- Part-load efficiency: Pelton and Kaplan keep high efficiency at part load; Francis efficiency falls quickly below about 40–50% load.
- Cavitation and setting level: reaction turbines must be set low enough (Thoma's ), which adds excavation cost.
- Sediment in water: silty Himalayan rivers wear Francis runners quickly; Pelton is easier to repair.
- Cost, size and transport: runner size, powerhouse size and access road limits.
- Overall efficiency and maintenance needs, and availability of spares and local expertise.
- Asked 2 times
- 2073 Bhadra · 6 marks
- 2071 Magh · 6 marks
How the 'specific speed' is defined for a turbine? Discuss its purpose.
Answer
Specific speed () of a turbine is the speed at which a geometrically similar model turbine would run if it produced 1 kW of power under a head of 1 m. It is a type number that describes the shape of the runner.
Derivation (outline)
For similar turbines, the jet/flow velocity varies as and the peripheral speed , so . Discharge and power . Substituting :
When kW and m, . Hence
with in rpm, in kW and in m.
Purpose
- Selection of turbine type: each type works best in a band of :
| Turbine | range (kW, m) |
|---|---|
| Pelton (single jet) | 10–35 |
| Pelton (multi jet) | 35–60 |
| Francis | 60–300 |
| Kaplan / propeller | 300–1000 |
- Comparison of turbines: turbines of different size are compared on one scale.
- Model testing: a model and prototype with the same are geometrically and dynamically similar, so model results can be scaled up.
- Fixing speed and unit size: for a given head and power, choosing fixes the rotational speed, and hence the generator poles and cost.
- Cavitation check: the Thoma critical rises with , so fixes how low the runner must be set.
Example: rpm, kW, m gives , which lies at the boundary of multi-jet Pelton and slow Francis, so both would be compared.
- Asked 2 times
- 2080 Chaitra · 4 marks
- 2078 Chaitra · 4 marks
What is flow duration curve? Also discuss about its applicability.
Answer
A flow duration curve (FDC) is a plot of river discharge against the percentage of time that discharge is equalled or exceeded. It is drawn by arranging recorded (daily or monthly) flows in descending order and plotting each flow against its exceedance probability, (m = rank, n = number of values).
Q (m3/s)
|\
| \
| \__
| \____
| \______
| \_______
+--------------------------> % time exceeded
0 45 65 95 100
Applicability
- Design discharge: the turbine flow is chosen at a set exceedance, e.g. – for ROR projects in Nepal.
- Installed capacity and energy: the area under the FDC (limited by the design flow) gives the energy available; it is used to compute annual energy and plant factor.
- Firm power: flow at 90–95% exceedance gives the firm (dependable) power.
- Number and size of units: the shape of the curve shows how long the plant will run at part load, so it guides unit sizing.
- Riparian release and water rights: low-flow end of the curve shows the minimum flow to release downstream.
- Comparison of sites: a flat curve means steady flow (good for ROR); a steep curve means highly variable flow needing storage.
- 2079 Shrawan · 8 marks
Stating environmental impact of P-ROR type hydro-power plant, draw a schematic diagram showing all the necessary components and describe each of them.
Answer
A peaking run-of-river (P-ROR) plant is an ROR plant with a small daily pondage, so that water collected during off-peak hours is used to run the plant at full capacity during the evening peak (typically 4–6 hours).
Environmental impacts of P-ROR
- Hydro-peaking downstream: flow below the tailrace rises and falls sharply every day; this disturbs fish, aquatic insects and people using the riverbank.
- Dewatered stretch: between the dam and tailrace only the riparian release flows, reducing habitat, fish migration and water for irrigation/water mills.
- Pondage submergence: a small area of land and forest is flooded; some houses or farmland may be affected.
- Sediment trapping and flushing: the pond traps sediment; periodic flushing releases very turbid water downstream.
- Construction impacts: spoil from tunnels, access roads, landslides, dust, noise and inflow of workers.
- Positive impacts: clean peaking energy that replaces diesel/thermal imports, local roads, jobs and electrification.
Mitigation: adequate riparian release (at least 10% of minimum monthly flow in Nepal), fish ladders, controlled flushing, re-afforestation and spoil management.
Schematic of a P-ROR plant
River
==|== Dam/weir with spillway + undersluice
|
Intake (trash rack, gate)
|
Gravel trap -> Desander
|
[ DAILY PONDAGE ] (stores off-peak flow)
|
Headrace tunnel
|
Surge tank
|
Penstock (+ valve house)
|
Powerhouse: Turbine-Generator-Transformer
| |
Tailrace -> River Switchyard -> Grid
Components
- Diversion dam/weir: raises water level; gated spillway passes floods; undersluice flushes sediment at the intake.
- Intake: trash rack and gates admit the design discharge.
- Gravel trap and desander: remove sediment (usually >0.2 mm) before water enters the pondage and tunnel.
- Daily pondage: a reservoir sized to store the inflow of off-peak hours so the plant can run at full output during peak hours. Its volume is about .
- Headrace tunnel: pressure tunnel carrying water to the surge tank.
- Surge tank: absorbs water hammer and meets sudden load rise.
- Penstock and valve house: steel pipe to the powerhouse with an emergency butterfly valve at the top.
- Powerhouse: turbines (Francis or Pelton depending on head), generators, governors, excitation, control and auxiliaries.
- Tailrace: returns water to the river; may include a re-regulating pond to reduce hydro-peaking.
- Switchyard and transmission line: step up and evacuate power to the grid.
- 2078 Kartik · 8 marks
Discuss major components of a Daily Pondage Run off the River type hydropower project with suitable schematic diagram.
Answer
A daily pondage run-of-river (PROR) project stores river water for a few hours each day in a small pond so the plant can generate more during the daily peak load. It has all ROR components plus the pondage.
Schematic
River ==|== Weir/dam + spillway + undersluice
|
Intake ---> Gravel trap ---> Desander
|
[ DAILY PONDAGE ]
|
Headrace tunnel/canal
|
Surge tank/forebay
|
Penstock
|
Valve -> Turbine -> Generator
| |
Tailrace Transformer
| |
River Switchyard
Major components
- Headworks: diversion weir or low dam to raise water level; gated spillway for floods; undersluice to flush sediment away from the intake.
- Intake: side or frontal intake with trash rack and gates to admit design discharge.
- Gravel trap: removes gravel and coarse sand near the intake.
- Desander (settling basin): long, slow-flow basin where fine sediment settles; flushed periodically. Essential in Nepal to protect turbines.
- Daily pondage: small reservoir (or enlarged desander/forebay) that stores the off-peak inflow. Storage needed peak hours. It lets a dry-season plant give full output for about 4–6 peak hours.
- Headrace tunnel or canal: carries water to the surge tank/forebay with small head loss.
- Surge tank (or forebay): absorbs pressure surges and supplies water during sudden load increase.
- Penstock: steel pressure pipe with anchor blocks; valve at the top for emergency closure.
- Powerhouse: turbine (Francis for medium head, Pelton for high head), generator, governor, excitation, cooling and control systems.
- Tailrace: returns water to the river.
- Electrical works: step-up transformer, switchyard and transmission line to the grid.
Advantages
Higher peak capacity and revenue than plain ROR, better match with Nepal's evening peak, and much smaller submergence than a storage project. Examples in Nepal: Kaligandaki "A", Middle Marsyangdi and Upper Tamakoshi are peaking ROR projects.
- 2078 Chaitra · 8 marks
Discuss major components of a Daily Pondage Run off the River type hydropower project with tentative head 150 m and discharge 10 m³/s per unit. Illustrate with suitable schematic diagram.
Answer
For a head of about 150 m and 10 m³/s per unit, the unit output is roughly
and the specific speed at 600 rpm is , which lies well inside the Francis range (60–300). So the project is a medium-head daily pondage run-of-river (PROR) scheme with vertical Francis units of roughly 12–13 MW each.
Schematic
River ==|== Diversion weir + gated spillway
|
Intake (trash rack, gates)
|
Gravel trap -> Desander (2 or more bays)
|
[ DAILY PONDAGE ] -- spillway/flushing
|
Headrace tunnel (pressurised)
|
Surge tank
|
Penstock (steel, ~150 m head)
|
Butterfly valve
|
Francis turbine + Generator (~13 MW)
| |
Draft tube Unit transformer
| |
Tailrace -> River Switchyard -> Grid
Major components
- Diversion weir and spillway: raise water level and pass monsoon floods; undersluice keeps the intake free of sediment.
- Intake: sized for total design discharge (10 m³/s × number of units) plus flushing water; trash rack and gates.
- Gravel trap and desander: remove particles larger than about 0.2 mm, as sediment at 150 m head quickly erodes Francis runners and guide vanes.
- Daily pondage: stores off-peak inflow; for example, to run a 10 m³/s unit for 5 peak hours when the dry-season inflow is only 5 m³/s, storage m³ is needed.
- Headrace tunnel: carries water under low pressure to the surge tank.
- Surge tank: absorbs water hammer when governor closes the wicket gates and supplies water on load increase.
- Penstock: about 150 m static head plus water hammer allowance (typically 20–30%), with anchor blocks and expansion joints.
- Main inlet valve: butterfly valve, suitable for medium head.
- Francis turbine: spiral casing, stay vanes, wicket gates, runner and draft tube; vertical shaft; runner set below tailwater as required by cavitation.
- Generator: vertical synchronous generator at 11 kV, e.g. about 15 MVA at 0.85 pf, with excitation system and governor.
- Tailrace: returns water to the river below the powerhouse.
- Electrical system: unit step-up transformer (11/132 kV), switchyard, station supply and diesel generator for black start.
- 2070 Magh · 8 marks
Compare the components, operation and characteristics of run of river (ROR) type hydropower plant with pondage run of river (PROR).
Answer
A run-of-river (ROR) plant uses the river flow as it comes, with no storage. A pondage run-of-river (PROR) plant adds a small pond that stores water for a few hours so the plant can follow the daily load and give more power at peak time.
| Aspect | ROR | PROR |
|---|---|---|
| Storage | None (only forebay) | Daily pondage, a few hours of storage |
| Headworks | Low weir | Weir or slightly higher dam to create pond |
| Extra component | — | Pondage with flushing arrangement |
| Operation | Base load; output follows river flow | Peaking; stores off-peak water, generates more at peak |
| Dry-season output | Low, nearly constant | Same energy, but concentrated into peak hours |
| Installed capacity | Based on design flow (e.g. ) | Can be higher than ROR for same river |
| Load following | Poor | Good, within the pond volume |
| Cost | Lowest | Higher (pond, larger dam, gates) |
| Environmental impact | Least; dewatered stretch only | Adds small submergence and hydro-peaking downstream |
| Sediment | Passes through after desander | Pond traps sediment, needs flushing |
| Value to grid | Energy only | Energy plus peaking capacity |
Components
Both have: weir/dam, intake, gravel trap, desander, headrace, forebay or surge tank, penstock, powerhouse, tailrace and switchyard. PROR adds the pondage (and its spillway and flushing gates) and usually has a pressure tunnel with surge tank.
Operation and characteristics
- ROR: turbine discharge equals river inflow minus riparian release; in the wet season it runs at full load and spills the excess, in the dry season it runs at part load.
- PROR: during the night the pond fills; in the 4–6 peak hours the plant runs at full load using inflow plus stored water. Total daily energy is about the same as ROR, but its value is higher because peak energy is scarce in Nepal.
- Examples: many small IPP plants in Nepal are ROR; Kaligandaki "A" and Middle Marsyangdi are PROR.
- 2080 Chaitra · 8 marks
Draw schematic diagram of a hydropower plant and explain the basic civil, mechanical and electrical components used.
Answer
A hydropower plant converts the potential energy of water into electricity. Its works are grouped into civil, mechanical and electrical components.
River/Reservoir
==|== Dam/weir [CIVIL]
| Intake, desander
| Headrace tunnel/canal
| Surge tank / forebay
v
Penstock -> Valve [MECH]
v
Turbine ---- Generator [MECH] [ELEC]
| Governor | Excitation
Draft tube v
| GCB -> GSU transformer
Tailrace v [ELEC]
v Switchyard -> Transmission line
River
Civil components
- Dam / diversion weir: raises water level, creates head or storage; includes spillway and undersluice.
- Intake: trash rack and gates admit design flow.
- Gravel trap and desander: remove sediment.
- Headrace canal or tunnel: conveys water with low head loss.
- Forebay or surge tank: provides a free water surface, absorbs water hammer.
- Powerhouse: building or cavern for units, crane and control room.
- Tailrace: returns water to the river.
- Access roads, anchor blocks and saddles for the penstock.
Mechanical components
- Penstock: steel pipe that delivers water under pressure.
- Main inlet valve: butterfly or spherical valve.
- Turbine: Pelton (high head), Francis (medium head), Kaplan (low head).
- Governor: controls flow to keep speed and frequency constant.
- Draft tube: recovers outlet energy of reaction turbines.
- Auxiliaries: cooling water, lubrication and oil pressure units, compressed air, EOT crane, dewatering and drainage pumps, fire fighting.
Electrical components
- Generator: synchronous, usually 11 kV.
- Excitation system and AVR: brushless or static; control voltage and reactive power.
- Generator circuit breaker and bus duct.
- Generator step-up transformer: e.g. 11/132 kV.
- Switchyard: circuit breakers, isolators, CTs, PTs, lightning arresters, busbars.
- Auxiliary supply: station transformer, DC battery and charger, diesel generator for black start.
- Protection, control, metering, SCADA and communication (PLCC/OPGW).
- Earthing system: grounding mat for powerhouse and switchyard.
- 2079 Chaitra · 8 marks
Draw a schematic diagram of reservoir type hydro-power plant and describe necessary civil, mechanical and electrical components.
Answer
A reservoir (storage) type hydropower plant has a high dam that stores water in a large reservoir, usually for seasonal use. Water stored in the wet season is released in the dry season, so the plant can supply firm and peaking power all year. Kulekhani-I (60 MW) is Nepal's main example.
Schematic
Reservoir (FSL) ~~~~~~~~~~~~
~~~~~~~~~~~~~~~ |\
~~~ storage ~~~ | \ High dam
~~~~~~~~~~~~~~~ | \ + spillway
Intake tower -->|===\=============\
(MOL) |____\ \ Headrace tunnel
[Surge tank]
|
| Penstock
v
Valve -> Turbine -> Generator
| |
Draft tube Transformer
| |
Tailrace Switchyard
v v
River Grid
Civil components
- Dam: concrete gravity, arch or rockfill dam that creates head and storage. Full supply level (FSL) and minimum operating level (MOL) define the live storage.
- Reservoir: stores water from the monsoon for the dry season; dead storage below MOL holds sediment.
- Spillway: gated or ungated, passes the design flood safely.
- Intake tower: draws water from various levels with trash rack and gates.
- Headrace tunnel: pressure tunnel to the surge tank.
- Surge tank: protects the tunnel from water hammer and supplies water on load rise.
- Diversion tunnel/cofferdam (during construction), bottom outlet for emptying and flushing.
- Powerhouse (surface or underground) and tailrace.
Mechanical components
- Penstock with anchor blocks; main inlet valve (butterfly or spherical).
- Turbine: Francis for medium head or Pelton for high head (Kulekhani uses Pelton).
- Governor: keeps frequency constant by controlling flow.
- Draft tube (reaction turbines), cooling water, oil and compressed air systems, EOT crane.
Electrical components
- Synchronous generator with excitation system and AVR.
- Generator circuit breaker and bus duct.
- Step-up transformer and switchyard (breakers, isolators, CT, PT, lightning arresters).
- Station service: station transformer, DC battery, diesel generator for black start.
- Protection, control and SCADA; earthing mat.
Features
Reservoir plants give firm power, peaking and frequency regulation, but have high cost, long construction time, resettlement and sedimentation problems.
- 2081 Shrawan · 6 marks
Discuss major components of a high dam type hydropower project with suitable schematic diagram.
Answer
A high dam type project uses a tall dam (usually above about 15 m, often 100 m or more) to create a large head and storage reservoir; the powerhouse is placed at the toe of the dam or at the end of a short waterway.
Reservoir ~~~~~~~~~~|\
~~~~~~~~~~~~~~~~~~~~~| \ High dam
Intake (trash rack)->|==\====\
| \ \ Penstock
|____\ \
Spillway [Powerhouse]
Turbine-Gen
| |
Tailrace Transformer
| |
River Switchyard
Major components
- High dam: concrete gravity, arch or rockfill/earthfill; creates head and storage. It must be safe against overturning, sliding and seepage.
- Reservoir: live storage between full supply level and minimum operating level; dead storage for sediment.
- Spillway and energy dissipator: pass floods safely and protect the riverbed below.
- Intake: at the dam face or in a tower, with trash rack and gates, placed above sediment level.
- Bottom outlet / sluice: to flush sediment and empty the reservoir.
- Penstock: short pressure pipe through or around the dam to the turbines (surge tank needed only if the waterway is long).
- Powerhouse: at the dam toe; contains turbines (usually Francis), generators, governors and auxiliaries.
- Tailrace: returns water to the river.
- Electrical works: step-up transformer, switchyard and transmission line.
Example: the proposed Budhigandaki (about 1200 MW) and Kulekhani reservoir in Nepal; worldwide, Three Gorges and Tehri.
Advantages and limitations
- Gives large head with a short waterway, firm power through the dry season, peaking capacity and flood control.
- Needs very high investment and long construction time, causes submergence and resettlement, and loses storage to sedimentation, which is serious in Himalayan rivers.
- 2072 Magh · 8 marks
Draw the schematic diagram of hydropower plant showing different structural components. State the role of surge tank in hydropower plant construction.
Answer
The structural (mainly civil) components of a hydropower plant collect, store, clean and carry water to the turbine and return it to the river.
Schematic
Reservoir/River
==|== Dam/weir + spillway
|
Intake (trash rack, gates)
|
Desander
|
Headrace tunnel ================\
|
[SURGE TANK]
|
Penstock
|
[POWERHOUSE: turbine,
generator]
|
Tailrace -> River
Structural components
- Dam or weir with spillway: creates head/storage and passes floods.
- Intake: admits water; trash rack keeps out debris.
- Gravel trap and desander: remove sediment.
- Headrace canal or tunnel: carries water at a gentle slope.
- Forebay or surge tank: free water surface at the head of the penstock.
- Penstock with anchor blocks and saddle supports.
- Powerhouse: foundation, superstructure, crane beams.
- Tailrace channel.
Role of surge tank
A surge tank is an open vertical shaft or chamber placed at the junction of the long low-pressure headrace tunnel and the steep penstock.
- Protects against water hammer: when load is rejected, the governor closes the gates quickly. The moving water column cannot stop instantly; without a surge tank the pressure rise would travel through the whole tunnel. The surge tank lets the water rise in it, so the high pressure is limited to the short penstock.
- Supplies water on load increase: when gates open suddenly, water is drawn from the tank until the slow tunnel flow speeds up, avoiding a drop in pressure (and vacuum) in the penstock.
- Reduces penstock and tunnel thickness: lower design pressure means cheaper tunnel lining.
- Improves governing: reduces the effective water inertia time constant , since only the penstock length counts, making speed regulation stable.
- Types: simple, restricted orifice, differential and chamber types.
- 2078 Kartik · 4+4 marks
What is scientific method of turbine selection? Mention major factors governing turbine during selection of appropriate turbine type.
Answer
Scientific method of turbine selection
Turbine selection by the scientific method is based on specific speed and the site's head–discharge data, checked against standard application charts.
- Find net head and design discharge per unit (e.g. from the FDC less riparian release).
- Find unit output .
- Choose a synchronous speed .
- Calculate
(N in rpm, P in kW, H in m). 5. Select the type from the range: Pelton 10–35 (single jet), Francis 60–300, Kaplan 300–1000. 6. Cross-check with the head range (Pelton 50–1300 m, Francis 10–350 m, Kaplan 2–40 m) and the manufacturer's – chart; check cavitation (Thoma's ) and part-load efficiency.
Major factors governing turbine selection
- Net head: primary factor; fixes the broad type.
- Discharge and its variation: low head–high flow suits Kaplan; high head–low flow suits Pelton.
- Specific speed and rotational speed: higher speed gives smaller generator but more cavitation risk.
- Part-load efficiency: Pelton and Kaplan have flat efficiency curves; Francis drops at low load.
- Cavitation and setting: reaction turbines need submergence, adding excavation cost.
- Sediment content: high silt erodes Francis runners; Pelton runners are easier to repair.
- Number of units and unit size, transport limits.
- Cost, maintenance and runaway speed.
Example
Net head 300 m, design flow 4 m³/s for one unit: MW. At 600 rpm, , which is in the multi-jet Pelton range; a 2-jet or 4-jet Pelton (or a slow Francis) would be compared on cost and part-load efficiency.
- 2072 Magh · 8 marks
What do you mean by discharge exceedance? Describe the criterion for selecting turbine in hydro-electric power plant.
Answer
Discharge exceedance
Discharge exceedance is the percentage of time a given river discharge is equalled or exceeded. It is read from the flow duration curve (FDC). For example, m³/s means the river flow is 10 m³/s or more for 45% of the time (about 164 days a year).
- Low exceedance (e.g. ) → large flow, available for a short time.
- High exceedance (e.g. ) → small but dependable (firm) flow.
- In Nepal, ROR projects are usually designed at about –; firm power is judged from –.
- Exceedance is found by ranking the recorded flows in descending order and computing for rank out of values.
- The choice of design exceedance is a trade-off: a lower exceedance gives more installed capacity and energy but a lower plant factor and higher cost per kW.
Q
|\
| \
| \___ Q45
| \_____ Q65
| \______ Q95
+---------------------> % exceedance
Criteria for selecting turbine
- Net head: Pelton for high head (50–1300 m), Francis for medium head (10–350 m), Kaplan/propeller for low head (2–40 m). Crossflow (Michell–Banki) and Turgo are used in small plants.
- Specific speed: ; Pelton 10–35, Francis 60–300, Kaplan 300–1000 (metric, kW).
- Discharge and its variation: if flow varies greatly, choose a turbine with good part-load efficiency (Pelton, Kaplan) or use several units.
- Part-load operation: Francis efficiency falls below about 40–50% load; Pelton remains efficient down to 20%.
- Rotational speed: higher speed gives smaller generator; limited by cavitation and runaway speed.
- Cavitation: Thoma's coefficient fixes the setting below tailwater for reaction turbines.
- Sediment and abrasion: important for Himalayan rivers.
- Cost, efficiency, maintenance and local experience.
Example
For a site with m and m³/s split into two units of 3 m³/s, unit power MW. At 750 rpm, , at the boundary of multi-jet Pelton and slow Francis; the Pelton is preferred if the river is silty or long part-load running is expected.
- 2072 Asoj · 8 marks
Discuss the effect of the following factors in selecting of a turbine for a hydroelectric plant? (i) head (ii) speed and specific speed (iii) part load operation.
Answer
Turbine selection depends mainly on head, speed/specific speed and the expected part-load operation.
(i) Head
Head is the first and most important factor because it decides the velocity of water.
| Head range | Suitable turbine |
|---|---|
| High (above ~300 m, up to 1300 m) | Pelton (impulse) |
| Medium (30–300 m) | Francis (reaction) |
| Low (2–40 m) | Kaplan / propeller |
| Small plants, 3–250 m | Crossflow, Turgo |
- High head gives high jet velocity; an impulse turbine with small flow suits it.
- Low head needs large flow to give the same power, so a large flow-area axial runner (Kaplan) is used.
- Head variation also matters: Kaplan copes with varying head better than propeller.
(ii) Speed and specific speed
- Specific speed joins head, power and speed into one value that fixes the runner shape: Pelton 10–35, Francis 60–300, Kaplan 300–1000.
- A higher running speed gives a smaller, cheaper generator (fewer poles, ), so designers prefer the highest speed that is safe.
- But higher means a higher Thoma cavitation coefficient, so the runner must be set lower (more excavation), and the runaway speed is higher.
- Therefore the speed is chosen as the highest synchronous speed for which cavitation and runaway limits are satisfied.
(iii) Part-load operation
ROR plants often run at part load in the dry season, so the shape of the efficiency curve matters.
eff
| ____________ Pelton/Kaplan (flat)
| / ___
| / / \__ Francis (peaked)
|/ / \__ Propeller (sharp)
+--------------------> % load
0 25 50 75 100
- Pelton: efficiency stays high from about 20% to 100% load (flow controlled by needle; multiple jets can be shut).
- Kaplan: adjustable runner blades and guide vanes keep high efficiency over a wide range.
- Francis: best efficiency near 80–90% of rated load; falls quickly below about 40–50%, with vibration and cavitation.
- Propeller (fixed blade): very poor at part load.
If part-load running is expected, choose Pelton/Kaplan, or use several smaller Francis units so each runs near full load.
- 2079 Jestha · 8 marks
Describe the characteristics of various types of turbines used in hydro electric power stations.
Answer
Hydraulic turbines are of two main kinds: impulse turbines, in which the whole pressure head is turned into a free jet before it strikes the runner (Pelton, Turgo, crossflow), and reaction turbines, in which the runner is full of water under pressure and both pressure and kinetic energy act on it (Francis, Kaplan, propeller).
Pelton turbine (impulse, tangential flow)
- Head: high, about 50–1300 m; small discharge.
- Specific speed: about 10–35 per jet (up to ~60 with multiple jets).
- Water from one or more nozzles strikes double-cup buckets at atmospheric pressure; flow controlled by a spear (needle); a deflector cuts the jet on load rejection.
- Flat efficiency curve: high efficiency from about 20% to 100% load. Maximum efficiency about 90–92%.
- No draft tube; no cavitation in the runner; easy to inspect and repair, tolerant of sediment.
Francis turbine (reaction, mixed flow)
- Head: medium, about 10–350 m (most common 30–300 m); medium discharge.
- Specific speed: about 60–300.
- Spiral casing, stay vanes, adjustable guide vanes, runner (radial inflow, axial outflow) and draft tube.
- Highest peak efficiency (about 93–95%) but falls at part load below about 40–50%; vibration and draft tube surges at low load.
- Sensitive to cavitation and sediment erosion; runner setting fixed by Thoma's .
Kaplan turbine (reaction, axial flow)
- Head: low, about 2–40 m; large discharge.
- Specific speed: about 300–1000.
- Adjustable runner blades and guide vanes (double regulation) keep efficiency high over a wide load and head range.
- Large size, high speed relative to head; high cavitation risk, so deep setting.
- Propeller turbine: same with fixed blades; cheap but poor part-load efficiency.
Small-hydro turbines
- Crossflow (Michell–Banki): head 3–250 m, simple, cheap, flat efficiency (about 75–85%); used in Nepalese micro-hydro.
- Turgo: impulse, head 50–250 m, higher speed than Pelton for the same head.
Summary
| Feature | Pelton | Francis | Kaplan |
|---|---|---|---|
| Type | Impulse | Reaction | Reaction |
| Flow direction | Tangential | Radial in, axial out | Axial |
| Head | High | Medium | Low |
| Discharge | Low | Medium | High |
| (kW) | 10–35 | 60–300 | 300–1000 |
| Part-load efficiency | Very good | Poor | Very good |
| Draft tube | No | Yes | Yes |
| Cavitation risk | Low | Medium | High |
- 2078 Chaitra · 4 marks
Differentiate applicability of Francis and Kaplan Turbine in reference to hydropower project.
Answer
Both Francis and Kaplan are reaction turbines, but the Francis is a mixed-flow turbine for medium heads, while the Kaplan is an axial-flow turbine with adjustable blades for low heads and large discharge.
| Point | Francis | Kaplan |
|---|---|---|
| Flow | Radial in, axial out (mixed) | Axial |
| Head range | About 10–350 m (typically 30–300 m) | About 2–40 m |
| Discharge | Medium | Large |
| Specific speed (kW) | 60–300 | 300–1000 |
| Runner blades | Fixed, 9–19 vanes | Adjustable, 3–8 blades |
| Regulation | Guide vanes only | Guide vanes and runner blades (double) |
| Part-load efficiency | Falls below ~40–50% load | High over wide range |
| Cavitation | Moderate | Higher; needs deep setting |
| Typical project | Medium-head ROR/PROR in hills | Barrage or canal-drop plant on large rivers |
In hydropower projects: Francis suits most medium-head schemes in Nepal's hills (e.g. Kaligandaki "A", Middle Marsyangdi). Kaplan suits low-head, high-flow sites such as barrages on large rivers in the plains, canal falls and run-of-river schemes with large and varying flow.
- 2080 Chaitra · 4 marks
Discuss about suitability of Kaplan turbine in context of Nepalese hydropower sector.
Answer
The Kaplan turbine suits low heads (about 2–40 m) with large discharge. Its suitability in Nepal is limited, because most Nepalese hydropower sites are in steep hills with medium to high heads.
Points against wide use
- Nepal's rivers fall steeply, so most projects have heads of 50–600 m, which suit Francis and Pelton turbines.
- Low-head sites lie mainly in the Terai and inner valleys, where the land is flat; a barrage there floods farmland and may affect India downstream (border rivers).
- Nepalese rivers carry heavy sediment in the monsoon; Kaplan runners have high blade tip speeds and are prone to abrasion and cavitation.
- Kaplan units are large and heavy for their output; transporting them on hill roads is hard, and civil works (deep setting) are costly.
Where Kaplan is suitable
- Canal-drop and barrage plants: e.g. the Gandak hydropower station on the Gandak canal and potential sites on the Koshi, Karnali and Narayani in the plains.
- Low-head, high-flow ROR schemes on large rivers in the Terai and Chure foothills.
- Kaplan's flat part-load efficiency is useful where river flow varies a lot between seasons.
- Small low-head schemes can use simpler propeller or bulb turbines.
So Kaplan has a niche role in Nepal; Francis and Pelton dominate, but Kaplan is the right choice for low-head, high-discharge sites in the southern plains.
- 2073 Magh · 8 marks
What are the disadvantages of a very low specific speed reaction turbine? What are its advantages? How does the efficiency of the pelton wheel vary with its speed?
Answer
A very low specific speed reaction turbine is a slow Francis runner (about = 60–100, kW units) used near the top of the Francis head range. Its runner is large in diameter with long, narrow passages and nearly radial flow.
Disadvantages
- Large runner diameter for the power produced, so the turbine and generator (more poles at low speed) are heavy and costly.
- High friction and disc-friction losses in long narrow passages, so peak efficiency is lower than a medium- Francis.
- Low running speed means a large generator with many poles.
- Leakage losses through seals rise at high head.
- At heads where low- Francis is used, a Pelton may be cheaper and more efficient at part load.
Advantages
- Low cavitation risk: Thoma's critical is small at low , so the runner can be set higher above tailwater with less excavation.
- Can work under high heads (up to about 350–600 m), with small discharge.
- Robust runner, stable operation and smaller draft tube.
- Less sensitive to tailwater level changes.
Efficiency of Pelton wheel with speed
For a Pelton wheel with jet velocity , bucket speed , blade outlet angle and friction factor , the hydraulic efficiency is
Setting :
- Efficiency is a parabola in speed ratio : zero when the wheel is stationary (), maximum at (in practice about 0.46 due to losses), and zero again at runaway ().
- With and , (theoretical).
eff
| ___
| / \
| / \
| / \
| / \
+--------------+---> u/V1
0 0.46 1.0
Since a Pelton runs at constant synchronous speed while the jet velocity is fixed by head, the speed ratio stays near optimum, and load changes are handled by the needle; this is why its efficiency is high over a wide load range.
- 2078 Kartik · 6 marks
What are hydrograph and flow duration curve? Discuss its applicability.
Answer
Hydrograph
A hydrograph is a graph of river discharge plotted against time in calendar order (hours, days or months). It shows when high and low flows occur, e.g. the monsoon peak in July–August and the dry-season low in March–April for Nepalese rivers.
Q (m3/s)
| __
| / \
| / \
| / \__
| _____/ \______
+---------------------------> Month
Jan Mar May Jul Sep Nov
Flow duration curve (FDC)
An FDC is a graph of discharge against the percentage of time it is equalled or exceeded. It is made by sorting the same flow data in descending order and plotting each value against its exceedance . Time order is lost, but the duration of each flow is shown.
Q (m3/s)
|\
| \
| \___
| \______
| \__________
+--------------------------> % time exceeded
0 45 65 95 100
Applicability of the hydrograph
- Seasonal energy: monthly flows give month-wise energy, needed for wet/dry season tariff and PPA.
- Flood design: peak flood hydrographs size spillways, cofferdams and diversion works.
- Storage design: the mass curve (cumulative hydrograph) gives the reservoir or pondage volume needed to meet demand.
- Construction and maintenance planning: plan works and unit outages in low-flow months.
- Sediment planning: high-flow months carry most sediment, guiding desander operation.
Applicability of the FDC
- Design discharge: chosen at a set exceedance, e.g. – for ROR in Nepal.
- Installed capacity and annual energy: area under the FDC up to the design flow gives energy; plant factor is found from it.
- Firm power: from –.
- Number and size of units: shows how often the plant runs at part load.
- Riparian release: from the low-flow tail.
- Comparison of sites: a flat FDC means steady flow, ideal for ROR; a steep FDC means storage is needed.
| Point | Hydrograph | FDC |
|---|---|---|
| x-axis | Time (calendar) | % time exceeded |
| Shows sequence | Yes | No |
| Main use | Seasonal energy, floods, storage | Design flow, capacity, firm power |
- 2078 Chaitra · 4 marks
How would flow duration curve affect while designing unit sizes of power plant?
Answer
The flow duration curve (FDC) shows how long each flow is available, so it decides how many units are needed and how big each should be, so that turbines run near their best efficiency for most of the year.
How the FDC affects unit sizing
- Total design flow: the plant's design discharge is taken at a chosen exceedance (e.g. ). This fixes total capacity .
- Minimum turbine flow: every turbine has a minimum stable flow (Francis about 40% of rated, Pelton about 10–20%, Kaplan about 20–30%). The dry-season flow from the FDC (e.g. –) must be at least the minimum flow of one unit, or the plant must shut down in the dry season.
- Steep FDC → more units: if the flow drops far below the design flow for long periods, divide the capacity into two or more units. In the dry season one unit runs near full load instead of all units at poor part load.
- Flat FDC → fewer, larger units: steady flow allows one or two large units, which are cheaper per kW.
- Equal-sized units are preferred for interchangeable spares and simple operation; unequal units are used only when the FDC is very steep.
- Reliability and maintenance: with at least two units, maintenance can be done in the low-flow season while the other unit uses all the available water.
Example
If m³/s and m³/s, a single Francis unit would need at least m³/s and would stop in the driest months. With two units of 5 m³/s each, one unit needs only 2 m³/s, so it keeps running even at .
- 2075 Bhadra · 6 marks
The design exceedance of hydropower plant Q45%, what does that mean? Compare Q45% with Q65% while designing hydropower plant from the perspective of power producer (seller).
Answer
Meaning of Q45%
A design exceedance of Q45% means the plant's design (rated) discharge is the flow that the river equals or exceeds 45% of the time, about days a year. The installed capacity is based on this flow:
For the other 55% of the time the plant runs at part load, following the river flow. In Nepal, NEA's power purchase practice for ROR projects has moved from about (older practice) to about –.
Comparison from the seller's (IPP) point of view
| Point | Q45% design | Q65% design |
|---|---|---|
| Design flow | Larger | Smaller |
| Installed capacity | Higher (MW) | Lower |
| Annual energy | More (extra wet-season energy) | Less |
| Plant factor | Lower (about 55–65%) | Higher (about 70–80%) |
| Capital cost | Higher (bigger waterway, units) | Lower |
| Cost per kWh | Can be higher if the extra energy is only wet-season | Lower per kWh |
| Wet-season spill/curtailment risk | Higher (NEA may curtail surplus in monsoon) | Lower |
| Dry-season share of energy | Smaller proportion | Larger proportion |
| Revenue | Higher total, if all energy is bought | Lower total, steadier |
Seller's view
- Q45 gives more MW and more total energy, which raises revenue if NEA buys all energy under a take-or-pay PPA. Bank financing and per-MW benefits also favour larger capacity.
- But most of the extra energy comes in the monsoon, when the tariff is lower (dry-season rate is higher than wet-season rate in NEA's posted rates) and when the grid already has surplus, so spillage or curtailment can reduce income.
- Q65 gives a smaller, cheaper plant with higher plant factor and lower risk, but loses wet-season energy.
- The final choice is made by comparing incremental energy and revenue against incremental cost (B/C ratio, IRR) for several exceedance values; with a firm PPA, sellers usually prefer about Q40–Q45.
- 2074 Bhadra · 5 marks
Why riparian release is considered during the design of hydropower plant? What are the criteria of design discharge selection?
Answer
Why riparian release is considered
Riparian release (environmental flow, compensation flow) is the minimum flow that must be left in the river below the diversion weir. It is deducted from the river flow before calculating the plant's design discharge.
- Aquatic life: keeps fish, insects and plants alive in the dewatered stretch between weir and tailrace; allows fish migration.
- Downstream water rights: people use river water for drinking, irrigation, water mills, washing and cremation (religious use) at ghats.
- Water quality and landscape: prevents stagnation, pollution and loss of scenic value.
- Legal requirement: in Nepal, the Hydropower Development Policy 2001 and EIA guidelines require releasing at least 10% of the minimum monthly average flow, or more if the EIA finds it necessary.
So available flow for generation .
Criteria for selection of design discharge
- Flow duration curve: design flow is chosen at a set exceedance, e.g. – for ROR in Nepal (older practice ).
- Riparian release deducted first.
- Type of project: ROR uses an exceedance flow; PROR and storage projects can use larger flows for peaking.
- Economics: design flow is increased step by step until the incremental benefit equals incremental cost (maximum NPV or acceptable IRR, B/C).
- PPA and grid demand: the buyer's policy (NEA) on exceedance, dry/wet energy and plant factor.
- Minimum turbine flow and number of units: the low-flow season must still run at least one unit.
- Sediment and site constraints: tunnel size, desander capacity and geology limit the flow that can be conveyed economically.
- 2078 Chaitra · 4+2 marks
What are the factors to be considered during selection of appropriate site for hydropower? Also mentions the factors that govern discharge of a hydropower project.
Answer
Factors for selection of a hydropower site
- Availability of water: a river with good, reliable flow (from rainfall, snow and glaciers), shown by long-term hydrological data.
- Available head: a steep river reach or a river bend where a short tunnel gives a large head.
- Geology: sound rock for dam, tunnel and powerhouse; avoid active faults, landslides and weak zones.
- Storage possibility: a narrow gorge with a wide valley upstream if storage is wanted.
- Sediment load: low sediment or space for a desander.
- Access and transport: roads for heavy equipment and construction materials.
- Distance to load or grid: short transmission line reduces cost and losses.
- Environmental and social impact: minimal submergence, resettlement, forest loss and impact on protected areas.
- Natural hazards: floods, GLOF, earthquakes, debris flows.
- Cost of the project: cost per kW and per kWh.
Factors governing discharge of a hydropower project
- Catchment area above the intake.
- Rainfall amount and distribution (monsoon), plus snow and glacier melt.
- Evaporation and transpiration losses.
- Catchment characteristics: slope, soil, geology, forest cover, which control runoff and baseflow.
- Upstream use: irrigation and drinking water abstractions, and riparian release requirement.
- 2070 Magh · 5+3 marks
What are the criteria for selection of a hydropower project? If the water in the river is known to carry high sediments and debris, what would be your particular recommendation in its design?
Answer
Criteria for selection of a hydropower project
- Hydrology: sufficient and reliable flow; FDC and long-term data.
- Head: steep gradient or large drop over a short distance.
- Topography and geology: good dam, tunnel and powerhouse sites; stable slopes.
- Sediment and hazards: sediment load, floods, GLOF, landslides and seismicity.
- Access and transmission: road access and distance to grid or load centre.
- Environmental and social impact: submergence, resettlement, fish, protected areas; EIA clearance.
- Power market: demand, PPA possibility and energy mix (peaking or base load).
- Economics: cost per kW, levelised cost per kWh, IRR, B/C ratio, payback.
- Legal and institutional: licences, water rights and local acceptance.
Recommendation for a river with high sediment and debris
- Headworks: gated weir with undersluice to keep the intake area flushed; boulder/debris barrier and coarse trash rack upstream of intake.
- Intake design: side intake placed on the outer bend, raised sill and sediment excluder to draw cleaner surface water.
- Gravel trap close to the intake with flushing gates.
- Larger desander: multiple bays, designed to remove finer particles (e.g. 0.2 mm, or 0.1–0.15 mm for high-head Pelton/Francis), with continuous or frequent flushing.
- Turbine choice: prefer Pelton where head allows, as it is easier to repair; for Francis, use lower runner velocity and sediment-resistant design.
- Materials: 13Cr-4Ni stainless steel runners with hard coatings (e.g. tungsten-carbide HVOF) on runners, guide vanes and nozzles.
- Operation: monitor sediment concentration online and shut down units during flood peaks above a set limit; keep spare runners and needles.
- For storage/pondage: provide low-level flushing outlets and plan regular reservoir flushing.
Questions from Old Question Collection (EE 753) (IOE EE 753 exam papers from 2070 Magh to 2082 Shrawan), Question bank (ioesolutions) (IOE EE 753 exam papers from 2070 Bhadra to 2074 Magh) and Old questions (NCE Library) (IOE EE 753 exam papers from 2070 Bhadra to 2080 Chaitra). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗