Chapter 4 · 24 hours
Electric System Design of a Power Plant
IOE past exam questions
Past questions and answers
62 questions set from this chapter, 13 of them more than once. Most asked first.
- Asked 5 times
- 2082 Shrawan · 6 marks
- 2079 Jestha · 8 marks
- 2075 Bhadra · 6 marks
- 2074 Bhadra · 6 marks
- 2071 Bhadra · 6 marks
Compare Brushless Excitation System with Static Excitation System for a synchronous generator on the basis of schematic diagram, operating range, accessories required, cost and so on.
Answer
Both systems supply DC to the rotor field of a synchronous generator. A brushless system uses a shaft-mounted AC exciter with rotating diodes, so no brushes are needed. A static system takes power from the generator terminals through a transformer and a thyristor bridge, and feeds the field through slip rings and brushes.
Schematic diagrams
BRUSHLESS EXCITATION
stationary | rotating (on shaft)
PMG/aux --> AVR |
supply | |
v |
Exciter field | Exciter armature (3-ph)
(stator) ~~~~~~~|~~~~> |
| Rotating diode bridge
| |
| Main field (rotor)
| |
Main generator stator --> Grid
STATIC EXCITATION
Gen terminals --+---------------> GSU --> Grid
|
Excitation transformer
|
Thyristor bridge <-- AVR
|
Field breaker
|
Brushes + slip rings
|
Main field (rotor)
Comparison
| Basis | Brushless excitation | Static excitation |
|---|---|---|
| Power source | AC exciter on shaft (with PMG or aux supply to AVR) | Generator terminals via excitation transformer |
| Rectifier | Rotating diode bridge | Stationary thyristor bridge |
| Brushes/slip rings | None | Required |
| Control | AVR controls exciter field; acts through exciter time constant | AVR fires thyristors directly on main field |
| Response speed | Slower (about 0.5–1 s exciter time constant) | Very fast (tens of ms), high ceiling voltage |
| Negative field forcing / fast de-excitation | Not possible (diodes) | Possible (inverter mode, field breaker) |
| Operating range | Good for steady loads; limited transient support | Wide; best for stability, PSS, large swings |
| Behaviour during close-in fault | Unaffected if PMG-fed | Ceiling drops with terminal voltage; needs field flashing for start |
| Accessories | Rotating diodes, diode fuses, diode-failure and rotor earth-fault monitoring (telemetry), PMG | Excitation transformer, thyristor bridge with cooling, field breaker, de-excitation resistor, field flashing (battery), brush gear |
| Maintenance | Very low; no carbon dust | Brush and slip ring maintenance; carbon dust |
| Field measurement | Rotor current and temperature not directly measurable | Directly measurable |
| Cost | Economical for small and medium machines; becomes costly for large ratings | Economical for large machines; extra cost of transformer and brushes |
| Typical use | Small/medium hydro, diesel and remote plants | Large hydro and thermal units on strong grid |
Conclusion: brushless is chosen where low maintenance and reliability matter (small to medium, remote plants); static is chosen for large units where fast response and transient stability matter.
- Asked 5 times
- 2081 Chaitra · 6 marks
- 2081 Shrawan · 8 marks
- 2079 Shrawan · 4 marks
- 2078 Kartik · 6 marks
- 2075 Bhadra · 4 marks
Describe the major steps that to be followed for design of earthing (grounding) mat in power station and its switchyard.
Answer
A grounding (earthing) mat is a buried grid of horizontal conductors with vertical rods under a powerhouse and switchyard. It must carry fault current to earth safely and keep step and touch voltages within tolerable limits. Design normally follows IEEE Std 80.
Layout
+----+----+----+----+ Horizontal grid
| | | | | (Cu or GI conductor
+----+----+----+----+ at 0.5-0.8 m depth)
| | | | |
+----+----+----+----+ o = earth rods
o | | | o
+----+----+----+----+
Steps
- Site data: area of switchyard/powerhouse; measure soil resistivity by the Wenner four-pin method; resistivity of surface layer (crushed rock) .
- Fault current and time: find maximum earth fault current , split factor and decrement factor :
Fault clearing time and shock duration (e.g. 0.5–1 s). 3. Conductor size: from IEEE 80 (Onderdonk-type) formula
then add corrosion allowance and mechanical minimum. 4. Tolerable step and touch voltages (50 kg body):
- Initial design: choose grid spacing , depth , total conductor length and number of rods, covering the whole area plus about 1 m beyond the fence.
- Grid resistance (Sverak):
- Ground potential rise: . If , the design is safe; go to step 10.
- Mesh and step voltages:
- Check and modify: require and . If not, reduce spacing, add conductors or rods, add crushed rock, or extend the grid, and repeat.
- Detailed design: connect all equipment frames, neutrals, fences, lightning arresters and cable sheaths; check transferred potentials; target resistance typically below 1 Ω for large stations.
- Asked 3 times
- 2082 Shrawan · 6 marks
- 2074 Bhadra · 6 marks
- 2073 Magh · 5 marks
Discuss the various factors which should be considered for the choice of generator during the design of a power plant.
Answer
The generator must match the turbine, the grid and the site. The main factors are:
- Rating (MVA) and power factor: ; power factor usually 0.85–0.9 lagging so the unit can supply reactive power. Some overload margin (e.g. 10%) is often specified.
- Rated voltage: usually 6.6 kV or 11 kV for hydro units (higher, e.g. 13.8–15.75 kV, for very large units); chosen with GSU and bus/cable cost.
- Speed and number of poles: fixed by the turbine: . Hydro units are slow, salient-pole machines with many poles.
- Shaft arrangement: vertical (large Francis/Kaplan) or horizontal (small Pelton/Francis).
- Reactances and SCR: sets fault level and breaker rating; SCR and set stability and voltage regulation.
- Inertia constant (GD²): larger inertia limits speed rise on load rejection and improves stability, but costs more.
- Efficiency and losses: high efficiency (above 97–98%) saves energy over the plant life.
- Insulation and temperature rise: class F insulation with class B temperature rise is common; altitude derating above 1000 m.
- Cooling: air-cooled (open or closed with air–water coolers) for hydro.
- Excitation system: brushless for small/medium units, static for large units.
- Neutral grounding: high-resistance grounding via NGT.
- Grid requirements: capability curve, reactive power range, fault ride-through, harmonics.
- Transport and erection limits: weight and size on hill roads; split stator if needed.
- Standards and cost: IEC 60034; capital cost versus loss capitalisation.
Example
For a 10 MW turbine output, , pf 0.85: generator rating MVA, 11 kV, 50 Hz; if the turbine speed is 600 rpm, poles .
- Asked 3 times
- 2078 Kartik · 4 marks
- 2074 Magh · 3+5 marks
- 2074 Bhadra · 6 marks
What is the significance of short circuit ratio (SCR) in design of synchronous generator? Show analytically its impact on stability of the power system.
Answer
Significance of SCR in generator design
- Air gap and size: a high SCR needs a low , i.e. a larger air gap and more field ampere-turns; the machine becomes larger, heavier and costlier.
- Stability: higher SCR gives a higher steady-state power limit and stronger synchronizing torque.
- Voltage regulation: higher SCR → smaller voltage drop with load, so better regulation.
- Fault level: higher SCR → higher steady short-circuit current, so heavier switchgear.
- Line charging: a high-SCR machine can charge long, lightly loaded lines without self-excitation.
- Losses: a larger field current increases field losses. So SCR is a compromise between cost and performance; hydro generators connected by long lines are usually given SCR of about 1.0–1.2 or more.
Impact on stability
Short circuit ratio (SCR) is the ratio of field current needed to produce rated open-circuit voltage to the field current needed to circulate rated armature current on a sustained three-phase short circuit:
Typical values: salient-pole hydro generators 1.0–1.5; cylindrical-rotor turbo generators 0.5–0.7.
Analytical relation with stability
Power delivered by a generator (neglecting resistance and saliency) to an infinite bus:
- Maximum (steady-state limit) power: . Lower SCR → lower .
- Load angle for given load: . Lower SCR → larger , closer to the 90° limit.
- Synchronizing power coefficient: . Lower SCR → smaller restoring torque after a disturbance.
Numerical illustration ( p.u. kept the same, p.u., p.u.):
| SCR | (p.u.) | (p.u.) | (p.u./rad) | Margin | |
|---|---|---|---|---|---|
| 1.2 | 0.833 | 2.16 | 23.17° | 1.986 | 60.6% |
| 1.0 | 1.000 | 1.80 | 28.18° | 1.587 | 52.8% |
| 0.6 | 1.667 | 1.08 | 51.91° | 0.666 | 21.3% |
So the lower the SCR, the lower the stability margin (higher , smaller and ).
On a – graph, a lower SCR gives a flatter sine curve with a lower peak, so the operating point sits closer to the peak and a smaller disturbance can push the machine out of step.
- Asked 3 times
- 2081 Shrawan · 4 marks
- 2073 Bhadra · 4 marks
- 2071 Magh · 4 marks
What could be the consequences of using higher or lower short circuit ratio (SCR) for a synchronous generator?
Answer
Short circuit ratio (p.u.). Its value changes the size, cost and behaviour of a synchronous generator.
| Aspect | Higher SCR (low ) | Lower SCR (high ) |
|---|---|---|
| Air gap | Larger | Smaller |
| Size, weight, cost | Larger, heavier, costlier | Smaller, cheaper |
| Field current and losses | Higher | Lower |
| Steady-state stability limit | Higher, more stable | Lower, less stable |
| Synchronizing power | Higher | Lower |
| Voltage regulation | Better (less drop) | Poorer |
| Short-circuit current | Higher; heavier CBs | Lower |
| Line-charging capability | Good, resists self-excitation | Poor |
| Efficiency | Slightly lower (more field loss) | Slightly higher |
Consequences in brief
- Too high SCR: an over-sized, expensive machine with higher fault levels and more field losses; benefits may not justify the cost.
- Too low SCR: cheaper machine but poor stability margin and voltage regulation; needs fast excitation (static, with PSS) and careful operation; risk of losing synchronism on a weak grid.
- Typical values: hydro (salient pole) 1.0–1.5, turbo generators 0.5–0.7.
- Asked 3 times
- 2081 Chaitra · 6 marks
- 2073 Magh · 3+2 marks
- 2072 Asoj · 4 marks
Discuss working of a brushless excitation with necessary schematic diagram. When would you recommend using such excitation system?
Answer
A brushless excitation system supplies DC to the rotor of a synchronous generator without brushes or slip rings. A small AC exciter and a diode rectifier are mounted on the generator shaft, so the rectified current goes straight into the field winding.
Schematic
BRUSHLESS EXCITATION
stationary | rotating (on shaft)
PMG/aux --> AVR |
supply | |
v |
Exciter field | Exciter armature (3-ph)
(stator) ~~~~~~~|~~~~> |
| Rotating diode bridge
| |
| Main field (rotor)
| |
Main generator stator --> Grid
Working
- A permanent magnet generator (PMG) on the same shaft (or an auxiliary supply) feeds the AVR.
- The AVR compares generator terminal voltage with the set value and controls the DC current in the stationary field of the AC exciter.
- The exciter armature rotates with the shaft and produces three-phase AC.
- A rotating diode bridge on the shaft converts this AC into DC.
- This DC flows directly into the main field winding on the rotor; the main generator then produces terminal voltage.
- If voltage falls (load increase), the AVR raises exciter field current → exciter output rises → main field current rises → terminal voltage is restored.
- Fuses protect the diodes; a rotor earth-fault relay works through a slip-ring-free telemetry or injection device.
When to recommend brushless excitation
- Small and medium hydro plants, especially remote or unmanned stations in Nepal, where low maintenance is important.
- Where carbon dust from brushes is a problem (enclosed or humid powerhouses) or in hazardous atmospheres.
- High-speed machines (horizontal Pelton/Francis units, turbo generators) where slip ring wear is high.
- Where the generator feeds a weak/isolated system and a PMG-fed AVR keeps excitation during faults.
- When very fast excitation response is not required for system stability (for large units on a stressed grid, static excitation is preferred).
- Asked 3 times
- 2082 Shrawan · 6 marks
- 2079 Chaitra · 4 marks
- 2077 Chaitra · 4 marks
List out the necessary protection schemes to be employed for a medium size generator in a power plant.
Answer
A medium size generator (roughly 5–100 MVA) is protected against internal faults, abnormal operating conditions and system disturbances. Typical schemes, with ANSI device numbers:
| ANSI | Protection | Purpose |
|---|---|---|
| 87G | Generator differential | Fast clearing of stator phase-to-phase faults |
| 87GT / 87T | Overall gen-transformer / transformer differential | Faults in GSU and connections |
| 64G (59N + 27TN) | Stator earth fault (95% neutral overvoltage + 100% third harmonic) | Earth faults in stator winding (high-resistance grounded via NGT) |
| 64R | Rotor (field) earth fault | First earth fault in field winding |
| 40 | Loss of excitation (field failure) | Prevents running as induction generator and drawing VArs |
| 46 | Negative phase sequence | Unbalanced loads/open phase; rotor heating |
| 32 | Reverse power | Motoring when turbine power is lost |
| 51V / 21 | Voltage-restrained overcurrent / impedance | Backup for external faults |
| 49 | Stator thermal overload (RTDs) | Overheating |
| 59 / 27 | Over/under voltage | Load rejection, AVR failure |
| 81O / 81U | Over/under frequency | Speed and grid frequency deviations |
| 24 | Overfluxing (V/Hz) | Protects generator and GSU core |
| 78 | Pole slipping (out of step) | Loss of synchronism |
| 50/27 | Inadvertent energisation | Breaker closed at standstill |
| 50BF | Breaker failure | Backup tripping of adjacent breakers |
Mechanical/hydraulic protections
Overspeed, bearing and oil temperature, vibration, cooling water failure, low oil pressure, shear pin failure.
Tripping logic
Faults like 87G, 64G, 64R (second stage) trip the GCB, field breaker and turbine (emergency shutdown); abnormal conditions like 46, 49 or 81 first alarm, then trip after a time delay.
- Asked 3 times
- 2074 Magh · 5+3 marks
- 2071 Magh · 5+3 marks
- 2070 Bhadra · 5+3 marks
Explain any two scheme of unit generator transformer combination used in power plant on the basis of fault level, maintenance outage and efficiency. Also draw the single line diagram for both of the scheme.
Answer
In a power plant, the generator is connected to the grid through a step-up transformer. Two common schemes are (1) the unit scheme, one generator to one transformer, and (2) the grouped (combined) scheme, two generators to one transformer.
Scheme 1: Unit connection (one generator – one transformer)
G1 G2
| |
GCB GCB
|---UAT |---UAT
GSU1 GSU2
| |
HV CB HV CB
| |
===================== HV bus
- Fault level: a fault on the generator bus is fed by one generator plus the grid through one GSU impedance; LV fault level is lower, so GCB and bus duct ratings are smaller.
- Maintenance outage: a GSU fault or maintenance takes out only its own unit; other units keep running. Each unit is independent.
- Efficiency: each transformer runs close to full load when its unit runs; when a unit is off, its transformer can be disconnected, so no-load losses are saved. But total no-load and load loss of several small transformers is higher than one large transformer, and cost is higher.
- Reliability: highest; widely used for large units.
Scheme 2: Grouped connection (two generators – one transformer)
G1 G2
| |
GCB1 GCB2
| |
================ LV (11 kV) bus
|---- Station transformer
GSU (2 x unit rating)
|
HV CB
|
================ HV bus
- Fault level: a fault on the LV bus is fed by both generators plus the grid, so the LV fault level is much higher; GCBs and bus need higher breaking capacity.
- Maintenance outage: a GSU fault or maintenance takes out both units, so energy loss is larger. A generator can be taken out by its own GCB while the other runs.
- Efficiency: one large transformer has lower cost per MVA and lower total losses at full load; but when only one unit runs (dry season), the transformer runs at half load and its full no-load loss remains.
- Cost: fewer transformers, HV breakers and bays, so cheaper and smaller switchyard; common for small and medium hydro in Nepal.
Comparison
| Basis | Unit scheme | Grouped scheme |
|---|---|---|
| LV fault level | Lower | Higher |
| GCB rating | Smaller | Larger |
| Outage on transformer fault | One unit | Both units |
| Transformer losses | Higher total, but idle transformer can be switched off | Lower at full load; no-load loss always present |
| Switchyard cost | Higher (more bays) | Lower |
| Flexibility | High | Lower |
- Asked 3 times
- 2079 Jestha · 8 marks
- 2073 Magh · 6 marks
- 2070 Magh · 8 marks
Develop a typical specification while procuring a power transformer to be used in power plant design.
Answer
A technical specification for a power plant's power (step-up) transformer lists the ratings, design, performance and test requirements so that bidders quote a transformer that fits the plant and grid. A typical specification (following IEC 60076) for a hydropower GSU is:
| Item | Typical specification |
|---|---|
| Type, application | Outdoor, oil-immersed, 3-phase, two-winding, generator step-up |
| Standard | IEC 60076 (all parts) |
| Rated power | e.g. 30 MVA (ONAN) / 37.5 MVA (ONAF) |
| Rated voltage ratio | e.g. 132 / 11 kV |
| Frequency | 50 Hz |
| Vector group | YNd11 (HV star neutral solidly earthed) |
| Impedance | About 10–12.5% on rated MVA (with tolerance per IEC) |
| Tap changer | Off-circuit ±2 × 2.5% on HV (or OLTC if grid needs it) |
| Cooling | ONAN/ONAF (or OFWF in cavern powerhouses) |
| Insulation level (BIL) | HV 650 kVp lightning impulse, 275 kV power frequency (for 145 kV class); LV 75 kVp, 28 kV |
| Temperature rise | Top oil 60 K, average winding 65 K over 40 °C ambient |
| Altitude | Derating/insulation correction above 1000 m |
| Losses | Guaranteed no-load and load losses, capitalised in bid evaluation |
| Efficiency, regulation | Stated at rated load and 0.85 pf |
| Noise level | e.g. below 75 dB(A) |
| Short-circuit withstand | 2 s thermal, dynamic per IEC 60076-5 |
| Core and winding | CRGO core; copper windings; disc/helical type |
| Oil | Mineral oil to IEC 60296 |
| Bushings | Porcelain/composite, with bushing CTs for protection |
| Accessories | Conservator with air-cell, silica gel breather, Buchholz relay, PRV, OTI, WTI, MOG, drain/filter valves, rollers, earthing terminals, marshalling box |
| Tests | Routine (ratio, polarity, resistance, impedance, losses, dielectric), type (temperature rise, impulse) and special tests; FAT witnessed |
| Transport | Max weight and dimensions for hill road access; nitrogen-filled transport if needed |
| Documents and spares | Drawings, manuals, recommended spares, warranty |
The rating is fixed from generator MVA (e.g. two 15 MVA units → 30 MVA), impedance from fault-level and stability studies, and BIL from the insulation coordination of the HV system.
- Asked 2 times
- 2081 Chaitra · 4 marks
- 2078 Chaitra · 6 marks
What is capability curve of a generator? Describe briefly.
Answer
A capability curve (P–Q chart) of a synchronous generator shows the region of active power and reactive power in which the generator can operate continuously without exceeding thermal and stability limits. Operators use it to set loading and VAr output.
Q (lagging, over-excited)
^
|-------._ field heating limit
| '.
| \
| | <- turbine limit
| | (P = Pmax)
+------------+---> P
| | <- stator heating
| / limit (circle S)
| ______.'
| under-excitation /
| stability limit
v
Q (leading, under-excited)
Limits that form the curve
- Stator (armature) current heating limit: ; a circle centred at the origin with radius equal to rated MVA.
- Field (rotor) current heating limit: maximum excitation emf gives a circle centred at with radius . This limits the lagging (over-excited) region.
- Prime mover (turbine) limit: maximum turbine output, a vertical line .
- Under-excitation limits: in the leading region, the steady-state stability limit ( approaching 90°, with practical margin) and stator end-core heating limit the VAr absorption.
- Minimum load limit: some turbines (e.g. Francis) cannot run stably below about 40% load.
Use
- Rated point lies where the stator circle meets the field circle at rated power factor (e.g. 0.85 lagging).
- Shows how much reactive power the unit can supply or absorb at a given , needed for grid voltage control and for setting AVR limiters (over-excitation and under-excitation limiters).
- Asked 2 times
- 2082 Shrawan · 4 marks
- 2081 Chaitra · 2+4 marks
What is neutral grounding transformer (NGT)? Also describe the steps to find optimal size of NGT.
Answer
A neutral grounding transformer (NGT) is a single-phase distribution-type transformer connected between the generator neutral and earth, with a resistor on its secondary. The resistor, reflected to the primary as a high resistance, gives high-resistance grounding of the generator.
Generator (star)
\ | /
\|/ neutral
|
NGT primary (e.g. 11 kV/sqrt3)
|||
NGT secondary (e.g. 240 V)
|
[R] loading resistor
| + 59N relay across R
=== earth
Purpose: limits stator earth fault current to about 5–15 A, preventing core damage; limits transient overvoltages during arcing faults; allows sensitive stator earth fault protection (59N relay across the resistor).
Steps to find optimal size of NGT
- Total capacitance to earth per phase : stator winding, generator bus duct/cables, GSU LV winding, surge capacitors and VT windings.
- Capacitive earth fault current:
- Choose resistor current (resistance not more than the capacitive reactance), so that transient overvoltage stays below about 2.6 p.u.:
- NGT voltage ratio: primary rated at generator phase-to-neutral voltage (often line voltage for safety margin), secondary e.g. 240 V; turns ratio .
- Secondary resistor value: .
- NGT kVA rating: (short-time rating for 1 min or until protection trips), giving a smaller, cheaper transformer than a continuous rating.
- Check: total fault current is within the allowed limit (typically below 10–15 A) and the relay sensitivity covers about 95% of the winding.
- Asked 2 times
- 2082 Shrawan · 6 marks
- 2073 Magh · 3 marks
Which circuit breaker would you think suitable as generator circuit breaker (GCB) in hydropower station, and why?
Answer
A generator circuit breaker (GCB) is placed between the generator and the step-up transformer. For a hydropower station, an SF6 generator circuit breaker (or a vacuum GCB for small and medium units), designed and tested to IEEE C37.013 / IEC 62271-37-013, is suitable. A normal distribution breaker built to IEC 62271-100 is not adequate.
Why a special GCB is needed
- High DC component: the generator circuit has a high X/R ratio, so the fault current DC offset decays slowly; currents can have delayed current zeros. The GCB must interrupt such asymmetric currents.
- High rate of rise of TRV: the transformer and generator have small capacitance, so the transient recovery voltage rises very fast; SF6 and vacuum interrupters can withstand it.
- High continuous current: e.g. a 30 MVA unit at 11 kV carries about 1.6 kA; large units carry tens of kA.
- Out-of-phase switching: the GCB must interrupt during unsuccessful synchronisation.
- Frequent operation: hydro units start and stop daily (peaking), so a long mechanical and electrical life is needed.
Why SF6 (or vacuum)
- SF6 has excellent arc-quenching and dielectric strength, handles high currents and asymmetry, and is compact; it is the usual choice for medium and large hydro units.
- Vacuum GCBs are compact and maintenance-free for small/medium units; precautions: current chopping may cause overvoltage, so surge arresters and RC surge suppressors are fitted near the generator and transformer.
- Air-blast and oil breakers are obsolete for this duty.
Benefits of using a GCB
- Generator faults are cleared fast and selectively; the unit is synchronised on the LV side.
- Station auxiliaries can be fed from the grid through the GSU when the generator is off (back-feeding), so a separate station transformer may not be needed.
- Better protection of the GSU and generator, higher plant availability.
- Asked 2 times
- 2074 Magh · 5 marks
- 2071 Magh · 6 marks
Discuss electrical characteristics of unit transformer that to be considered during its selection.
Answer
The unit transformer (generator step-up transformer of a unit) connects a generator to the HV system. Its electrical characteristics must suit both the generator and the grid.
Electrical characteristics considered
- Rated MVA: at least the generator rated MVA (e.g. 15 MVA for a 12.75 MW, 0.85 pf unit); some margin for overload and the unit auxiliary load.
- Voltage ratio: LV equal to generator voltage (e.g. 11 kV); HV equal to grid voltage plus margin for line drop (e.g. 132 kV).
- Vector group: YNd11 is common: delta on generator side blocks zero-sequence and third harmonics; star-earthed HV gives an earthed system.
- Percentage impedance: about 8–14%. Higher impedance reduces fault level and breaker rating; lower impedance improves voltage regulation and stability. Fixed by fault-level and stability studies.
- Tappings: off-circuit taps (e.g. ±2 × 2.5%) or OLTC on HV, to match grid voltage and control VAr flow.
- Losses and efficiency: no-load (iron) and load (copper) losses are capitalised; low losses save energy for 30+ years.
- Insulation level (BIL) and temperature rise: HV BIL as per insulation coordination; temperature rise per IEC 60076 (oil 60 K, winding 65 K); altitude correction above 1000 m.
- Cooling: ONAN/ONAF for outdoor; OFWF in underground powerhouses.
- Overfluxing capability: must withstand V/Hz rise on load rejection (e.g. 1.1 p.u. continuous, 1.4 p.u. for a few seconds).
- Short-circuit withstand: thermal and dynamic for 2 s per IEC 60076-5.
- Magnetising inrush and noise level.
- Standards: IEC 60076.
- 2071 Bhadra · 5+5 marks
Discuss the various factors which should be considered for the choice of generator during the design of a power plant. Also clarify analytically that lower the short circuit ratio (SCR), lower be the stability of the system.
Answer
Factors for the choice of generator
- Rating (MVA) and power factor: ; power factor usually 0.85–0.9 lagging so the unit can supply reactive power. Some overload margin (e.g. 10%) is often specified.
- Rated voltage: usually 6.6 kV or 11 kV for hydro units (higher, e.g. 13.8–15.75 kV, for very large units); chosen with GSU and bus/cable cost.
- Speed and number of poles: fixed by the turbine: . Hydro units are slow, salient-pole machines with many poles.
- Shaft arrangement: vertical (large Francis/Kaplan) or horizontal (small Pelton/Francis).
- Reactances and SCR: sets fault level and breaker rating; SCR and set stability and voltage regulation.
- Inertia constant (GD²): larger inertia limits speed rise on load rejection and improves stability, but costs more.
- Efficiency and losses: high efficiency (above 97–98%) saves energy over the plant life.
- Insulation and temperature rise: class F insulation with class B temperature rise is common; altitude derating above 1000 m.
- Cooling: air-cooled (open or closed with air–water coolers) for hydro.
- Excitation system: brushless for small/medium units, static for large units.
- Neutral grounding: high-resistance grounding via NGT.
- Grid requirements: capability curve, reactive power range, fault ride-through, harmonics.
- Transport and erection limits: weight and size on hill roads; split stator if needed.
- Standards and cost: IEC 60034; capital cost versus loss capitalisation.
Lower SCR gives lower stability (analytical proof)
Short circuit ratio (SCR) is the ratio of field current needed to produce rated open-circuit voltage to the field current needed to circulate rated armature current on a sustained three-phase short circuit:
Typical values: salient-pole hydro generators 1.0–1.5; cylindrical-rotor turbo generators 0.5–0.7.
Analytical relation with stability
Power delivered by a generator (neglecting resistance and saliency) to an infinite bus:
- Maximum (steady-state limit) power: . Lower SCR → lower .
- Load angle for given load: . Lower SCR → larger , closer to the 90° limit.
- Synchronizing power coefficient: . Lower SCR → smaller restoring torque after a disturbance.
Numerical illustration ( p.u. kept the same, p.u., p.u.):
| SCR | (p.u.) | (p.u.) | (p.u./rad) | Margin | |
|---|---|---|---|---|---|
| 1.2 | 0.833 | 2.16 | 23.17° | 1.986 | 60.6% |
| 1.0 | 1.000 | 1.80 | 28.18° | 1.587 | 52.8% |
| 0.6 | 1.667 | 1.08 | 51.91° | 0.666 | 21.3% |
So the lower the SCR, the lower the stability margin (higher , smaller and ).
Physically, a low SCR means a high synchronous reactance, i.e. weak magnetic coupling between rotor and stator through a small air gap; the generator must swing to a larger angle to transmit the same power, leaving less margin before it slips a pole.
- 2070 Magh · 5+3 marks
Discuss the various factors which should be considered for the choice of generator during the design of a power plant. Also mention the significance of short circuit ratio in the selection of generator.
Answer
Factors for the choice of generator
- Rating (MVA) and power factor: ; power factor usually 0.85–0.9 lagging so the unit can supply reactive power. Some overload margin (e.g. 10%) is often specified.
- Rated voltage: usually 6.6 kV or 11 kV for hydro units (higher, e.g. 13.8–15.75 kV, for very large units); chosen with GSU and bus/cable cost.
- Speed and number of poles: fixed by the turbine: . Hydro units are slow, salient-pole machines with many poles.
- Shaft arrangement: vertical (large Francis/Kaplan) or horizontal (small Pelton/Francis).
- Reactances and SCR: sets fault level and breaker rating; SCR and set stability and voltage regulation.
- Inertia constant (GD²): larger inertia limits speed rise on load rejection and improves stability, but costs more.
- Efficiency and losses: high efficiency (above 97–98%) saves energy over the plant life.
- Insulation and temperature rise: class F insulation with class B temperature rise is common; altitude derating above 1000 m.
- Cooling: air-cooled (open or closed with air–water coolers) for hydro.
- Excitation system: brushless for small/medium units, static for large units.
- Neutral grounding: high-resistance grounding via NGT.
- Grid requirements: capability curve, reactive power range, fault ride-through, harmonics.
- Transport and erection limits: weight and size on hill roads; split stator if needed.
- Standards and cost: IEC 60034; capital cost versus loss capitalisation.
Significance of SCR in generator selection
(p.u.). It is specified in the purchase specification because:
- Stability: steady-state limit ; higher SCR gives a larger stability margin, important for plants connected to the grid through long lines.
- Voltage regulation: higher SCR gives less voltage change with load.
- Line charging: high SCR prevents self-excitation when charging long, unloaded lines.
- Cost and size: higher SCR needs a larger air gap and more field copper, making the machine heavier and costlier.
- Fault level: higher SCR raises short-circuit current and switchgear rating. Typical selection: hydro units about 1.0–1.2 (salient pole), turbo units 0.5–0.7.
- 2079 Chaitra · 6 marks
Discuss logics behind recommending brushless excitation system over static excitation system.
Answer
A brushless excitation system uses a shaft-mounted AC exciter and rotating diodes, while a static excitation system uses a thyristor bridge fed from the generator terminals with slip rings and brushes. Brushless is recommended mainly for reliability, low maintenance and independence from terminal voltage.
BRUSHLESS EXCITATION
stationary | rotating (on shaft)
PMG/aux --> AVR |
supply | |
v |
Exciter field | Exciter armature (3-ph)
(stator) ~~~~~~~|~~~~> |
| Rotating diode bridge
| |
| Main field (rotor)
| |
Main generator stator --> Grid
Logic behind recommending brushless over static
- No brushes or slip rings: removes the main wear part of the static system; no brush replacement, no sparking, no carbon dust that contaminates windings and causes insulation failure.
- Low maintenance and high availability: ideal for remote, small and medium hydro plants in Nepal where skilled staff and spares are limited.
- Self-contained supply: with a PMG-fed AVR, excitation does not depend on generator terminal voltage, so excitation stays available during close-in faults and the machine can build up voltage without field flashing from a battery; this helps black start.
- Better for high speeds: slip ring wear and heating grow with peripheral speed, so high-speed units favour brushless.
- Safer environment: no open sparking; suitable for dusty, humid or hazardous areas.
- Fewer external components: no excitation transformer, large thyristor cubicle or field breaker; less space in the powerhouse.
- Economical for small and medium ratings.
Limitations to keep in mind
- Slower response (exciter time constant), no negative field forcing, so less help for transient stability.
- Rotor current and diode health are hard to monitor; a failed diode needs shutdown to replace.
- For large units on a weak grid, static excitation remains the better choice.
- 2080 Chaitra · 6 marks
Discuss brushless excitation system. Also mention its pros and cons in comparison to its best possible alternative.
Answer
A brushless excitation system supplies the synchronous generator field from a shaft-mounted AC exciter whose output is rectified by a rotating diode bridge, so no brushes or slip rings are needed between the exciter and the main field.
Working
- A small permanent magnet generator (PMG) or station supply feeds the AVR.
- The AVR controls a thyristor bridge that feeds the stationary field of the AC exciter.
- The AC exciter has a rotating armature on the main shaft. Its 3-phase output goes to a rotating diode rectifier mounted on the same shaft.
- The rectified DC goes directly to the main generator field winding.
PMG --> AVR --> Exciter field (stator)
|
===== shaft ========|=====================
Exciter armature -> Rotating diodes -> Main field
(rotating) (rotating) (rotor)
|
Main stator --> Gen terminals
Best alternative
The best alternative is the static (thyristor) excitation system, where the field is fed from the generator terminals through an excitation transformer and thyristor bridge, using slip rings.
Pros of brushless excitation (compared with static)
- No brushes or slip rings: low maintenance, no carbon dust, no brush sparking; good for remote, unmanned plants and hazardous areas.
- Excitation power is taken from the shaft, so it is independent of generator terminal voltage; it can supply field current during close-in faults (good for fault current support and relay operation).
- Self-contained with a PMG: no need for an external supply or field flashing at start.
- Fewer external power components (no large excitation transformer or high-current thyristor cubicle).
Cons of brushless excitation (compared with static)
- Slow response: the exciter field time constant (about 0.5–1 s) adds delay, so transient stability support is poorer than static excitation (response in tens of ms).
- No fast field de-excitation: the main field cannot be forced negative or shorted quickly; field suppression after a fault is slow because the decay depends on the rotor time constant.
- Rotating diodes and fuses cannot be inspected while running; diode failure needs special monitoring.
- Longer shaft and extra rotating mass; higher cost for very large machines.
- Rotor field current and voltage cannot be measured directly.
| Feature | Brushless | Static |
|---|---|---|
| Brushes/slip rings | None | Needed |
| Response | Slow | Very fast |
| De-excitation | Slow | Fast (inverting) |
| Maintenance | Low | Brush upkeep |
| Fault-time supply | Maintained | Drops with |
| Typical use | Small–medium hydro, diesel | Large hydro, thermal |
- 2081 Shrawan · 6 marks
Explain static excitation system. Also highlight its pros and cons in comparison to its best possible alternative.
Answer
A static excitation system is one in which the generator field is fed with DC from a thyristor (SCR) rectifier that has no rotating parts. The power is taken from the generator terminals through an excitation transformer and reaches the rotor through slip rings and brushes.
Working
- An excitation transformer connected to the generator terminals steps the voltage down.
- A fully controlled 3-phase thyristor bridge rectifies it. The AVR changes the firing angle to control the field voltage, .
- The DC goes to the field through slip rings. A field breaker and a discharge resistor/crowbar are provided for de-excitation.
- At start the terminal voltage is zero, so field flashing from the station battery or AC supply builds up the initial voltage.
Gen terminals -> Exc. transformer -> Thyristor bridge
|
PT, CT -> AVR (firing angle) --+
v
Battery -> Field flashing -> Field CB -> Slip rings
|
Main field
Best alternative
The main alternative is the brushless excitation system: an AC exciter with rotating diodes mounted on the shaft.
Pros (compared with brushless)
- Very fast response: the field voltage changes almost at once. A high ceiling voltage (often 1.6–2 times rated or more) improves transient stability.
- Fast de-excitation: the bridge can work in inverter mode (negative field voltage) to kill the field quickly during internal faults.
- No rotating exciter, so the shaft is shorter and the machine is simpler. Easy to fit in an existing plant.
- Field voltage and current can be measured directly, and PSS and limiters can be added easily.
- Thyristors are easy to reach for maintenance and redundant bridges can be used.
Cons (compared with brushless)
- Needs slip rings and brushes, so brush wear, carbon dust and regular maintenance.
- Supply comes from the generator terminals, so during a close three-phase fault the terminal voltage collapses and the excitation is lost unless there is compound (CT) support. Fault current may decay before the relays act.
- Needs field flashing for start.
- The thyristors produce harmonics and shaft voltages. Cooling and a large transformer are needed.
| Point | Static | Brushless |
|---|---|---|
| Response | Very fast | Slow |
| Brushes | Required | None |
| Field suppression | Fast | Slow |
| Fault-time support | Weak | Good |
| Typical use | Large hydro/thermal | Small–medium units |
- 2073 Magh · 5 marks
Discuss the working of Brushless excitation system and static excitation system with proper schematic diagram.
Answer
Both are modern excitation systems for synchronous generators. They differ in where the rectifier is and how DC reaches the field.
Brushless excitation system
- A PMG (pilot exciter) on the shaft supplies the AVR.
- The AVR feeds DC to the stationary field of the main AC exciter.
- The AC exciter armature rotates with the shaft and produces 3-phase AC.
- A rotating diode bridge on the shaft rectifies it and feeds the main field directly. No brushes are needed.
- The AVR controls the exciter field, which in turn controls the main field.
PMG ---> AVR ---> Exciter field (stationary)
: (air gap)
[ROTOR] Exciter armature -> Diode bridge -> Main field
:
Main stator ---> Generator terminals ---> PT/CT to AVR
Static excitation system
- An excitation transformer fed from the generator terminals supplies a thyristor bridge.
- The AVR compares the terminal voltage with the set value and changes the firing angle of the thyristors.
- The DC output goes to the rotor through a field breaker and slip rings/brushes.
- At start, field flashing from the battery gives the initial field until the voltage builds up.
Gen terminals -> Exc. transformer -> Thyristor bridge
| (alpha)
AVR <- PT, CT |
v
Battery -> Field flashing -> Field CB -> Slip rings
|
Main field
| Item | Brushless | Static |
|---|---|---|
| Rectifier | Rotating diodes | Stationary thyristors |
| Brushes | No | Yes |
| Response | Slower | Very fast |
- 2079 Chaitra · 8 marks
Describe the working principle of electronic based automatic voltage regulator with suitable diagrams.
Answer
An electronic automatic voltage regulator (AVR) keeps the generator terminal voltage at the set value by measuring it continuously and adjusting the field current through power-electronic switches (thyristors or transistors), with no moving parts.
Principle
It is a closed-loop (feedback) control system. The error between the reference voltage and the measured voltage is amplified and used to change the exciter field:
where is the amplifier gain and is the signal from the stabiliser (PSS). If falls (for example, when load increases), the error rises, the field current increases and the voltage comes back.
Block diagram
Vref -->( + )--> Amplifier -> Firing -> Thyristor
^ - (PID) circuit bridge
| |
| v
| Exciter / field
| |
Rectifier v
& filter <------- PT <------- Generator Vt
^
Stabilising feedback / limiters
Main parts and their work
- Sensing (PT + rectifier + filter): steps down the terminal voltage, rectifies and smooths it into a DC signal proportional to . Often the reactive current from a CT is added (load compensation/droop) so parallel units share vars.
- Comparator (error detector): compares the sensed signal with a stable reference (zener or digital set-point).
- Amplifier / controller: op-amp or digital PID amplifies the error.
- Firing circuit: converts the control voltage into a firing angle for the thyristors. Smaller gives more field voltage, since for a full bridge.
- Power stage: thyristor bridge feeding the exciter field (brushless) or main field (static).
- Stabilising feedback: rate feedback from the field voltage, or a PSS, damps hunting and oscillations.
- Limiters and protection: over-excitation limiter, under-excitation limiter, V/Hz limiter, stator current limiter.
Operation
- Steady state: firing angle fixed, .
- Load increases or lagging power factor: drops, error positive, decreases, field current rises, restored.
- Load rejection: rises, increases (or inverts), field reduced.
Modes
- Auto mode: voltage control as above.
- Manual mode: field current control, used for testing or when the PT fails.
Advantages over electromechanical regulators
- Fast response with no dead band.
- No moving contacts, so little maintenance.
- Accurate regulation (about ±0.5 %).
- Easy to add limiters, PSS and remote control.
- 2075 Bhadra · 6 marks
List out the major elements that limits the alternator's capability curve. Draw a typical capability curve of alternator and explain it.
Answer
The capability curve of an alternator is a P–Q chart that shows the safe region of operation, i.e. the combinations of active power P and reactive power Q that the machine can deliver continuously at rated voltage without exceeding any limit.
Elements that limit the curve
- Armature (stator) current heating limit: . At rated this is a circle centred at the origin with radius equal to rated MVA.
- Field (rotor) current heating limit: the maximum excitation allowed by rotor heating. It is a circle centred at with radius . It limits operation at lagging (over-excited) power factor.
- Prime mover (turbine) limit: maximum mechanical power, a vertical line .
- Steady-state stability limit: at leading power factor the load angle approaches . A practical limit with margin is used.
- Stator end-core heating limit: in under-excited operation leakage flux heats the stator ends and limits leading-var absorption.
- Minimum excitation / minimum turbine load: for example cavitation zones in hydro turbines limit low load.
Typical capability curve
Q lagging (MVAr)
^
|~~~~~--.. <- field current limit
| A `.
| o <- rated MVA, rated pf
| | <- stator current limit
| | <- turbine (max P) limit
+------------+------> P (MW)
| |
| B /
| ..-` <- stability / end-core limit
|..--~~
v Q leading (MVAr)
Explanation
- Region A (over-excited, lagging pf): the field current limit is the binding curve from zero P up to the rated power factor point. Above rated pf (more P), the stator current limit governs.
- Rated point: where the field and stator limit circles meet, i.e. rated MVA at rated pf (e.g. 0.85 lagging).
- High P region: the stator circle and the turbine limit line cut off the curve.
- Region B (under-excited, leading pf): the steady-state stability limit (with margin) and stator end heating limit how much reactive power the machine can absorb.
- The operator must keep the operating point inside the enclosed area. The AVR limiters (OEL, UEL) are set from this curve.
- 2072 Asoj · 4 marks
Describe speed governing system of hydro generator.
Answer
The speed governing system of a hydro generator controls the turbine's water flow (wicket gate or needle opening) so that the speed, and hence the frequency, stays constant and load is shared between units in parallel.
Components
- Speed sensor: a PMG or toothed wheel with pick-up giving speed/frequency.
- Governor controller: electronic PID; compares actual speed with the reference and includes droop (permanent speed regulation, usually 4–5 %).
- Electro-hydraulic converter / proportional valve: turns the electrical signal into oil flow.
- Pilot and main distributing valves, servomotor: move the wicket gates (Francis/Kaplan) or the needle and deflector (Pelton).
- Oil pressure unit: pump, accumulator and sump.
- Feedback: gate position transducer.
f_ref -->( + )--> PID + droop --> E/H valve --> Servomotor
^ - |
| Wicket gates
Speed sensor <-- Generator <-- Turbine <---+
Working
- Load increases: speed falls, the error opens the gates, more water flows and the speed recovers.
- Droop makes each unit pick up load in proportion to its rating.
- Hydro needs slow gate movement (temporary droop/dashpot) because of water hammer and the water starting time . Pelton turbines use a deflector for quick load rejection.
- 2077 Chaitra · 8 marks
Write down the types of generator neutral grounding. Specify the types to be used in accordance to the size of power plant with their advantages and disadvantages.
Answer
Generator neutral grounding means connecting the star point of the stator winding to earth, directly or through an impedance, to limit earth-fault current, control overvoltages and allow earth-fault protection.
Types
- Ungrounded (isolated neutral)
- Solid (effective) grounding: neutral connected straight to earth.
- Low-resistance grounding: resistor limits fault current to about 100–1000 A.
- Low-reactance grounding: reactor limits fault current to roughly 25–100 % of the 3-phase fault current.
- High-resistance grounding: usually through a distribution transformer with a secondary resistor, limiting the fault current to about 5–15 A.
- Resonant grounding (Petersen coil / ground fault neutraliser): reactor tuned to the stator capacitance; fault current nearly zero.
Gen Gen Gen Gen
star star star star
| | | |
| [R] [X] )||( dist. tr.
=== === === [r] secondary
solid low-R reactance high-R
Selection according to plant size
| Plant / connection | Usual grounding | Reason |
|---|---|---|
| Small LV sets (< ~1 MW, 400 V, feeding loads directly) | Solid | Needed for 4-wire loads and LV protection |
| Small–medium generators on a common bus (MV) | Low-resistance or reactance | Several machines on bus; selective relaying |
| Medium–large unit-connected (gen–transformer) | High-resistance via distribution transformer | Very low fault current, little core damage |
| Very large units (some practice) | Resonant / high-R | Minimum damage, may run briefly with a fault |
Advantages and disadvantages
| Type | Advantages | Disadvantages |
|---|---|---|
| Ungrounded | Can continue with one earth fault | Transient overvoltages (up to 6 pu) from arcing; fault hard to locate |
| Solid | Simple, cheap; phase voltages stay near normal; easy relaying | Very high fault current (can exceed 3-phase value), core burning, mechanical stress |
| Low resistance | Limits damage; good relay current | Some stator iron damage; resistor losses during fault |
| Reactance | Cheaper than resistor for high current | Can cause transient overvoltage if is high |
| High resistance | Fault current ~10 A, almost no core damage; overvoltage limited by damping () | Needs sensitive 95 % + 100 % stator earth-fault protection; only for unit system |
| Resonant | Arc self-extinguishes, least damage | Tuning needed; costly; complex protection |
In Nepalese hydro plants, the common practice is a high-resistance grounding through a distribution (neutral grounding) transformer for unit-connected generators, and a neutral grounding resistor for small MV generators sharing a bus.
- 2079 Chaitra · 6 marks
Compare grounded and ungrounded power system.
Answer
A grounded system has its neutral connected to earth (solidly or through an impedance). An ungrounded (isolated neutral) system has no intended connection to earth; it is only coupled to earth through the line-to-ground capacitances.
Comparison
| Point | Grounded system | Ungrounded system |
|---|---|---|
| Neutral potential | Held near earth | Floats; can shift |
| Healthy-phase voltage during L-G fault | Near phase voltage (solid) | Rises to line voltage ( times) |
| Arcing-ground overvoltages | Suppressed | Can reach 5–6 pu, damaging insulation |
| Earth-fault current | Large enough to trip relays | Small capacitive current () |
| Fault detection | Easy, selective earth-fault relays | Difficult; only alarm via voltage relays |
| Insulation level | Graded insulation; cheaper equipment | Full line-voltage insulation needed |
| Continuity of supply | Faulted section trips at once | Can run with one earth fault for a while |
| Safety | Better; touch voltage cleared fast | Second fault can be dangerous |
| Lightning arresters | Lower-rated arresters can be used | Higher rating needed |
| Interference | Earth-fault current may disturb telecom | Little |
| Typical use | Modern systems, generators, above 33 kV | Old small systems, some industrial LV |
Capacitive current in an ungrounded system
When one phase is earthed, the other two line capacitances charge to line voltage. The fault current is
At fault currents above about 4–5 A this capacitive current causes arcing grounds: the arc repeatedly strikes and extinguishes, building up voltage on the healthy phases.
Conclusion for practice
Almost all modern power systems are grounded. The method depends on voltage level: solid for LV and EHV, resistance/reactance for MV, and high-resistance for unit-connected generators.
- 2078 Chaitra · 4 marks
Discuss advantages of solidly grounded system of generator grounding.
Answer
In solid grounding, the generator neutral is connected directly to the station earth with no intentional impedance.
Advantages
- Neutral held at earth potential: during a line-to-ground fault the healthy phases stay close to phase voltage, so there are no high overvoltages.
- No arcing-ground problem: the fault current is large and the arc does not restrike, so transient overvoltages are eliminated.
- Reduced insulation cost: equipment and lightning arresters can be rated for phase voltage (about 80 % arresters).
- Simple and reliable protection: the large earth-fault current operates ordinary overcurrent/earth-fault relays quickly and selectively.
- Simple and cheap: no resistor, reactor or transformer to buy and maintain.
- Supports single-phase loads: a 4-wire LV supply (phase-to-neutral loads) is possible, which is why small LV diesel and micro-hydro sets are usually solidly grounded.
- Better personnel safety because faults are cleared quickly.
Limitation
For large generators the earth-fault current can exceed the 3-phase fault current (since is small), causing stator core burning and severe mechanical stress, so solid grounding is used mainly on small LV machines.
- 2078 Chaitra · 6 marks
How are the concepts of STEP POTENTIAL and TOUCH POTENTIAL utilized during grounding mat design of a power project area? Why and how these potentials are appropriately set?
Answer
Step potential is the voltage between a person's two feet, 1 m apart, when standing on the ground during an earth fault. Touch potential is the voltage between the hand touching an earthed metal structure and the feet standing on the ground. Both arise because fault current flowing into the soil makes the ground surface potential uneven.
Earthed structure
| hand
|---o <- touch voltage = V(structure) - V(feet)
| /|\
======|==/=\============== ground surface
| feet 1 m apart <- step voltage = V1 - V2
---- grid conductors (mat) buried ~0.5 m ----
How they are used in grid (mat) design (IEEE Std 80)
- Tolerable limits are found first from the body current that the heart can withstand (Dalziel): , with for a 50 kg person. With body resistance 1000 Ω:
where is the surface-layer resistivity, the surface layer derating factor and the fault clearing time.
- Grid potential rise is calculated. If GPR is below the tolerable touch voltage, the design is safe.
- Otherwise the actual mesh voltage (worst touch voltage in a mesh corner) and actual step voltage are calculated from the grid geometry (spacing, conductor length, depth, soil resistivity).
- The design is accepted only if and . If not, the grid is changed and the check repeated.
Why they are set this way
- Ensures that the current through a human body during the worst fault stays below the ventricular fibrillation threshold within the fault clearing time.
- Touch voltage is usually the critical one, because hand-to-feet current passes near the heart and the feet act in parallel, giving less resistance.
How they are kept within limits
- Close grid spacing and more conductors; extra rods at the perimeter.
- Surface layer of crushed rock/gravel (high , about 3000 Ω·m), which raises the tolerable limits.
- Faster fault clearing (smaller ).
- Bonding all metal structures and fences to the grid; grading rings around equipment and at gates.
- Lowering grid resistance with deeper rods or treated soil.
- 2074 Magh · 3 marks
What particular precaution should be taken while using vacuum circuit breaker (VCB) as a generator circuit breaker (CB)?
Answer
A generator circuit breaker (GCB) must interrupt very high currents with a large DC component and a fast-rising TRV. A vacuum circuit breaker (VCB) chops current sharply, so special precautions are needed.
Precautions
- Surge protection against current chopping: install surge arresters (metal oxide) and RC surge suppressors / surge capacitors at the generator and transformer terminals, because chopping and re-ignition create high overvoltages on the inductive winding.
- Check DC component and delayed current zeros: the breaker must be type-tested to IEEE C37.013 / IEC 62271-37-013 for generator duty, since the DC offset can delay current zeros.
- TRV control: add capacitors to reduce the rate of rise of recovery voltage.
- Rate it for continuous current with proper cooling, and check vacuum integrity periodically.
- 2070 Bhadra · 3+5 marks
What particular precautions should be taken while using vacuum circuit breakers as a generator circuit breaker? State the limitations of vacuum circuit breaker in comparision to SF6 circuit breaker in HV application.
Answer
Precautions when a VCB is used as a generator CB
A generator breaker sees a very high fault current with a large DC component (because of the high X/R ratio), delayed current zeros, and a very fast TRV rate of rise. A VCB interrupts so well that it can chop the current before natural zero. On the inductive generator and transformer windings this gives overvoltages and multiple re-ignitions. So:
- Install metal-oxide surge arresters close to the breaker on both sides.
- Install surge capacitors or RC snubbers at the generator terminals to slow the voltage rise and damp chopping overvoltages.
- Choose a breaker type-tested for generator duty (IEEE C37.013 / IEC 62271-37-013), including asymmetrical breaking with high DC content and out-of-phase switching.
- Check the TRV/RRRV capability; add TRV capacitors if needed.
- Make sure the continuous current rating and temperature rise are adequate (forced cooling if needed).
- Use low-chopping contact material (e.g. Cu–Cr) and monitor vacuum integrity.
Limitations of VCB compared with SF6 in HV application
| Point | VCB | SF6 CB |
|---|---|---|
| Voltage per break | Up to about 36–40 kV; series interrupters needed above | One break handles 145–245 kV, more with series |
| HV use (>72.5 kV) | Limited, few products | Standard up to 800 kV |
| Current chopping | Higher; switching overvoltages | Very low chopping |
| Capacitive switching | Risk of restrike | Restrike-free |
| Continuous current | Limited by contact size | Very high (several kA) |
| Insulation outside bottle | Needs separate insulation | Gas gives insulation too (GIS) |
| Size at HV | Bulky with many breaks | Compact |
Summary of VCB limitations at HV: the dielectric strength of a vacuum gap does not rise linearly with gap length, so a single bottle cannot be built economically above about 40 kV. Several bottles in series need voltage grading. Chopping overvoltages are higher and the continuous current rating is lower. For these reasons SF6 dominates above 72.5 kV, although SF6 is a greenhouse gas.
- 2072 Magh · 8 marks
Make a comparison between vacuum circuit breaker with SF6 circuit breaker in a power system.
Answer
A vacuum circuit breaker (VCB) extinguishes the arc in a sealed vacuum bottle (about to torr), where the arc is a metal vapour arc that dies at current zero. An SF6 circuit breaker extinguishes the arc by blowing sulphur hexafluoride, an electronegative gas, across it. The gas captures free electrons and quickly restores dielectric strength.
Arc quenching in brief
- VCB: on contact separation, metal vapour from the contacts carries the arc. At current zero the vapour condenses on shields within microseconds, so the gap recovers very fast. Spiral or axial magnetic field contacts keep the arc diffuse.
- SF6: puffer or self-blast type. The moving piston compresses the gas and blows it through the nozzle onto the arc. SF6 has about 2–3 times the dielectric strength of air at the same pressure.
VCB bottle SF6 puffer interrupter
+---------+ +-----------------+
| fixed | | fixed contact |
| === | | == <- gas |
| shield | | nozzle blast |
| === | | == piston |
| moving | | moving contact |
+--bellows+ +-----------------+
Comparison
| Point | VCB | SF6 CB |
|---|---|---|
| Medium | Vacuum | SF6 gas at 3–6 bar |
| Voltage range | 3.3–36 kV (mainly MV) | 33–800 kV (mainly HV/EHV) |
| Dielectric recovery | Very fast | Fast |
| Current chopping | Higher; needs surge suppressors | Very low |
| Contact travel | Small (10–20 mm) | Larger |
| Operating mechanism | Small spring mechanism | Larger spring/hydraulic |
| Maintenance | Almost none; sealed for life | Gas pressure monitoring, leak checks |
| Number of operations | Very high (10,000–30,000) | Lower |
| Fire/explosion risk | None | None |
| Environment | Clean | SF6 is a strong greenhouse gas; arc products toxic |
| Monitoring | Vacuum loss hard to detect | Gas density monitor |
| Size at MV | Compact | Compact |
| Size at HV | Many breaks, bulky | Compact, used in GIS |
| Cost | Lower at MV | Lower at HV |
| Capacitor switching | Possible restrike | Good |
Use in power systems
- VCB: the usual choice for MV switchgear (11 kV and 33 kV feeders), generator terminals of small–medium hydro units, motor and capacitor bank switching, and frequent-operation duties.
- SF6: the usual choice for 132 kV, 220 kV and 400 kV outdoor switchyards and GIS. In Nepal the 132/220 kV substations of NEA use SF6 breakers, while 11/33 kV panels use VCBs.
For new designs, SF6-free alternatives (vacuum interrupter with clean air insulation) are spreading because of the environmental impact of SF6.
- 2080 Chaitra · 6 marks
List out the most essential protection schemes required for Alternator and Generator Step Up transformer in a mega size power project.
Answer
In a mega (large) hydro or thermal project, the alternator and its generator step-up (GSU) transformer are protected by a set of main and backup relays, usually grouped as a unit protection scheme with an overall differential zone.
Generator protections (ANSI number)
| Protection | ANSI | Purpose |
|---|---|---|
| Generator differential | 87G | Stator phase-to-phase faults |
| Stator earth fault 95 % | 59N / 64G | Earth faults on 95 % of winding |
| 100 % stator earth fault | 27TN / 64S | Faults near neutral (3rd harmonic or injection) |
| Rotor earth fault | 64R / 64F | Field winding earth fault |
| Loss of excitation | 40 | Field failure, under-excitation |
| Negative sequence | 46 | Unbalanced load, rotor heating |
| Reverse power | 32 | Motoring of the unit |
| Over/under frequency | 81 | Abnormal speed |
| Over/under voltage | 59 / 27 | Load rejection, AVR failure |
| Overfluxing (V/Hz) | 24 | Core over-excitation |
| Voltage-restrained overcurrent / impedance | 51V / 21 | Backup for external faults |
| Pole slipping | 78 | Loss of synchronism |
| Stator thermal / RTD | 49 | Overload, cooling failure |
| Inadvertent energisation | 50/27 | Breaker closed on a stopped unit |
GSU transformer protections
| Protection | ANSI | Purpose |
|---|---|---|
| Transformer differential | 87T | Internal phase faults |
| Restricted earth fault (HV) | 64REF / 87N | Earth faults near HV neutral |
| Buchholz relay | 63 | Incipient internal faults, gas |
| Oil and winding temperature | 26 / 49 | Overheating |
| Pressure relief device | 63PR | Sudden internal pressure |
| HV overcurrent and earth fault | 50/51, 50N/51N | Backup |
| Overfluxing | 24 | Over-excitation of core |
| Oil level, cooling failure | 71 | Alarm |
Overall scheme
An overall (unit) differential 87GT covers the generator, GSU and unit auxiliary transformer together. Relays are duplicated as Main-1 and Main-2 groups with separate CTs and DC supplies for very large units. Trips go through a master trip relay (86) to the GCB, HV breaker, field breaker and turbine shutdown.
- 2081 Chaitra · 6 marks
What is restricted earth fault protection? Illustrate its use with suitable diagram.
Answer
Restricted earth fault (REF) protection is a sensitive unit protection that detects earth faults inside a defined zone only, usually a star-connected transformer or generator winding. It compares the sum of the three phase currents with the neutral current.
Principle
- CTs are placed in each phase and in the neutral-to-earth connection, all of the same ratio.
- The three phase CTs are connected in parallel (residual connection) and then in parallel with the neutral CT, with a relay across them.
- External earth fault (outside the zone): the residual current from the phase CTs equals the neutral CT current, so they circulate between CTs and no current flows through the relay.
- Internal earth fault (inside the winding): the neutral current has no matching residual current, so the difference flows through the relay and it trips.
A ---[CT]-----+---- to system
B ---[CT]-----+
C ---[CT]-----+
Star | | | |
winding \ | / | residual
\|/ |
N ---+--[CT_N]---+---[ R ]--+
| relay |
earth (high-impedance, with
stabilising resistor
and Metrosil)
Features
- Usually a high-impedance relay with a stabilising resistor so CT saturation on heavy external faults does not cause false trips. A non-linear resistor (Metrosil) limits voltage during internal faults.
- Very sensitive: it covers faults close to the neutral end, where the ordinary transformer differential (87T) is not sensitive enough. On a resistance-earthed winding a fault near the neutral gives very little phase current.
- Fast and stable.
Use
- HV star winding of the generator step-up transformer (solidly earthed side).
- Star winding of station/auxiliary transformers.
- Small generators with resistance earthing.
For a delta winding, REF is applied using an earthing transformer or the three phase CTs alone (balanced earth fault protection).
- 2073 Bhadra · 8 marks
Draw the unit protection scheme of a power transformer. Mention the selection criteria for the power transformer. What reflects the Vector group of a power transformer?
Answer
Unit protection scheme of a power transformer
The main unit protection of a power transformer is percentage-biased differential protection (87T), backed by restricted earth fault, Buchholz and others. It compares the currents entering and leaving the transformer. Inside the zone the difference trips the relay; for through faults the currents balance.
HV bus Power transformer LV bus
---[CT1]-----+====( Yd11 )====+-----[CT2]---
| | Buchholz(63) | |
| REF(64) | |
| |
+---> [ 87T bias + operate ] <---+
2nd harmonic block
(inrush), 5th (overflux)
|
Master trip 86 -> HV & LV CBs
Points to note:
- CT ratios and connections (or software settings) correct for the ratio and the phase shift of the vector group (for Yd11, CTs on the Y side connected in delta, or numerical compensation).
- Bias (restraint) handles CT mismatch and tap-changer range.
- 2nd harmonic restraint blocks tripping on magnetising inrush. 5th harmonic blocking is used for overfluxing.
- Supplementary protections: REF (64), Buchholz (63), oil/winding temperature (26/49), pressure relief (63PR), overcurrent and earth-fault backup (50/51, 51N), overfluxing (24).
Selection criteria for a power transformer
- Rated MVA: from generator rating (e.g. generator MVA plus margin), with cooling class ONAN/ONAF/OFAF.
- Voltage ratio: generator voltage to transmission voltage (e.g. 11/132 kV); tap changer range (OLTC or off-circuit, e.g. ±10 % in 1.25 % or 2.5 % steps).
- Vector group to suit the system and earthing (GSU usually YNd11 with HV star grounded).
- Impedance (% Z): balance between fault level limit and voltage regulation/stability; usually 10–14 % for GSU.
- Number of phases: three-phase unit or a bank of single-phase units (transport limits on hilly roads in Nepal).
- Insulation level: BIL and power-frequency withstand.
- Losses (no-load and load), efficiency and capitalised loss cost.
- Cooling, temperature rise, altitude derating, noise, transport size and weight.
- Standards: IEC 60076.
What the vector group reflects
The vector group (e.g. YNd11, Dyn11, Yy0) tells:
- The winding connection of HV (capital letter: Y, D, Z) and LV (small letter: y, d, z).
- Whether the neutral is brought out (N or n).
- The phase displacement of LV with respect to HV by the clock number, each hour being . For example "11" means LV leads HV by (11 o'clock position), and "1" means LV lags by .
It is essential for parallel operation (only transformers with the same phase shift can be paralleled), for differential CT compensation, and for earthing and the third-harmonic path (a delta winding traps triplen harmonics).
- 2081 Shrawan · 4 marks
What does "black start capability" of a generating unit mean? How would it have been made so?
Answer
Black start capability is the ability of a generating unit or plant to start itself and energise the dead bus and transmission lines without any power from the external grid, after a total or partial blackout. Such units are used to restore the system.
How a unit is made black-start capable
- Independent auxiliary supply: a diesel generator (DG) set or a small house/auxiliary hydro unit to power the station auxiliaries (governor oil pumps, cooling water pumps, lubrication, lighting).
- Station battery and DC system sized to operate breakers, protection, controls and field flashing during the dead period.
- Excitation able to build up from zero: field flashing from the battery (for static excitation), or a PMG-fed brushless exciter, which needs no external source.
- Governor and turbine that can start with stored oil pressure (accumulator) or DG-powered pumps; hydro gates or valves that can open on DC/stored energy.
- Controls and protection settings for isolated (island) mode: frequency control mode, dead-bus closing logic, synchronising for later reconnection.
- The unit must be able to energise transformers and lines (charging current, inrush) and carry the initial loads.
Hydro plants are ideal black-start sources because they start quickly and need little auxiliary power.
- 2080 Chaitra · 4 marks
Discuss briefly about requirements of DC supply system in a power generating station.
Answer
The DC supply system gives a reliable, uninterrupted power source for the vital control, protection and emergency loads of a power station, even when all AC supply is lost.
Requirements
- Loads served: relay and protection circuits, breaker trip and close coils, control and SCADA, alarms, emergency lighting, field flashing, DC emergency oil pumps (governor, bearing lube), communication (often 48 V).
- Voltage levels: typically 220 V or 110 V DC for control and switchgear, 48 V DC for telecom/PLCC, 24 V for some electronics.
- Battery bank: lead-acid (VRLA or flooded) or Ni-Cd, sized for the duty cycle (e.g. 1–3 hours of emergency load plus trip and close surges at the end), with ageing and temperature factors (IEEE 485).
- Battery chargers: float-cum-boost chargers fed from the station AC. Usually two chargers and two battery banks for redundancy in large stations.
- Distribution: DC distribution board with separate feeders, fuses/MCBs, and earth-fault monitoring because the DC system is unearthed.
- Reliability: separate battery room with ventilation (hydrogen), voltage monitoring and alarms, and regular capacity tests.
- 2073 Bhadra · 6 marks
What is DOD of a battery? Draw the typical schemes of service station.
Answer
Depth of discharge (DOD)
Depth of discharge (DOD) is the fraction of a battery's rated capacity that has been taken out, expressed in percent:
It is the complement of the state of charge: . For example, taking 60 Ah from a 200 Ah battery gives a DOD of 30 %.
Importance:
- A deeper DOD shortens battery life (fewer cycles). Lead-acid batteries are usually designed for 50–80 % maximum DOD, Ni-Cd and Li-ion can go deeper.
- Battery sizing for a station uses the allowed DOD and the end-of-discharge voltage (e.g. 1.75–1.8 V/cell for lead-acid).
Station service (auxiliary supply) schemes
Station service supplies the auxiliaries: pumps, cooling, governors, cranes, lighting, battery chargers. Common schemes:
1. Unit auxiliary transformer (UAT) tapped from the generator bus, with station transformer backup
Gen G1 --+-- GSU T1 --+-- HV bus (132 kV)
| |
UAT1 Station service tr (from HV bus)
| |
Unit aux board 1 ----+---- Common station board
|
DG set (standby / black start)
2. Common station service board fed from two sources (main bus and tertiary/grid)
11 kV gen bus --> SST-1 --+
|-- 415 V board --> loads
33/11 kV feeder -> SST-2 -+ (bus coupler)
|
DG set --> Emergency board
|
Battery charger --> DC board
Key features:
- At least two independent sources with automatic changeover (bus coupler).
- An emergency diesel generator for black start and essential loads.
- Unit boards for each generating unit's own auxiliaries, plus a common board for shared loads.
- Essential loads moved to the emergency board; DC system with its own battery for vital loads.
- 2070 Magh · 8 marks
Name the auxillary and ancillary systems with their function in a hydropower plant with Francis turbine of 100 MW.
Answer
Auxiliary systems are the supporting systems that are needed for the main generating unit to start, run, and stop safely. Ancillary systems are plant-wide support systems (station services, safety, handling) that are not part of the energy conversion itself. For a 100 MW plant with Francis turbines (assume 2 × 50 MW or 3 units), they are as follows.
Mechanical auxiliary systems
| System | Function |
|---|---|
| Governor and oil pressure unit | Moves wicket gates to control speed/load; accumulator stores oil pressure |
| Main inlet valve (butterfly/spherical) with hydraulic unit | Isolates the turbine from the penstock; emergency closure |
| Cooling water system | Cools generator air coolers, bearings, transformer (via heat exchangers); pumps, filters, strainers |
| Lubrication / bearing oil system | Lubricates thrust and guide bearings; high-pressure oil lifting during start |
| Brake and jacking system | Stops the rotor at low speed; lifts the rotor for inspection |
| Drainage and dewatering system | Removes leakage water; empties draft tube and spiral case for maintenance |
| Compressed air system | Brakes, governor accumulator air, tools, (synchronous condenser mode) |
| Shaft seal water | Prevents water leakage at the turbine shaft |
Electrical auxiliary systems
| System | Function |
|---|---|
| Excitation system and AVR | Field current, voltage and var control |
| Generator neutral grounding | Limits earth-fault current |
| Station service AC (UAT, station transformer, 415 V boards) | Power to all auxiliaries |
| Emergency diesel generator | Black start and backup supply |
| DC system (battery + chargers) | Protection, control, emergency loads |
| Protection, control, SCADA and synchronising | Safe automatic operation |
| Metering and communication (PLCC, fibre) | Energy accounting, dispatch link |
Ancillary systems
| System | Function |
|---|---|
| Fire detection and fighting (CO2 for generator, water spray for transformer, hydrants) | Safety from fire |
| Heating, ventilation and air conditioning | Keeps powerhouse and control room within temperature/humidity limits |
| EOT crane in powerhouse | Erection and maintenance of heavy parts |
| Lighting and emergency lighting | Normal and safe operation |
| Earthing and lightning protection | Personnel and equipment safety |
| Water supply and sewerage, oil handling and purification | Plant services |
| Workshop, stores, CCTV and security | Maintenance and safety |
| Intake and gate control, desander flushing, trash rack cleaning | Water conveyance operation |
In addition, the plant provides ancillary services to the grid: frequency regulation, reactive power/voltage support, spinning reserve and black start.
- 2079 Shrawan · 8 marks
Write down the different types of high voltage bus bar with appropriate line diagram. Write the advantages and disadvantages of main and transfer bus bar.
Answer
A busbar is a conductor in a switchyard to which incoming and outgoing circuits are connected. Its arrangement decides reliability, flexibility of maintenance and cost.
Types of HV busbar arrangement
1. Single bus: all circuits on one bus. Cheap, but any bus fault or maintenance shuts down everything.
L1 L2 L3
| | |
[CB] [CB] [CB]
==+=====+=====+== bus
[CB] [CB]
| |
G1 T1
2. Sectionalised single bus: bus split by a bus-section breaker; a fault affects only one section.
3. Main and transfer bus: each circuit normally on the main bus; a bus coupler (transfer) breaker can take over any one feeder whose breaker is under maintenance.
Main bus ===+========+========+===
| | |
[CB] [CB] [BC] coupler
| | |
Transfer bus ---+--/ ----+--/ ----+---
| bypass isolator
L1 L2
4. Double bus (double bus single breaker): two main buses; each circuit can be connected to either bus through isolators, with a bus coupler.
Bus-1 ===+=========+=====+===
| | [BC]
Bus-2 ===+=========+=====+===
| (isolators)
[CB] [CB]
L1 L2
5. Double bus double breaker: each circuit has two breakers, one to each bus. Very reliable, costly.
6. Breaker-and-a-half (one-and-half breaker): three breakers for two circuits between two buses. Common at 220 kV and 400 kV.
7. Ring (mesh) bus: breakers form a closed loop; each circuit between two breakers.
Main and transfer bus: advantages
- Any feeder breaker can be taken out for maintenance without interrupting that feeder (it is fed through the transfer bus and bus coupler).
- Low cost compared with double bus or breaker-and-a-half: only one extra breaker.
- Simple layout and protection.
- Suitable for 33–132 kV substations.
Main and transfer bus: disadvantages
- A fault on the main bus or its maintenance shuts down the whole substation (no second main bus).
- Only one breaker at a time can be bypassed.
- Protection of the transferred feeder must be switched to the bus coupler, so switching is more complex and error-prone.
- More isolators and switching operations; needs interlocking.
- 2079 Jestha · 8 marks
Discuss the different types of busbar layout used in substation with suitable circuit diagram.
Answer
The busbar layout of a substation is the arrangement of buses, breakers and isolators that connects incoming and outgoing circuits. The choice is a trade-off between reliability, operational flexibility, maintenance and cost.
1. Single busbar
L1 L2 L3
[CB] [CB] [CB]
==+======+======+==
[CB] [CB]
T1 T2
Cheap and simple. A bus fault or bus maintenance causes a full outage. Used for small 11/33 kV substations.
2. Sectionalised single busbar
==+====+==[BS]==+====+==
L1 T1 L2 T2
A bus-section breaker (BS) divides the bus, so a fault takes out only half.
3. Main and transfer busbar
Main ===+=======+=======+===
[CB] [CB] [BC]
Trans ---+-------+-------+---
L1 L2
Any one feeder breaker can be maintained using the transfer bus and bus coupler (BC). A main-bus fault still causes full outage.
4. Double busbar (with bus coupler)
Bus-1 ===+======+======+===
| | [BC]
Bus-2 ===+======+======+===
[CB] [CB]
L1 L2
Circuits can be split between buses; either bus can be maintained. Common at 132 kV and 220 kV in Nepal.
5. Breaker-and-a-half
Bus-1 ==+==============+==
[CB] [CB]
+-- L1 L3 --+
[CB] [CB]
+-- L2 L4 --+
[CB] [CB]
Bus-2 ==+==============+==
Three breakers for two circuits. Any breaker or bus can be taken out without loss of supply. Used at 220–400 kV.
6. Ring (mesh) bus
L1 --+--[CB]--+-- L2
| |
[CB] [CB]
| |
L4 --+--[CB]--+-- L3
Each circuit sits between two breakers. Economical for 4–6 circuits, but protection is complex and an open ring reduces reliability.
Comparison
| Layout | Reliability | Cost | Use |
|---|---|---|---|
| Single | Low | Lowest | Small 11/33 kV |
| Sectionalised | Medium | Low | Distribution |
| Main + transfer | Medium | Moderate | 33–132 kV |
| Double bus | High | High | 132–220 kV |
| Breaker-and-half | Very high | Very high | 220–400 kV |
| Ring | High | Moderate | Small HV stations |
- 2070 Bhadra · 8 marks
Develop a typical specification while procuring a generator to be used in power plant design.
Answer
A generator specification is the technical document, part of the tender (bid) documents, that tells manufacturers exactly what generator the project needs. It covers the rating, design, performance, standards, tests and supply scope, so that bids can be compared on equal terms and the delivered machine fits the plant. A typical specification for a hydro generator (example: a 12.5 MVA unit) is set out below.
1. General and standards
- Scope: design, manufacture, testing at works, packing, transport to site, erection supervision and commissioning of 2 sets of three-phase synchronous generators with excitation and accessories.
- Standards: IEC 60034-1 (rating and performance), IEC 60034-3/-33 (hydro generators), IEC 60085 (insulation), IEC 60034-4 (test methods).
- Site conditions: altitude (e.g. 1200 m above MSL), ambient temperature (0–40 °C), humidity, seismic zone (Nepal: horizontal acceleration about 0.3 g), indoor powerhouse.
2. Rating and electrical data
| Item | Typical value |
|---|---|
| Type | 3-phase, salient-pole synchronous, vertical shaft |
| Rated output | 12.5 MVA at 0.85 pf lagging (10.625 MW) |
| Rated voltage / range | 11 kV ± 5% |
| Frequency | 50 Hz ± 2% (Nepal) |
| Rated speed / runaway speed | 600 rpm (10 poles) / withstand runaway for 15 min |
| Connection | Star, neutral brought out |
| Sub-transient reactance | ≤ 0.22 pu (unsaturated) |
| Short-circuit ratio | ≥ 1.0 |
| Efficiency | ≥ 97.5% at rated load (guaranteed, with penalty) |
| Insulation class / temperature rise | Class F insulation, Class B temperature rise |
| Inertia constant H / GD² | As required by governor stability, e.g. H ≥ 2.5 s |
| Capability | Continuous at rated MVA from 0.85 lag to 0.95 lead pf |
| Overload / unbalance | 10% for 1 h; continuous ≥ 10%, ≥ 20 s |
| Harmonics, TIF | THD of voltage < 5%, TIF as per IEC |
3. Mechanical and construction
- Stator: laminated low-loss steel, class F VPI insulated winding, RTDs (6 per phase) in slots.
- Rotor: salient poles with damper winding, designed for runaway speed.
- Bearings: thrust and guide bearings with oil coolers and RTDs; insulated against shaft currents.
- Cooling: closed-circuit air with air-to-water coolers (one spare cooler), or open ventilation for small sets.
- Brakes and jacks, space heaters, fire protection (CO₂ or water spray), vibration probes.
- Noise ≤ 85 dB(A) at 1 m.
4. Excitation and auxiliaries
- Static (or brushless) excitation with digital AVR, PSS, limiters (OEL, UEL, V/Hz), field flashing, field breaker.
- Ceiling voltage ≥ 1.6 pu, response time < 0.1 s.
- Neutral grounding equipment (NGT with resistor), surge arresters and surge capacitors, CTs and PTs, terminal and neutral cubicles.
5. Tests, documents and commercial items
- Type and routine tests at works: winding resistance, insulation resistance and PI, HV withstand, open- and short-circuit characteristics, reactances, heat run, overspeed, vibration.
- Site tests: dry-out, polarisation index, HV test, commissioning tests (load rejection).
- Documents: guaranteed technical particulars (GTP), drawings, O&M manuals, capability curve, test reports.
- Spares (one set of poles, bearing pads, coolers), tools, training.
- Delivery period, warranty (e.g. 24 months after commissioning), guaranteed efficiency with liquidated damages for shortfall, payment terms and price (FOB/CIF).
- 2079 Shrawan · 4 marks
Make a tentative an example type quotation of a high voltage side "circuit breaker" for power evacuation purpose at switch yard of a hydropower project that has installed capacity about 48 MW and line length to grid point substation is about 15 km.
Answer
A tentative quotation lists the technical data, quantity and price of the breaker so that the developer can budget and compare offers. Assumptions: 48 MW plant with 2 × 24 MW units, evacuation at 132 kV over 15 km by a double-circuit line, so the switchyard has 2 transformer bays and 2 line bays.
Rated current check: A, so a standard 1250 A rating is ample.
QUOTATION (example, indicative prices)
To: XYZ Hydropower Ltd., Kathmandu. Ref: 132 kV switchyard circuit breakers. Validity: 90 days.
| S.N. | Description | Qty | Unit price (NPR) | Amount (NPR) |
|---|---|---|---|---|
| 1 | 145 kV, 3-pole, outdoor SF6 live-tank circuit breaker, 1250 A, 31.5 kA for 3 s, making 80 kA peak, BIL 650 kVp, spring-charged mechanism, O-0.3 s-CO-3 min-CO, single-pole operation for auto-reclose (line bays), 110 V DC control, SF6 density monitor, support structure | 4 | 55,00,000 | 2,20,00,000 |
| 2 | Spares: trip/close coils, gas filling kit, density monitor | 1 lot | – | 5,00,000 |
| 3 | Supervision of erection and testing at site | 1 lot | – | 6,00,000 |
| Subtotal | 2,31,00,000 | |||
| VAT 13% | 30,03,000 | |||
| Grand total | 2,61,03,000 |
Terms:
- Standards: IEC 62271-100; type test reports enclosed.
- Delivery: CIF Birgunj/site within 6 months of LC; packing for hill transport.
- Warranty: 24 months from commissioning; payment by LC (10% advance, 80% on delivery, 10% after commissioning).
Prices are only indicative for budgeting; actual prices come from competitive bids.
- 2078 Kartik · 6 marks
Make a tentative an example type quotation of a "Power Transformer" for power evacuation purpose from switch yard of a general medium size hydropower project situated in hilly region.
Answer
A tentative quotation for a power transformer gives the main technical particulars, scope, price and terms so that the developer can budget and compare offers. Assumed project: a medium hydropower plant of 2 × 12 MW in a hilly region (altitude about 1500 m), evacuating at 132 kV. One step-up transformer per unit.
Rating: MVA, so a standard 16 MVA unit is chosen.
Main technical particulars offered
| Item | Offered value |
|---|---|
| Type | 3-phase, oil-immersed, outdoor, two-winding step-up |
| Rating | 16 MVA ONAN / 20 MVA ONAF |
| Voltage ratio | 11 / 132 kV, off-circuit taps ±2 × 2.5% on HV |
| Vector group | YNd11 (HV neutral solidly earthed) |
| Impedance | 10% ± IEC tolerance |
| Frequency | 50 Hz |
| Insulation level (HV) | BIL 650 kVp, power frequency 275 kV (corrected for altitude) |
| Losses (guaranteed) | No-load ≤ 12 kW; load loss ≤ 85 kW at 75 °C |
| Temperature rise | Oil 50 K, winding 55 K (reduced for altitude above 1000 m, IEC 60076-2) |
| Accessories | Buchholz relay, PRV, OTI/WTI, MOG, silica gel breather, HV/LV bushings, bushing CTs, radiators, fans, marshalling box |
| Hill transport | Shipping weight limited to about 30 t; may ship oil-filled or -filled, radiators separate |
| Standard | IEC 60076 |
Price schedule (indicative)
| S.N. | Description | Qty | Unit price (NPR) | Amount (NPR) |
|---|---|---|---|---|
| 1 | 16/20 MVA, 11/132 kV power transformer as above, with first oil filling | 2 | 4,50,00,000 | 9,00,00,000 |
| 2 | Mandatory spares (bushings, gaskets, Buchholz relay) | 1 lot | – | 15,00,000 |
| 3 | Transport to site, supervision of erection and commissioning | 1 lot | – | 40,00,000 |
| Subtotal | 9,55,00,000 | |||
| VAT 13% | 1,24,15,000 | |||
| Grand total | 10,79,15,000 |
Commercial terms
- Delivery: 7–9 months after LC; FOR site; route survey by supplier.
- Tests: routine tests (ratio, vector group, losses, impedance, insulation) witnessed by the owner; type test reports (temperature rise, impulse) submitted.
- Loss capitalisation: bids are compared with the capitalised value of guaranteed losses; a penalty applies for excess losses.
- Warranty: 24 months after commissioning; payment by LC; validity 120 days.
Prices are only indicative for budgeting; actual prices come from competitive bids.
- 2082 Shrawan · 3+3+3+3+4+4 marks
A typical hydropower plant has the following details:
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 5.62 Qmax (Q0) 210.00 m³/s February 4.80 Q25% 24.23 m³/s March 4.55 Q45% 9.82 m³/s April 4.8 Q65% 4.7 m³/s May 5.90 Q85% 3.1 m³/s June 12.70 Q95% 2.17 m³/s July 42.98 Qmin 0.64 m³/s August 100.26 September 64.23 October 24.00 November 10.37 December 6.80
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 330 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 99% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 20 km Transmission voltage level 132 kV Generator voltage level 11 kV
Design a power plant so to obtain following parameters:
(i) Electrical power output or installed capacity taking design discharge as Q45%. [3]
(ii) Select numbers of units [3]
(iii) Select the type of turbine [3]
(iv) Show appropriate generator transformer scheme. [3]
(v) Draw single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start. [4]
(vi) Calculate the rating of the transmission line side circuit breaker (HVCB) to be used in your design. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given). The line is taken as a single circuit (not stated).
(i) Installed capacity at
Driest month = March (4.55 m³/s), so riparian release m³/s.
Answer: generator output = 25.144 MW; power delivered to the 132 kV bus = 24.892 MW.
(ii) Number of units
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 12.6 MW.
- Generator rating: MVA → 15 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 16 MVA, 11/132 kV, YNd11 (next standard size above 15 MVA).
Answer: installed capacity = 2 × 12.6 MW = 25.2 MW.
(iii) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 86.3 |
| 750 | 8 | 64.7 |
| 600 | 10 | 51.8 |
| 500 | 12 | 43.2 |
| 428.6 | 14 | 37.0 |
| 375 | 16 | 32.4 |
| 333.3 | 18 | 28.8 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 12.96 MW each.
(iv) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (15 MVA each, about 787 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
(v) Single line diagram
Line to grid (132 kV, 20 km)
|
[CB]
|
===+====+================+=== 132 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
ST1 ---+ +--- ST2
| |
[GCB] [GCB]
| |
(G1) (G2)
| |
[NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 15 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 21% |
| Step-up transformers T1–T2 | 16 MVA each, 11/132 kV, YNd11, = 9.15% |
| Station transformer ST1, ST2 | 400 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 250 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, single circuit, 20 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
Bus bar used in the SLD
- 132 kV switchyard: double main bus bar with a bus coupler. Each bay (transformer or line) can be put on either bus, so one bus can be maintained without shutting down the plant and a bus fault affects only the circuits on that bus. This is the NEA practice at 132 kV and above.
- 11 kV: no common bus (unit scheme); each generator connects to its transformer through the GCB.
(vi) Rating of the transmission line side circuit breaker (HVCB)
Per-unit reactances on 100 MVA base:
For a fault on the 132 kV bus, the plant and the grid feed in parallel:
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 132 kV system | 145 kV |
| Rated normal current | ≥ 175 A | 1250 A |
| Breaking capacity | 1288.3 MVA (5.63 kA) | 31.5 kA |
| Making capacity | 14.37 kA peak | 80 kA peak |
| BIL | – | 650 kVp |
| Type | – | SF6, outdoor, spring mechanism, 3-pole, single-pole tripping for auto-reclose |
Answer: HV bus fault level = 1288.3 MVA (5.63 kA); select a 145 kV, 1250 A, 31.5 kA SF6 circuit breaker. Of this, the plant itself contributes only 101.4 MVA; the rest comes from the grid, so the result depends on the assumed grid fault level.
- 2081 Chaitra · 3+3+3+3+4+4 marks
A typical hydropower plant has the following details:
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 6.90 Qmax (Q0) 218.00 m³/s February 5.86 Q25% 28.24 m³/s March 4.58 Q45% 9.80 m³/s April 3.55 Q65% 6.7 m³/s May 5.10 Q85% 4.1 m³/s June 17.70 Q95% 2.9 m³/s July 72.95 Qmin 1.64 m³/s August 120.26 September 98.23 October 25.05 November 8.38 December 7.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 300 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 99% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.92 mH/km Transmission line length 20 km Generator voltage level 11 kV
Design a power plant so to obtain following parameters:
(i) Installed capacity in MW taking design discharge as Q45% [3]
(ii) Select numbers of units [3]
(iii) Select the type of turbine [3]
(iv) Choose suitable generator transformer scheme. [3]
(v) Draw single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start. [4]
(vi) Calculate the rating of the generator circuit breaker (GCB) to be used in your design. [4]
[Charts attached: turbine head-range table; turbine application chart for higher head (head against flow with Pelton, Turgo and Francis envelopes); chart for lower head (Pelton, Turgo, Crossflow, Francis and Kaplan envelopes); specific speed against net head chart]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
Transmission voltage (not given)
Use Still's formula for the economical voltage (L in km, P in kW):
Still's value of 86.4 kV lies between 66 kV and 132 kV; choose 132 kV, single circuit, the NEA grid voltage, which also leaves room for future projects in the area.
(i) Installed capacity in MW at
Driest month = April (3.55 m³/s), so riparian release m³/s.
Answer: generator output = 23.309 MW; power delivered to the 132 kV bus = 23.076 MW.
(ii) Number of units
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 11.7 MW.
- Generator rating: MVA → 14 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 16 MVA, 11/132 kV, YNd11 (next standard size above 14 MVA).
Answer: installed capacity = 2 × 11.7 MW = 23.4 MW.
(iii) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 93.6 |
| 750 | 8 | 70.2 |
| 600 | 10 | 56.2 |
| 500 | 12 | 46.8 |
| 428.6 | 14 | 40.1 |
| 375 | 16 | 35.1 |
| 333.3 | 18 | 31.2 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 12.02 MW each.
(iv) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (14 MVA each, about 735 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
(v) Single line diagram
Line to grid (132 kV, 20 km)
|
[CB]
|
===+====+================+=== 132 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
ST1 ---+ +--- ST2
| |
[GCB] [GCB]
| |
(G1) (G2)
| |
[NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 14 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 21% |
| Step-up transformers T1–T2 | 16 MVA each, 11/132 kV, YNd11, = 9.15% |
| Station transformer ST1, ST2 | 400 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 250 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, single circuit, 20 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
(vi) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
A unit-connected GCB sees the larger of two currents: (a) a fault on the transformer side fed by its own generator, (b) a fault on the generator side fed by the system through the unit transformer (grid plus the other units).
Design fault level for the GCB = larger value = 153.4 MVA.
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 919 A | 1250 A |
| Breaking capacity | 153.4 MVA (8.05 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 20.53 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 153.4 MVA; select a 12 kV, 1250 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2081 Shrawan · 2+3+3+4+4 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) Jan 4.68533 Qmax (Q0) 207.0024 m³/s Feb 3.867942 Q25% 18.2424 m³/s Mar 3.584017 Q45% 6.87999 m³/s Apr 4.553517 Q65% 4.706992 m³/s May 3.22678 Q85% 3.106132 m³/s Jun 12.77418 Q95% 2.17348 m³/s July 32.95867 Qmin 0.648732 m³/s Aug 40.26243 Sept 31.23782 Oct 15.05586 Nov 7.380238 Dec 4.858522
Parameter Value Gross head 220 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5.00% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9% Transmission line inductance 0.95 mH/km Transmission line length 25 km Generator voltage level 11 kV Transmission voltage level and no. of circuits Use optimal one
Design a hydro power plant so as to obtain the following parameters.
a) Installed capacity taking design discharge as Q45%. [2]
b) Select the number of unit and turbine type. [3]
c) Select the type of turbine. [3]
d) Draw the single line diagram showing number of units, generator, power transformer and station transformer. [4]
e) Calculate the rating of generator circuit breaker to be used in your design. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
Optimal transmission voltage and number of circuits
Use Still's formula for the economical voltage (L in km, P in kW):
The nearest standard voltage is 66 kV. Line current at 66 kV: A, which a single ACSR Dog or Wolf circuit carries easily. Choose 66 kV, single circuit: an 11.8 MW plant does not justify the extra cost of a second circuit, and 33 kV would give high losses and voltage drop over 25 km.
a) Installed capacity at
Driest month = May (3.22678 m³/s), so riparian release m³/s.
Answer: generator output = 11.737 MW; power delivered to the 66 kV bus = 11.502 MW.
b) Number of units (turbine type in part c)
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 5.9 MW.
- Generator rating: MVA → 7 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 8 MVA, 11/66 kV, YNd11 (next standard size above 7 MVA).
Answer: installed capacity = 2 × 5.9 MW = 11.8 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 97.9 |
| 750 | 8 | 73.4 |
| 600 | 10 | 58.7 |
| 500 | 12 | 48.9 |
| 428.6 | 14 | 42.0 |
| 375 | 16 | 36.7 |
| 333.3 | 18 | 32.6 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (16 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 375 rpm, about 6.05 MW each.
d) Single line diagram
Line to grid (66 kV, 25 km)
|
[CB]
|
===+=====+=============+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 7 MVA, 11 kV, 0.85 pf, 375 rpm, = 21% |
| Step-up transformers T1–T2 | 8 MVA each, 11/66 kV, YNd11, = 9% |
| Station transformer ST | 200 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 125 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, single circuit, 25 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 459 A | 630 A |
| Breaking capacity | 186.6 MVA (9.79 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 24.97 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 186.6 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2080 Chaitra · 3+2+3+4+4 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 13.5 Qmax (Q0) 149.00 m³/s February 8.6 Q25% 72.5 m³/s March 6.58 Q45% 22.87 m³/s April 7.5 Q65% 12.7 m³/s May 12.8 Q85% 8.70 m³/s June 25.7 Q95% 7.1 m³/s July 72.5 Qmin 5.05 m³/s August 101.2 September 81.3 October 27.05 November 21.38 December 14.35
Turbine type Head range (m) Kaplan and Propeller 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300 Michell-Banki 3 < H < 250 Turgo 50 < H < 250
Parameter Value Gross head 310 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 99% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 30 km Transmission voltage level As required Generator voltage level 11 kV Transmission circuit Choose appropriately as required (single or double)
(Please make your own smart assumption if needed beside given data above)
Design a power plant project so as to obtain following,
a) Installed capacity with design discharge as Q45% and appropriate number of units. [3]
b) Choose the appropriate type of Generator lead. [2]
c) Choose your generator transformer scheme mentioning the reasons. [3]
d) Make single line diagram for the project choosing earthing system, excitation system and bus bar system. [4]
e) Find Rating of high voltage circuit breaker of the project. [4]
[Charts attached: turbine head-range table; turbine application chart of head (m) against flow (m³/s) with Pelton, Turgo and Francis envelopes and power lines from 20 kW to 20 MW; low-head chart with Pelton, Turgo, Crossflow, Francis and Kaplan envelopes; specific speed against net head chart for Bulbo, Helice, Kaplan, Francis, Crossflow and Pelton; turbine efficiency against Q/Q0 curves for Full Kaplan, Pelton, Francis, Crossflow and Fixed propeller]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
Transmission voltage and circuits (assumed as required)
Use Still's formula for the economical voltage (L in km, P in kW):
Choose 132 kV, the nearest standard voltage, with a double-circuit line so that the 56.7 MW output is not lost when one circuit trips (N-1 security).
a) Installed capacity at
Driest month = March (6.58 m³/s), so riparian release m³/s.
Answer: generator output = 56.644 MW; power delivered to the 132 kV bus = 56.078 MW.
a) (contd.) Number of units
- Choose 3 units. A plant of this size would need very large single machines with only two units, which are hard to transport on Nepal's hill roads; three units also let the plant follow the large seasonal change in flow (one or two units in the dry months, all three in the wet months).
- Loss of one unit (forced outage or maintenance) removes only one third of the output.
- Per unit: m³/s, generator output MW → rate each unit at 18.9 MW.
- Generator rating: MVA → 22.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 25 MVA, 11/132 kV, YNd11 (next standard size above 22.5 MVA).
Answer: installed capacity = 3 × 18.9 MW = 56.7 MW.
Type of turbine (for unit speed)
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 114.4 |
| 750 | 8 | 85.8 |
| 600 | 10 | 68.6 |
| 500 | 12 | 57.2 |
| 428.6 | 14 | 49.0 |
| 375 | 16 | 42.9 |
| 333.3 | 18 | 38.1 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (18 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 750 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 3 × vertical-axis 4-jet Pelton turbines, 333.3 rpm, about 19.47 MW each.
b) Type of generator lead
Generator full-load current: A.
Choose a segregated phase bus duct (SPBD) from the generator terminals to the GCB and the step-up transformer LV side.
- About 1181 A is too high for a practical number of parallel cables (several runs per phase, poor current sharing, many terminations).
- An isolated phase bus duct (IPB) is used for very large machines (above about 3000–4000 A, i.e. more than about 60–100 MVA at 11 kV); it is not needed here.
- SPBD has each phase in its own compartment of an earthed metal enclosure, so a phase-to-phase fault is very unlikely, it is compact, self-cooled and low-maintenance.
- Rating: 12 kV, 1600 A continuous, short-time withstand ≥ the GCB rating (25 kA for 1 s), aluminium bars, with tap-off for the station transformer, surge capacitors and PTs.
c) Generator–transformer scheme and reasons
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (22.5 MVA each, about 1181 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
d) Single line diagram with earthing, excitation and bus bar
Line-1 Line-2 (132 kV, 30 km)
| |
[CB] [CB]
| |
===+===+===========+===========+=== 132 kV bus
| | |
[CB] [CB] [CB]
| | |
(T1) (T2) (T3)
| | |
ST1 ---+ + +--- ST2
| | |
[GCB] [GCB] [GCB]
| | |
(G1) (G2) (G3)
| | |
[NGT] [NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G3 | 22.5 MVA, 11 kV, 0.85 pf, 333.3 rpm, = 21% |
| Step-up transformers T1–T3 | 25 MVA each, 11/132 kV, YNd11, = 9.15% |
| Station transformer ST1, ST2 | 1000 kVA, 11/0.4 kV, Dyn11, 5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 625 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, double circuit, 30 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
Choices shown on the SLD: earthing – each generator neutral through a neutral grounding transformer with secondary resistor (high-resistance earthing, fault current about 10 A), the HV star of each GSU solidly earthed, and all equipment bonded to the powerhouse/switchyard earth mat; excitation – static (thyristor) excitation fed from an excitation transformer at each generator terminal, with field flashing from the 110 V DC battery (fast response for a large grid-connected unit); bus bar – 132 kV double main bus with bus coupler, two line bays for the double-circuit line.
e) Rating of high voltage circuit breaker
Per-unit reactances on 100 MVA base:
For a fault on the 132 kV bus, the plant and the grid feed in parallel:
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 132 kV system | 145 kV |
| Rated normal current | ≥ 410 A | 1250 A |
| Breaking capacity | 1552.0 MVA (6.79 kA) | 31.5 kA |
| Making capacity | 17.31 kA peak | 80 kA peak |
| BIL | – | 650 kVp |
| Type | – | SF6, outdoor, spring mechanism, 3-pole, single-pole tripping for auto-reclose |
Answer: HV bus fault level = 1552.0 MVA (6.79 kA); select a 145 kV, 1250 A, 31.5 kA SF6 circuit breaker. Of this, the plant itself contributes only 230.9 MVA; the rest comes from the grid, so the result depends on the assumed grid fault level.
- 2079 Chaitra · 1+2+3+2+4+4 marks
A typical hydropower plant has the following details:
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 3.30 Qmax (Q0) 110.00 m³/s February 2.20 Q25% 16.42 m³/s March 1.40 Q45% 6.82 m³/s April 1.00 Q65% 3.7 m³/s May 3.50 Q85% 2.10 m³/s June 6.00 Q95% 1.17 m³/s July 14.00 Qmin 0.64 m³/s August 35.00 September 24.00 October 12.00 November 7.50 December 5.00
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 95 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 20% Transformer reactance 11% Transmission line inductance 0.77 mH/km Transmission line length 80 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Single circuit
Design a hydro power plant so as to obtain following parameters
a) Electrical power output taking design discharge as Q65%. [1]
b) Select the numbers of unit and installed capacity. [2]
c) Select the type of turbine. [3]
d) Select the type of bus bar to be used. [2]
e) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start. [4]
f) Calculate the rating of generator circuit breaker and high voltage circuit breaker in your design. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = April (1 m³/s), so riparian release m³/s.
Answer: generator output = 2.782 MW; power delivered to the 66 kV bus = 2.727 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 1.4 MW.
- Generator rating: MVA → 2 MVA, 11 kV, 0.85 pf, 50 Hz.
- One step-up transformer for both units: 4 MVA, 11/66 kV, YNd11 (next standard size above 4 MVA).
Answer: installed capacity = 2 × 1.4 MW = 2.8 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 136.1 |
| 750 | 8 | 102.1 |
| 600 | 10 | 81.7 |
| 500 | 12 | 68.1 |
| 428.6 | 14 | 58.4 |
| 375 | 16 | 51.1 |
| 333.3 | 18 | 45.4 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (6 poles): , which is in the medium Francis range. A Pelton would need many jets (single-jet far above 30), and Kaplan is ruled out because the head is above 40 m.
Answer: 2 × vertical-axis Francis turbines, 1000 rpm, about 1.43 MW each.
d) Type of bus bar
- 11 kV: single bus bar; the two small generators and the transformer feeder are connected to it through VCB panels.
- 66 kV: single bus bar with one transformer bay and one line bay.
Reason: the plant is only 2.8 MW with one line, so a simple single bus is the most economical; an outage of the bus means loss of a small block of power only, and maintenance can be planned for the dry season.
e) Single line diagram
Line to grid (66 kV, 80 km)
|
[CB]
|
===+======+=== 66 kV bus
|
[CB]
|
(T1)
|
[CB]
|
===+======+======+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
===========================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 2 MVA, 11 kV, 0.85 pf, 1000 rpm, = 20% |
| Step-up transformer T1 | 4 MVA, 11/66 kV, YNd11, = 11% |
| Station transformer ST | 100 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 62.5 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, single circuit, 80 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
f) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 131 A | 630 A |
| Breaking capacity | 50.4 MVA (2.64 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 6.74 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 50.4 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
f) (contd.) Rating of HV circuit breaker
For a fault on the 66 kV bus, the plant and the grid feed in parallel:
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 66 kV system | 72.5 kV |
| Rated normal current | ≥ 44 A | 630 A |
| Breaking capacity | 196.6 MVA (1.72 kA) | 25 kA |
| Making capacity | 4.39 kA peak | 63 kA peak |
| BIL | – | 325 kVp |
| Type | – | SF6, outdoor, spring mechanism, 3-pole |
Answer: HV bus fault level = 196.6 MVA (1.72 kA); select a 72.5 kV, 630 A, 25 kA SF6 circuit breaker. Of this, the plant itself contributes only 12.9 MVA; the rest comes from the grid, so the result depends on the assumed grid fault level.
- 2079 Shrawan · 3+2+3+4+4 marks
A typical hydro power plant has the following details
Month Discharge (m³/s) Flow duration Discharge (m³/s) Baishakh 6.26 Qmax (Q0) 157.00 m³/s Jestha 12.45 Q25% 18.24 m³/s Ashad 32.12 Q40% 12.85 m³/s Shrawan 49.08 Q65% 10.7 m³/s Bhadra 44.47 Q85% 6.40 m³/s Ashoj 23.88 Q95% 4.91 m³/s Kartik 11.57 Qmin 3.35 m³/s Mangsir 7.2 Poush 5.06 Magh 4.1 Falgun 3.69 Chaitra 4.25
Turbine type Head range (m) Kaplan and Propeller 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300 Michell-Banki 3 < H < 250 Turgo 50 < H < 250
Parameter Value Gross head 589 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 99% Head loss 4% Riparian release 10% of driest flow Generator sub-transient reactance 18% Transformer reactance 7.15% Transmission line inductance 0.95 mH/km Transmission line length 12 km Transmission voltage level 132 kV Generator voltage level 11 kV Transmission circuit Double circuit
(Please make your own smart assumption if needed beside given data above)
Design a power plant project so as to obtain following
a) Electrical power output taking design discharge as Q40%. [3]
b) Select the numbers of units and installed capacity. [2]
c) Recommend the appropriate type of Generator-transformer scheme. [3]
d) Make single line diagram for the project choosing your generator transformer scheme and bus bar system. [4]
e) Find MVA rating of a generator circuit breaker of the project. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 4% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = Falgun (3.69 m³/s), so riparian release m³/s.
Answer: generator output = 61.111 MW; power delivered to the 132 kV bus = 60.500 MW.
b) Number of units and installed capacity
- Choose 3 units. A plant of this size would need very large single machines with only two units, which are hard to transport on Nepal's hill roads; three units also let the plant follow the large seasonal change in flow (one or two units in the dry months, all three in the wet months).
- Loss of one unit (forced outage or maintenance) removes only one third of the output.
- Per unit: m³/s, generator output MW → rate each unit at 20.4 MW.
- Generator rating: MVA → 24 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 25 MVA, 11/132 kV, YNd11 (next standard size above 24 MVA).
Answer: installed capacity = 3 × 20.4 MW = 61.2 MW.
Type of turbine (for unit speed)
m is above the Francis limit (350 m), so only a Pelton turbine is possible; specific speed fixes the speed and number of jets.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 52.6 |
| 750 | 8 | 39.4 |
| 600 | 10 | 31.5 |
| 500 | 12 | 26.3 |
| 428.6 | 14 | 22.5 |
| 375 | 16 | 19.7 |
| 333.3 | 18 | 17.5 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (8 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
The Pelton also keeps high efficiency at part load and handles sediment well.
Answer: 3 × vertical-axis 4-jet Pelton turbines, 750 rpm, about 21.00 MW each.
c) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (24 MVA each, about 1260 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
d) Single line diagram
Line-1 Line-2 (132 kV, 12 km)
| |
[CB] [CB]
| |
===+===+===========+===========+=== 132 kV bus
| | |
[CB] [CB] [CB]
| | |
(T1) (T2) (T3)
| | |
ST1 ---+ + +--- ST2
| | |
[GCB] [GCB] [GCB]
| | |
(G1) (G2) (G3)
| | |
[NGT] [NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G3 | 24 MVA, 11 kV, 0.85 pf, 750 rpm, = 18% |
| Step-up transformers T1–T3 | 25 MVA each, 11/132 kV, YNd11, = 7.15% |
| Station transformer ST1, ST2 | 1000 kVA, 11/0.4 kV, Dyn11, 5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 625 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, double circuit, 12 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d) (contd.) Bus bar system
- 132 kV switchyard: double main bus bar with a bus coupler. Each bay (transformer or line) can be put on either bus, so one bus can be maintained without shutting down the plant and a bus fault affects only the circuits on that bus. This is the NEA practice at 132 kV and above.
- 11 kV: no common bus (unit scheme); each generator connects to its transformer through the GCB.
e) MVA rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
A unit-connected GCB sees the larger of two currents: (a) a fault on the transformer side fed by its own generator, (b) a fault on the generator side fed by the system through the unit transformer (grid plus the other units).
Design fault level for the GCB = larger value = 294.1 MVA.
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 1575 A | 1600 A |
| Breaking capacity | 294.1 MVA (15.44 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 39.37 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 294.1 MVA; select a 12 kV, 1600 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2079 Jestha · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) Jan 11.95 Qmax (Q0) 674.19 m³/s Feb 9.94 Q25% 48.90 m³/s Mar 9.20 Q45% 16.75 m³/s Apr 11.93 Q65% 9.34 m³/s May 8.48 Q85% 6.21 m³/s Jun 42.28 Q95% 4.38 m³/s July 120.98 Qmin 1.40 m³/s Aug 143.00 Sep 110.27 Oct 50.95 Nov 24.66 Dec 16.17
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 120 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 15% Transformer reactance 12% Transmission line inductance 0.96 mH/km Transmission line length 20 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Single circuit
Design a power plant so as to obtain the following parameters
i) Electrical power output taking design discharge as Q45%
ii) Select the numbers of units and installed capacity with suitable reasons
iii) Draw the single line diagram showing numbers of units, generators, power transformer, station transformer and diesel generator for black start
iv) Select the type of turbine
v) Select the type of busbar with suitable reasons
vi) Calculate the MVA level of LV bus, MV bus and HV bus
vii) Calculate the rating of CB to be used in your design.
(Assume suitable data if required)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 500 MVA at the 33 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
i) Electrical power output at
Driest month = May (8.48 m³/s), so riparian release m³/s.
Answer: generator output = 15.525 MW; power delivered to the 33 kV bus = 15.215 MW.
ii) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 7.8 MW.
- Generator rating: MVA → 9.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 10 MVA, 11/33 kV, YNd11 (next standard size above 9.5 MVA).
Answer: installed capacity = 2 × 7.8 MW = 15.6 MW.
iii) Single line diagram
Line to grid (33 kV, 20 km)
|
[CB]
|
===+=====+=============+=== 33 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 9.5 MVA, 11 kV, 0.85 pf, 600 rpm, = 15% |
| Step-up transformers T1–T2 | 10 MVA each, 11/33 kV, YNd11, = 12% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 33 kV, single circuit, 20 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
iv) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 240.2 |
| 750 | 8 | 180.1 |
| 600 | 10 | 144.1 |
| 500 | 12 | 120.1 |
| 428.6 | 14 | 102.9 |
| 375 | 16 | 90.1 |
| 333.3 | 18 | 80.0 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (10 poles): , which is in the medium Francis range. A Pelton would need many jets (single-jet far above 30), and Kaplan is ruled out because the head is above 40 m.
Answer: 2 × vertical-axis Francis turbines, 600 rpm, about 8.00 MW each.
v) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 33 kV: single bus bar, sectionalised, with transformer bays and one line bay.
Reason: for a 15.6 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
vi) MVA level of LV, MV and HV buses
LV = 0.4 kV auxiliary bus, MV = 11 kV generator bus, HV = 33 kV switchyard bus. Station transformer 250 kVA, 4.5%.
Per-unit reactances on 100 MVA base:
| Bus | Fault MVA | (kA) |
|---|---|---|
| LV (0.4 kV) | 5.41 | 7.80 |
| MV (11 kV) | 200.5 | 10.52 |
| HV (33 kV) | 204.6 | 3.58 |
Answer: LV ≈ 5.41 MVA, MV ≈ 200.5 MVA, HV ≈ 204.6 MVA.
vii) Rating of circuit breakers
Breaking current from the bus fault levels above; making current = 2.55 × (IEC 62271-100); rated current ≥ 1.25 × full-load current.
| Breaker | Full-load current | Required breaking | Selected |
|---|---|---|---|
| GCB / 11 kV CBs | 499 A per generator | 200.5 MVA, 10.52 kA (make 26.8 kA) | 12 kV, 630 A, 25 kA VCB |
| HV CB (33 kV) | 350 A total | 204.6 MVA, 3.58 kA (make 9.1 kA) | 36 kV, 630 A, 16 kA SF6 |
| LV ACB (0.4 kV) | 361 A (station tr.) | 5.41 MVA, 7.80 kA (make 13.3 kA*) | 415 V, 630 A, 25 kA ACB |
*At 0.4 kV the making current uses the IEC 60947-2 factor n = 1.7 for this fault current.
Answer: 11 kV GCB: 12 kV, 630 A, 25 kA; 33 kV CB: 36 kV, 630 A, 16 kA; 0.4 kV ACB: 630 A, 25 kA.
- 2078 Chaitra · 3+2+3+4+4 marks
A typical hydro power plant has the following details
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 7.50 Qmax (Q0) 207.00 m³/s February 6.60 Q25% 28.24 m³/s March 5.58 Q45% 18.87 m³/s April 6.55 Q65% 13.7 m³/s May 8.8 Q85% 8.90 m³/s June 17.77 Q95% 7.91 m³/s July 56.95 Qmin 5.05 m³/s August 134.26 September 103.27 October 29.05 November 19.38 December 12.35
Turbine type Head range (m) Kaplan and Propeller 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300 Michell-Banki 3 < H < 250 Turgo 50 < H < 250
Parameter Value Gross head 360 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 19% Transformer reactance 8.15% Transmission line inductance 0.95 mH/km Transmission line length 22 km Transmission voltage level 132 kV Generator voltage level 11 kV Transmission circuit Double circuit
(Please make your own smart assumption if needed beside given data above)
Design a power plant project so as to obtain following
a) Electrical power output taking design discharge as Q45%. [3]
b) Select the numbers of units and installed capacity. [2]
c) Recommend the appropriate type of Generator-transformer scheme. [3]
d) Make single line diagram for the project choosing your generator transformer scheme and bus bar system. [4]
e) Find MVA Rating of a generator circuit breaker of the project. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = March (5.58 m³/s), so riparian release m³/s.
Answer: generator output = 53.635 MW; power delivered to the 132 kV bus = 52.562 MW.
b) Number of units and installed capacity
- Choose 3 units. A plant of this size would need very large single machines with only two units, which are hard to transport on Nepal's hill roads; three units also let the plant follow the large seasonal change in flow (one or two units in the dry months, all three in the wet months).
- Loss of one unit (forced outage or maintenance) removes only one third of the output.
- Per unit: m³/s, generator output MW → rate each unit at 17.9 MW.
- Generator rating: MVA → 21.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 25 MVA, 11/132 kV, YNd11 (next standard size above 21.5 MVA).
Answer: installed capacity = 3 × 17.9 MW = 53.7 MW.
Type of turbine (for unit speed)
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 92.3 |
| 750 | 8 | 69.2 |
| 600 | 10 | 55.4 |
| 500 | 12 | 46.2 |
| 428.6 | 14 | 39.6 |
| 375 | 16 | 34.6 |
| 333.3 | 18 | 30.8 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 3 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 18.43 MW each.
c) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (21.5 MVA each, about 1128 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
d) Single line diagram
Line-1 Line-2 (132 kV, 22 km)
| |
[CB] [CB]
| |
===+===+===========+===========+=== 132 kV bus
| | |
[CB] [CB] [CB]
| | |
(T1) (T2) (T3)
| | |
ST1 ---+ + +--- ST2
| | |
[GCB] [GCB] [GCB]
| | |
(G1) (G2) (G3)
| | |
[NGT] [NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G3 | 21.5 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 19% |
| Step-up transformers T1–T3 | 25 MVA each, 11/132 kV, YNd11, = 8.15% |
| Station transformer ST1, ST2 | 1000 kVA, 11/0.4 kV, Dyn11, 5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 625 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, double circuit, 22 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d) (contd.) Bus bar system
- 132 kV switchyard: double main bus bar with a bus coupler. Each bay (transformer or line) can be put on either bus, so one bus can be maintained without shutting down the plant and a bus fault affects only the circuits on that bus. This is the NEA practice at 132 kV and above.
- 11 kV: no common bus (unit scheme); each generator connects to its transformer through the GCB.
e) MVA rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
A unit-connected GCB sees the larger of two currents: (a) a fault on the transformer side fed by its own generator, (b) a fault on the generator side fed by the system through the unit transformer (grid plus the other units).
Design fault level for the GCB = larger value = 257.9 MVA.
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 1411 A | 1600 A |
| Breaking capacity | 257.9 MVA (13.53 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 34.51 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 257.9 MVA; select a 12 kV, 1600 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2078 Kartik · 3+3+2+4+4 marks
A typical hydro power plant has the following details
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 5.5 Qmax (Q0) 207.00 m³/s February 4.6 Q25% 28.24 m³/s March 3.58 Q45% 8.87 m³/s April 4.55 Q65% 5.7 m³/s May 4.8 Q85% 4.10 m³/s June 12.77 Q95% 2.91 m³/s July 39.95 Qmin 1.05 m³/s August 50.26 September 41.23 October 23.05 November 9.38 December 6.35
Turbine type Head range (m) Kaplan and Propeller 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300 Michell-Banki 3 < H < 250 Turgo 50 < H < 250
Parameter Value Gross head 260 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 30 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Double circuit
(Please make your own smart assumption if needed beside given data above)
Design a power plant project so as to obtain following
a) Electrical power output taking design discharge as Q45%. [3]
b) Select the numbers of units and installed capacity. [3]
c) Choose the appropriate type of Generator lead. [2]
d) Make single line diagram for the project choosing your generator transformer scheme and bus bar system. [4]
e) Find Rating of generator circuit breaker of the project. [4]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = March (3.58 m³/s), so riparian release m³/s.
Answer: generator output = 18.006 MW; power delivered to the 66 kV bus = 17.646 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 9.1 MW.
- Generator rating: MVA → 11 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 12.5 MVA, 11/66 kV, YNd11 (next standard size above 11 MVA).
Answer: installed capacity = 2 × 9.1 MW = 18.2 MW.
Type of turbine (for unit speed)
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 98.4 |
| 750 | 8 | 73.8 |
| 600 | 10 | 59.0 |
| 500 | 12 | 49.2 |
| 428.6 | 14 | 42.2 |
| 375 | 16 | 36.9 |
| 333.3 | 18 | 32.8 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (16 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 375 rpm, about 9.28 MW each.
c) Type of generator lead
Generator full-load current: A.
Choose 11 kV XLPE single-core copper cables (generator lead in cable trench/tray) or a non-segregated phase bus duct.
- At about 577 A, two runs per phase of 1C 240 mm² Cu XLPE cable (about 400–450 A per cable laid in trefoil after derating) carry the current with margin.
- Cables are cheap, flexible to route inside the powerhouse, and easy to terminate at the GCB panel and transformer.
- A bus duct (NSPBD/SPBD) becomes economic only for higher currents (above about 1000–1500 A); IPB only for very large units.
d) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (11 MVA each, about 577 A at 11 kV), the transmission voltage is 66 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
d) (contd.) Single line diagram
Line-1 Line-2 (66 kV, 30 km)
| |
[CB] [CB]
| |
===+====+==========+=====+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
ST1 ---+ +--- ST2
| |
[GCB] [GCB]
| |
(G1) (G2)
| |
[NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 11 MVA, 11 kV, 0.85 pf, 375 rpm, = 21% |
| Step-up transformers T1–T2 | 12.5 MVA each, 11/66 kV, YNd11, = 9.15% |
| Station transformer ST1, ST2 | 315 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 200 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, double circuit, 30 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d) (contd.) Bus bar system
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 66 kV: single bus bar, sectionalised, with transformer bays and two line bays (double circuit).
Reason: for a 18.2 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
A unit-connected GCB sees the larger of two currents: (a) a fault on the transformer side fed by its own generator, (b) a fault on the generator side fed by the system through the unit transformer (grid plus the other units).
Design fault level for the GCB = larger value = 108.7 MVA.
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 722 A | 800 A |
| Breaking capacity | 108.7 MVA (5.70 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 14.54 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 108.7 MVA; select a 12 kV, 800 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2077 Chaitra · 3+3+3+5+4+6 marks
A typical hydro power plant has the following details
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.15 Qmax (Q0) 120.00 m³/s February 3.60 Q25% 43.24 m³/s March 3.44 Q45% 16.17 m³/s April 3.89 Q65% 5.99 m³/s May 5.54 Q85% 4.40 m³/s June 16.67 Q95% 3.71 m³/s July 43.36 Qmin 2.65 m³/s August 53.29 September 37.84 October 16.56 November 8.15 December 5.53
Parameter Value Gross head 550 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 99% Head loss 4.5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 25 km Transmission voltage level 132 kV Generator voltage level 11 kV Transmission circuit Single circuit
(Please make your own smart assumption if needed beside given data above)
Design a power plant project so as to obtain following
a) Electrical power output taking design discharge as Q45%. [3]
b) Select the numbers of units and Turbine Type. [3]
c) What kind of Generator lead do you choose and why? [3]
d) Make single line diagram for the project choosing your generator transformer scheme and bus bar system. [5]
e) Find Rating of generator circuit breaker of the project. [4]
f) Make a tentative quotation for purchasing suitable "Generator Transformer" as per the requirement of the project. [6]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 4.5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 2,000 MVA at the 132 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = March (3.44 m³/s), so riparian release m³/s.
Answer: generator output = 71.981 MW; power delivered to the 132 kV bus = 71.261 MW.
b) Number of units
- Choose 3 units. A plant of this size would need very large single machines with only two units, which are hard to transport on Nepal's hill roads; three units also let the plant follow the large seasonal change in flow (one or two units in the dry months, all three in the wet months).
- Loss of one unit (forced outage or maintenance) removes only one third of the output.
- Per unit: m³/s, generator output MW → rate each unit at 24 MW.
- Generator rating: MVA → 28.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 31.5 MVA, 11/132 kV, YNd11 (next standard size above 28.5 MVA).
Answer: installed capacity = 3 × 24 MW = 72 MW.
b) (contd.) Turbine type
m is above the Francis limit (350 m), so only a Pelton turbine is possible; specific speed fixes the speed and number of jets.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 62.5 |
| 750 | 8 | 46.9 |
| 600 | 10 | 37.5 |
| 500 | 12 | 31.3 |
| 428.6 | 14 | 26.8 |
| 375 | 16 | 23.5 |
| 333.3 | 18 | 20.8 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (10 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
The Pelton also keeps high efficiency at part load and handles sediment well.
Answer: 3 × vertical-axis 4-jet Pelton turbines, 600 rpm, about 24.74 MW each.
c) Generator lead and reason
Generator full-load current: A.
Choose a segregated phase bus duct (SPBD) from the generator terminals to the GCB and the step-up transformer LV side.
- About 1496 A is too high for a practical number of parallel cables (several runs per phase, poor current sharing, many terminations).
- An isolated phase bus duct (IPB) is used for very large machines (above about 3000–4000 A, i.e. more than about 60–100 MVA at 11 kV); it is not needed here.
- SPBD has each phase in its own compartment of an earthed metal enclosure, so a phase-to-phase fault is very unlikely, it is compact, self-cooled and low-maintenance.
- Rating: 12 kV, 2000 A continuous, short-time withstand ≥ the GCB rating (25 kA for 1 s), aluminium bars, with tap-off for the station transformer, surge capacitors and PTs.
d) Generator–transformer scheme
Choose the unit scheme (one generator connected to its own step-up transformer, with a generator circuit breaker between them).
| Point | Unit scheme (chosen) | Common bus / group scheme |
|---|---|---|
| Fault level at 11 kV | Low (one machine only) | High (all machines in parallel) |
| Effect of a transformer fault | Only one unit lost | Whole plant may trip |
| Maintenance outage | One unit at a time | Common transformer outage stops all |
| 11 kV switchgear | Only GCB and short leads | Large 11 kV bus and breakers |
| Losses / efficiency | No 11 kV bus losses | More 11 kV copper losses |
| Cost | More transformers | Fewer, larger transformers |
Reasons: the units are large (28.5 MVA each, about 1496 A at 11 kV), the transmission voltage is 132 kV, and the unit scheme keeps the 11 kV fault level and generator-voltage switchgear small. The GCB lets the unit be synchronised and tripped at 11 kV while the station transformer, tapped between the GCB and the step-up transformer, stays fed from the grid (back-feed) when the unit is stopped.
d) (contd.) Single line diagram
Line to grid (132 kV, 25 km)
|
[CB]
|
===+===+===========+===========+=== 132 kV bus
| | |
[CB] [CB] [CB]
| | |
(T1) (T2) (T3)
| | |
ST1 ---+ + +--- ST2
| | |
[GCB] [GCB] [GCB]
| | |
(G1) (G2) (G3)
| | |
[NGT] [NGT] [NGT]
ST1, ST2 (11/0.4 kV)
| |
===+====[BS]=======+=== 0.4 kV aux bus
|
[ACB]
|
(DG) diesel set, black start
| Item | Rating |
|---|---|
| Generators G1–G3 | 28.5 MVA, 11 kV, 0.85 pf, 600 rpm, = 21% |
| Step-up transformers T1–T3 | 31.5 MVA each, 11/132 kV, YNd11, = 9.15% |
| Station transformer ST1, ST2 | 1250 kVA, 11/0.4 kV, Dyn11, 5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 750 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 132 kV, single circuit, 25 km to grid substation |
| NGT | neutral grounding transformer with secondary resistor (high-resistance earthing) |
| 132 kV bus | double main bus with bus coupler (drawn as one line) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d) (contd.) Bus bar system
- 132 kV switchyard: double main bus bar with a bus coupler. Each bay (transformer or line) can be put on either bus, so one bus can be maintained without shutting down the plant and a bus fault affects only the circuits on that bus. This is the NEA practice at 132 kV and above.
- 11 kV: no common bus (unit scheme); each generator connects to its transformer through the GCB.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
A unit-connected GCB sees the larger of two currents: (a) a fault on the transformer side fed by its own generator, (b) a fault on the generator side fed by the system through the unit transformer (grid plus the other units).
Design fault level for the GCB = larger value = 270.9 MVA.
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 1870 A | 2000 A |
| Breaking capacity | 270.9 MVA (14.22 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 36.26 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 270.9 MVA; select a 12 kV, 2000 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
f) Tentative quotation for the generator transformers
Requirement: 3 generator step-up transformers, one per unit (unit scheme), each above the generator rating of 28.5 MVA, so 31.5 MVA, 11/132 kV units are quoted. The site is in a hilly region, so weight and size must suit hill-road transport.
| Item | Offered particulars |
|---|---|
| Type | 3-phase, oil-immersed, outdoor, two-winding step-up (GSU) |
| Rating | 31.5 MVA ONAN/ONAF (ONAF rating about 25% higher) |
| Voltage ratio | 11 kV / 132 kV, off-circuit taps ±2 × 2.5% on HV |
| Vector group | YNd11, HV neutral solidly earthed |
| Impedance | 9.15% (as used in the fault study) ± IEC tolerance |
| Insulation (HV) | BIL 650 kVp, 275 kV power frequency; altitude corrected |
| Guaranteed losses | No-load and load losses stated; capitalised in bid evaluation |
| Accessories | Buchholz, PRV, OTI/WTI, MOG, breather, bushing CTs for REF/differential, fans, marshalling box |
| Standard | IEC 60076 |
| S.N. | Description | Qty | Unit price (NPR) | Amount (NPR) |
|---|---|---|---|---|
| 1 | 31.5 MVA, 11/132 kV GSU transformer as above, with oil | 3 | 6,50,00,000 | 19,50,00,000 |
| 2 | Mandatory spares (bushings, gaskets, relays) | 1 lot | – | 25,00,000 |
| 3 | Transport to site, erection supervision, testing | 1 lot | – | 60,00,000 |
| Subtotal | 20,35,00,000 | |||
| VAT 13% | 2,64,55,000 | |||
| Grand total | 22,99,55,000 |
Terms: delivery 8–10 months after LC to site; routine tests witnessed, type test reports supplied; warranty 24 months after commissioning; payment by LC; validity 120 days. Prices are indicative for budgeting only; actual prices come from competitive bids.
- 2075 Bhadra · 2+2+4+4+4 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 5.2 Qmax (Q0) 211.00 m³/s February 3.86 Q25% 18.24 m³/s March 3.58 Q45% 7.00 m³/s April 4.55 Q65% 4.70 m³/s May 3.20 Q85% 3.10 m³/s June 12.77 Q95% 2.17 m³/s July 32.95 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.05 November 7.38 December 4.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 280 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 99% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.92 mH/km Transmission line length 30 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45% [2]
b) Select the numbers of units and installed capacity [2]
c) Select and Recommend suitable turbine [4]
d) Draw the single line diagram showing generators, power transformers, station transformer and diesel generator for black start [4]
e) Calculate the rating of generator circuit breaker to be used in your design [4]
(Assume suitable data if necessary and necessary graph is attached herewith)
[Chart attached: turbine efficiency (%) against Q/Q0 for Full Kaplan, Pelton, Francis, Crossflow and Fixed propeller]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3.2 m³/s), so riparian release m³/s.
Answer: generator output = 15.387 MW; power delivered to the 66 kV bus = 15.233 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 7.7 MW.
- Generator rating: MVA → 9.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 10 MVA, 11/66 kV, YNd11 (next standard size above 9.5 MVA).
Answer: installed capacity = 2 × 7.7 MW = 15.4 MW.
c) Selection and recommendation of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 82.9 |
| 750 | 8 | 62.2 |
| 600 | 10 | 49.7 |
| 500 | 12 | 41.5 |
| 428.6 | 14 | 35.5 |
| 375 | 16 | 31.1 |
| 333.3 | 18 | 27.6 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (12 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 500 rpm, about 7.93 MW each.
From the efficiency versus curves: Pelton and full Kaplan stay above about 85% down to 20–30% flow, while Francis drops sharply below about 40–50% flow and a fixed propeller is the worst. Since this plant runs at part flow for much of the year, the flat Pelton curve supports the choice.
d) Single line diagram
Line-1 Line-2 (66 kV, 30 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 9.5 MVA, 11 kV, 0.85 pf, 500 rpm, = 21% |
| Step-up transformers T1–T2 | 10 MVA each, 11/66 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, double circuit, 30 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 623 A | 630 A |
| Breaking capacity | 242.7 MVA (12.74 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 32.48 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 242.7 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2074 Magh · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.62 Qmax (Q0) 210.00 m³/s February 3.80 Q25% 18.24 m³/s March 3.55 Q45% 7.82 m³/s April 4.55 Q65% 4.7 m³/s May 3.5 Q85% 3.10 m³/s June 12.70 Q95% 2.17 m³/s July 32.98 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.00 November 7.37 December 4.80
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 230 m Turbine efficiency 90% Generator efficiency 96% Transformer efficiency 99% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 55 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%.
b) Select the numbers of units and installed capacity.
c) Select the type of turbine.
d) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start.
e) Calculate the rating of the generator circuit breaker (GCB) to be used in your design.
(Assume suitable data if necessary and necessary graph is attached herewith)
[Charts attached: turbine selection chart of discharge against head with Kaplan, Francis and Pelton envelopes; specific speed against net head chart; Pelton turbine efficiency curves for 1 to 4 injectors]
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 500 MVA at the 33 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3.5 m³/s), so riparian release m³/s.
Answer: generator output = 13.834 MW; power delivered to the 33 kV bus = 13.696 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 7 MW.
- Generator rating: MVA → 8.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 10 MVA, 11/33 kV, YNd11 (next standard size above 8.5 MVA).
Answer: installed capacity = 2 × 7 MW = 14 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 101.0 |
| 750 | 8 | 75.8 |
| 600 | 10 | 60.6 |
| 500 | 12 | 50.5 |
| 428.6 | 14 | 43.3 |
| 375 | 16 | 37.9 |
| 333.3 | 18 | 33.7 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (16 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 375 rpm, about 7.21 MW each.
d) Single line diagram
Line-1 Line-2 (33 kV, 55 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 33 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8.5 MVA, 11 kV, 0.85 pf, 375 rpm, = 21% |
| Step-up transformers T1–T2 | 10 MVA each, 11/33 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 33 kV, double circuit, 55 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 558 A | 630 A |
| Breaking capacity | 151.8 MVA (7.97 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 20.32 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 151.8 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2074 Bhadra · 16 marks
A typical hydro power plant has following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.92 Qmax (Q0) 211.00 m³/s February 3.86 Q25% 18.24 m³/s March 3.58 Q45% 6.80 m³/s April 4.55 Q65% 4.70 m³/s May 3.0 Q85% 3.10 m³/s June 12.77 Q95% 2.17 m³/s July 32.95 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.02 November 7.38 December 4.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 250 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 35 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%.
b) Select the numbers of units and installed capacity.
c) Select the type of turbine.
d) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start.
e) Suggest the type of bus bar to be used.
f) Calculate the rating of the generator circuit breaker to be used in your design.
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3 m³/s), so riparian release m³/s.
Answer: generator output = 13.368 MW; power delivered to the 66 kV bus = 13.100 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 6.7 MW.
- Generator rating: MVA → 8 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 8 MVA, 11/66 kV, YNd11 (next standard size above 8 MVA).
Answer: installed capacity = 2 × 6.7 MW = 13.4 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 89.0 |
| 750 | 8 | 66.8 |
| 600 | 10 | 53.4 |
| 500 | 12 | 44.5 |
| 428.6 | 14 | 38.2 |
| 375 | 16 | 33.4 |
| 333.3 | 18 | 29.7 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 6.89 MW each.
d) Single line diagram
Line-1 Line-2 (66 kV, 35 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 21% |
| Step-up transformers T1–T2 | 8 MVA each, 11/66 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, double circuit, 35 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 66 kV: single bus bar, sectionalised, with transformer bays and two line bays (double circuit).
Reason: for a 13.4 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
f) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 525 A | 630 A |
| Breaking capacity | 202.5 MVA (10.63 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 27.10 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 202.5 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2073 Magh · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.9 Qmax (Q0) 211.00 m³/s February 3.86 Q25% 18.24 m³/s March 3.58 Q45% 7.20 m³/s April 4.55 Q65% 4.70 m³/s May 3.00 Q85% 3.10 m³/s June 12.77 Q95% 2.17 m³/s July 32.95 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.05 November 7.38 December 4.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 245 m Turbine efficiency 91% Generator efficiency 98% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.9 mH/km Transmission line length 50 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%
b) Select the numbers of units and installed capacity
c) Select the type of turbine
d) Draw the single line diagram showing generators, power transformers, station transformer and a stand by generator for black start
e) Calculate the rating of generator circuit breaker to be used in your design. (Assume suitable data if necessary and necessary graph is attached herewith)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3 m³/s), so riparian release m³/s.
Answer: generator output = 14.050 MW; power delivered to the 66 kV bus = 13.769 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 7.1 MW.
- Generator rating: MVA → 8.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 10 MVA, 11/66 kV, YNd11 (next standard size above 8.5 MVA).
Answer: installed capacity = 2 × 7.1 MW = 14.2 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 93.1 |
| 750 | 8 | 69.8 |
| 600 | 10 | 55.9 |
| 500 | 12 | 46.6 |
| 428.6 | 14 | 39.9 |
| 375 | 16 | 34.9 |
| 333.3 | 18 | 31.0 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 7.17 MW each.
d) Single line diagram (standby diesel generator for black start)
Line-1 Line-2 (66 kV, 50 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8.5 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 21% |
| Step-up transformers T1–T2 | 10 MVA each, 11/66 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, double circuit, 50 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 558 A | 630 A |
| Breaking capacity | 219.9 MVA (11.54 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 29.43 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 219.9 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2073 Bhadra · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) Jan 6.13 Qmax (Q0) 449.46 m³/s Feb 5.10 Q25% 32.60 m³/s Mar 4.72 Q45% 11.17 m³/s Apr 6.12 Q65% 6.23 m³/s May 4.35 Q85% 4.14 m³/s Jun 21.68 Q95% 2.92 m³/s July 62.04 Qmin 0.93 m³/s Aug 73.37 Sep 56.55 Oct 26.13 Nov 12.65 Dec 8.24
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 120 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 20% Transformer reactance 15% Transmission line inductance 0.95 mH/km Transmission line length 35 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Single circuit
Design a power plant so as to obtain the following parameters:
a. Electrical power output taking design discharge as Q45%
b. Select the numbers of units and installed capacity with suitable reasons
c. Draw the single line diagram showing numbers of units, generators, power transformer, station transformer and diesel generator for black start
d. Select the type of turbine
e. Select the type of busbar with suitable reasons
f. Calculate the MVA level of LV bus, MV bus and HV bus
g. Calculate the rating of CB to be used in your design.
(Assume suitable data if required and the necessary graph is attached herewith)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a. Electrical power output at
Driest month = May (4.35 m³/s), so riparian release m³/s.
Answer: generator output = 10.481 MW; power delivered to the 66 kV bus = 10.271 MW.
b. Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 5.3 MW.
- Generator rating: MVA → 6.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 8 MVA, 11/66 kV, YNd11 (next standard size above 6.5 MVA).
Answer: installed capacity = 2 × 5.3 MW = 10.6 MW.
c. Single line diagram
Line to grid (66 kV, 35 km)
|
[CB]
|
===+=====+=============+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 6.5 MVA, 11 kV, 0.85 pf, 750 rpm, = 20% |
| Step-up transformers T1–T2 | 8 MVA each, 11/66 kV, YNd11, = 15% |
| Station transformer ST | 160 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 100 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, single circuit, 35 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d. Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 197.3 |
| 750 | 8 | 148.0 |
| 600 | 10 | 118.4 |
| 500 | 12 | 98.7 |
| 428.6 | 14 | 84.6 |
| 375 | 16 | 74.0 |
| 333.3 | 18 | 65.8 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (8 poles): , which is in the medium Francis range. A Pelton would need many jets (single-jet far above 30), and Kaplan is ruled out because the head is above 40 m.
Answer: 2 × vertical-axis Francis turbines, 750 rpm, about 5.40 MW each.
e. Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 66 kV: single bus bar, sectionalised, with transformer bays and one line bay.
Reason: for a 10.6 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
f. MVA level of LV, MV and HV buses
LV = 0.4 kV auxiliary bus, MV = 11 kV generator bus, HV = 66 kV switchyard bus. Station transformer 160 kVA, 4.5%.
Per-unit reactances on 100 MVA base:
| Bus | Fault MVA | (kA) |
|---|---|---|
| LV (0.4 kV) | 3.47 | 5.01 |
| MV (11 kV) | 143.3 | 7.52 |
| HV (66 kV) | 334.7 | 2.93 |
Answer: LV ≈ 3.47 MVA, MV ≈ 143.3 MVA, HV ≈ 334.7 MVA.
g. Rating of circuit breakers
Breaking current from the bus fault levels above; making current = 2.55 × (IEC 62271-100); rated current ≥ 1.25 × full-load current.
| Breaker | Full-load current | Required breaking | Selected |
|---|---|---|---|
| GCB / 11 kV CBs | 341 A per generator | 143.3 MVA, 7.52 kA (make 19.2 kA) | 12 kV, 630 A, 25 kA VCB |
| HV CB (66 kV) | 140 A total | 334.7 MVA, 2.93 kA (make 7.5 kA) | 72.5 kV, 630 A, 25 kA SF6 |
| LV ACB (0.4 kV) | 231 A (station tr.) | 3.47 MVA, 5.01 kA (make 7.5 kA*) | 415 V, 400 A, 25 kA ACB |
*At 0.4 kV the making current uses the IEC 60947-2 factor n = 1.5 for this fault current.
Answer: 11 kV GCB: 12 kV, 630 A, 25 kA; 66 kV CB: 72.5 kV, 630 A, 25 kA; 0.4 kV ACB: 400 A, 25 kA.
- 2072 Magh · 32 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.62 Qmax (Q0) 210.00 m³/s February 3.80 Q25% 18.24 m³/s March 3.55 Q45% 7.82 m³/s April 4.55 Q65% 4.7 m³/s May 3.5 Q85% 3.10 m³/s June 12.70 Q95% 2.17 m³/s July 32.98 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.00 November 7.37 December 4.80
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 250 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 55 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q25%.
b) Select the numbers of units and installed capacity.
c) Select the type of turbine.
d) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start.
e) Suggest the type of bus bar to be used
f) Calculate the rating of the generator circuit breaker (GCB) to be used in your design
(Assume suitable data if necessary and necessary graph is attached herewith)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 500 MVA at the 33 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3.5 m³/s), so riparian release m³/s.
Answer: generator output = 36.388 MW; power delivered to the 33 kV bus = 35.660 MW.
b) Number of units and installed capacity
- Choose 3 units. A plant of this size would need very large single machines with only two units, which are hard to transport on Nepal's hill roads; three units also let the plant follow the large seasonal change in flow (one or two units in the dry months, all three in the wet months).
- Loss of one unit (forced outage or maintenance) removes only one third of the output.
- Per unit: m³/s, generator output MW → rate each unit at 12.2 MW.
- Generator rating: MVA → 14.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 16 MVA, 11/33 kV, YNd11 (next standard size above 14.5 MVA).
Answer: installed capacity = 3 × 12.2 MW = 36.6 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 119.9 |
| 750 | 8 | 90.0 |
| 600 | 10 | 72.0 |
| 500 | 12 | 60.0 |
| 428.6 | 14 | 51.4 |
| 375 | 16 | 45.0 |
| 333.3 | 18 | 40.0 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (18 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 750 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 3 × vertical-axis 4-jet Pelton turbines, 333.3 rpm, about 12.50 MW each.
d) Single line diagram
Line-1 Line-2 (33 kV, 55 km)
| |
[CB] [CB]
| |
===+===+===========+===========+=== 33 kV bus
| | |
[CB] [CB] [CB]
| | |
(T1) (T2) (T3)
| | |
[CB] [CB] [CB]
| | |
=======+===[BS]====+===========+=========+=== 11 kV bus
| | | |
[GCB] [GCB] [GCB] [CB]
| | | |
(G1) (G2) (G3) (ST)
|
=========================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G3 | 14.5 MVA, 11 kV, 0.85 pf, 333.3 rpm, = 21% |
| Step-up transformers T1–T3 | 16 MVA each, 11/33 kV, YNd11, = 9.15% |
| Station transformer ST | 630 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 400 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 33 kV, double circuit, 55 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 33 kV: single bus bar, sectionalised, with transformer bays and two line bays (double circuit).
Reason: for a 36.6 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
f) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 951 A | 1250 A |
| Breaking capacity | 294.5 MVA (15.46 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 39.42 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 294.5 MVA; select a 12 kV, 1250 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2072 Asoj · 32 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) Jan 6.13 Qmax (Q0) 449.46 m³/s Feb 5.10 Q25% 32.60 m³/s Mar 4.72 Q45% 11.17 m³/s Apr 6.12 Q65% 6.23 m³/s May 4.35 Q85% 4.14 m³/s Jun 21.68 Q95% 2.92 m³/s July 62.04 Qmin 0.93 m³/s Aug 73.37 Sep 56.55 Oct 26.13 Nov 12.65 Dec 8.24
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 150 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 15% Transformer reactance 12% Transmission line inductance 0.97 mH/km Transmission line length 35 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Single circuit
Design a power plant so as to obtain the following parameters:
a. Electrical power output taking design discharge as Q45%
b. Select the numbers of units and installed capacity with suitable reasons
c. Draw the single line diagram showing numbers of units, generators, power transformer, station transformer and diesel generator for black start
d. Select the type of turbine
e. Select the type of busbar with suitable reasons
f. Calculate the MVA level of LV bus, MV bus and HV bus
g. Calculate the rating of CB to be used in your design.
(Assume suitable data if required and the necessary graph is attached herewith)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a. Electrical power output at
Driest month = May (4.35 m³/s), so riparian release m³/s.
Answer: generator output = 13.101 MW; power delivered to the 66 kV bus = 12.839 MW.
b. Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 6.6 MW.
- Generator rating: MVA → 8 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 8 MVA, 11/66 kV, YNd11 (next standard size above 8 MVA).
Answer: installed capacity = 2 × 6.6 MW = 13.2 MW.
c. Single line diagram
Line to grid (66 kV, 35 km)
|
[CB]
|
===+=====+=============+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8 MVA, 11 kV, 0.85 pf, 750 rpm, = 15% |
| Step-up transformers T1–T2 | 8 MVA each, 11/66 kV, YNd11, = 12% |
| Station transformer ST | 200 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 125 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, single circuit, 35 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
d. Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 166.9 |
| 750 | 8 | 125.2 |
| 600 | 10 | 100.1 |
| 500 | 12 | 83.5 |
| 428.6 | 14 | 71.5 |
| 375 | 16 | 62.6 |
| 333.3 | 18 | 55.6 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (8 poles): , which is in the medium Francis range. A Pelton would need many jets (single-jet far above 30), and Kaplan is ruled out because the head is above 40 m.
Answer: 2 × vertical-axis Francis turbines, 750 rpm, about 6.75 MW each.
e. Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 66 kV: single bus bar, sectionalised, with transformer bays and one line bay.
Reason: for a 13.2 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
f. MVA level of LV, MV and HV buses
LV = 0.4 kV auxiliary bus, MV = 11 kV generator bus, HV = 66 kV switchyard bus. Station transformer 200 kVA, 4.5%.
Per-unit reactances on 100 MVA base:
| Bus | Fault MVA | (kA) |
|---|---|---|
| LV (0.4 kV) | 4.35 | 6.27 |
| MV (11 kV) | 198.0 | 10.39 |
| HV (66 kV) | 349.2 | 3.06 |
Answer: LV ≈ 4.35 MVA, MV ≈ 198.0 MVA, HV ≈ 349.2 MVA.
g. Rating of circuit breakers
Breaking current from the bus fault levels above; making current = 2.55 × (IEC 62271-100); rated current ≥ 1.25 × full-load current.
| Breaker | Full-load current | Required breaking | Selected |
|---|---|---|---|
| GCB / 11 kV CBs | 420 A per generator | 198.0 MVA, 10.39 kA (make 26.5 kA) | 12 kV, 630 A, 25 kA VCB |
| HV CB (66 kV) | 140 A total | 349.2 MVA, 3.06 kA (make 7.8 kA) | 72.5 kV, 630 A, 25 kA SF6 |
| LV ACB (0.4 kV) | 289 A (station tr.) | 4.35 MVA, 6.27 kA (make 10.7 kA*) | 415 V, 400 A, 25 kA ACB |
*At 0.4 kV the making current uses the IEC 60947-2 factor n = 1.7 for this fault current.
Answer: 11 kV GCB: 12 kV, 630 A, 25 kA; 66 kV CB: 72.5 kV, 630 A, 25 kA; 0.4 kV ACB: 400 A, 25 kA.
- 2071 Magh · 16 marks
A typical hydro power plant has the following details
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.9 Qmax (Q0) 211.00 m³/s February 3.86 Q25% 18.24 m³/s March 3.58 Q45% 6.80 m³/s April 4.55 Q65% 4.70 m³/s May 3.00 Q85% 3.10 m³/s June 12.77 Q95% 2.17 m³/s July 32.95 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.05 November 7.38 December 4.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 250 m Turbine efficiency 91% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.92 mH/km Transmission line length 35 km Transmission voltage level 66 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%
b) Select the numbers of units and installed capacity
c) Select the type of turbine
d) Draw the single line diagram showing generators, power transformers, station transformer and diesel generator for black start
e) Calculate the rating of generator circuit breaker to be used in your design
f) Suggest the type of bus bar to be used
(Assume suitable data if necessary and necessary graph is attached herewith)
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 1,000 MVA at the 66 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3 m³/s), so riparian release m³/s.
Answer: generator output = 13.368 MW; power delivered to the 66 kV bus = 13.100 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 6.7 MW.
- Generator rating: MVA → 8 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 8 MVA, 11/66 kV, YNd11 (next standard size above 8 MVA).
Answer: installed capacity = 2 × 6.7 MW = 13.4 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 89.0 |
| 750 | 8 | 66.8 |
| 600 | 10 | 53.4 |
| 500 | 12 | 44.5 |
| 428.6 | 14 | 38.2 |
| 375 | 16 | 33.4 |
| 333.3 | 18 | 29.7 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (14 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 428.6 rpm, about 6.89 MW each.
d) Single line diagram
Line-1 Line-2 (66 kV, 35 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 66 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8 MVA, 11 kV, 0.85 pf, 428.6 rpm, = 21% |
| Step-up transformers T1–T2 | 8 MVA each, 11/66 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 66 kV, double circuit, 35 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Rating of generator circuit breaker
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 525 A | 630 A |
| Breaking capacity | 203.1 MVA (10.66 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 27.18 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 203.1 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
f) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 66 kV: single bus bar, sectionalised, with transformer bays and two line bays (double circuit).
Reason: for a 13.4 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
- 2071 Bhadra · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.62 Qmax (Q0) 210.00 m³/s February 3.80 Q25% 18.24 m³/s March 3.55 Q45% 7.82 m³/s April 4.55 Q65% 4.7 m³/s May 3.5 Q85% 3.10 m³/s June 12.70 Q95% 2.17 m³/s July 32.98 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.00 November 7.37 December 4.80
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 230 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 45 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%.
b) Select the numbers of units and installed capacity.
c) Select the type of turbine.
d) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start.
e) Suggest the type of bus bar to be used.
f) Calculate the rating of the generator circuit breaker (GCB) to be used in your design.
Answer
Assumptions: riparian release = 10% of the driest monthly mean flow; net head = gross head minus 5% loss; kN/m³; generator power factor 0.85; base = 100 MVA. For fault levels the grid is taken as a source of 500 MVA at the 33 kV grid substation at the far end of the line (an assumed typical value, since grid data is not given).
a) Electrical power output at
Driest month = May (3.5 m³/s), so riparian release m³/s.
Answer: generator output = 13.978 MW; power delivered to the 33 kV bus = 13.699 MW.
b) Number of units and installed capacity
- Choose 2 units. With a run-of-river flow that falls well below the design flow in the dry months, one unit can run near full load on half the design flow, so efficiency stays high in winter.
- One unit can be maintained while the other runs, and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW → rate each unit at 7 MW.
- Generator rating: MVA → 8.5 MVA, 11 kV, 0.85 pf, 50 Hz.
- Step-up transformer, one per unit: 10 MVA, 11/33 kV, YNd11 (next standard size above 8.5 MVA).
Answer: installed capacity = 2 × 7 MW = 14 MW.
c) Type of turbine
m lies in the Francis (10–350 m) and Pelton (50–1300 m) ranges, so the specific speed decides.
Shaft power per unit kW. With (synchronous speeds) and , where :
| (rpm) | Poles | (metric, kW) |
|---|---|---|
| 1000 | 6 | 101.0 |
| 750 | 8 | 75.8 |
| 600 | 10 | 60.6 |
| 500 | 12 | 50.5 |
| 428.6 | 14 | 43.3 |
| 375 | 16 | 37.9 |
| 333.3 | 18 | 33.7 |
Usual ranges: Pelton about 10–30 per jet (multi-jet ), Francis about 60–300, Kaplan 300–1000.
Choose rpm (16 poles): . With 4 jets, , inside the Pelton range.
Check of jet ratio: jet velocity m/s; bucket speed ; runner diameter m; jet diameter m; , acceptable.
A Francis at 1000 rpm () is also possible, but the Pelton is preferred because (i) its efficiency stays nearly flat from about 20% to 100% load (jets can be switched off), which suits a run-of-river plant whose flow falls far below the design flow in the dry season, and (ii) it tolerates the heavy sediment of Himalayan rivers better, and worn buckets and needles are easier to repair.
Answer: 2 × vertical-axis 4-jet Pelton turbines, 375 rpm, about 7.21 MW each.
d) Single line diagram
Line-1 Line-2 (33 kV, 45 km)
| |
[CB] [CB]
| |
===+=====+=========+===+=== 33 kV bus
| |
[CB] [CB]
| |
(T1) (T2)
| |
[CB] [CB]
| |
=========+====[BS]=====+=========+=== 11 kV bus
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST)
|
=================================+===+ 0.4 kV
|
[ACB]
|
(DG) black start
| Item | Rating |
|---|---|
| Generators G1–G2 | 8.5 MVA, 11 kV, 0.85 pf, 375 rpm, = 21% |
| Step-up transformers T1–T2 | 10 MVA each, 11/33 kV, YNd11, = 9.15% |
| Station transformer ST | 250 kVA, 11/0.4 kV, Dyn11, 4.5% (aux load about 1.5% of capacity) |
| Diesel generator DG | 160 kVA, 0.4 kV (essential auxiliaries for black start) |
| Line | 33 kV, double circuit, 45 km to grid substation |
| NGR | neutral grounding resistor (low-resistance earthing, one generator earthed at a time if preferred) |
BS = bus section breaker, GCB = generator circuit breaker, ACB = air circuit breaker. Black start: with the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting and battery chargers), one unit is started and runs in island mode, and it then energises the step-up transformer and the line.
e) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker, units split between the two sections, so a bus fault or maintenance takes out only part of the plant.
- 33 kV: single bus bar, sectionalised, with transformer bays and two line bays (double circuit).
Reason: for a 14 MW plant a sectionalised single bus gives reasonable reliability at low cost; a double bus or main-and-transfer bus would cost much more and is normally used only for larger plants or grid substations.
f) Rating of generator circuit breaker (GCB)
Per-unit reactances on 100 MVA base:
All generators feed the common 11 kV bus, so the GCB is rated for the full 11 kV bus fault level (generators plus the grid through the step-up transformers):
| Parameter | Required | Selected |
|---|---|---|
| Rated voltage | 11 kV system | 12 kV |
| Rated normal current | ≥ 558 A | 630 A |
| Breaking capacity | 159.4 MVA (8.37 kA) | 25 kA (520 MVA at 12 kV) |
| Making capacity | 21.34 kA peak | 63 kA peak |
| Short-time current | – | 25 kA, 3 s |
| Type | – | Vacuum (or SF6), generator-duty tested (IEEE C37.013) |
Answer: GCB fault level = 159.4 MVA; select a 12 kV, 630 A, 25 kA generator circuit breaker. The margin covers the DC component and delayed current zeros of generator faults; surge arresters and surge capacitors are fitted at the generator terminals when a VCB is used.
- 2070 Magh · 16 marks
A typical hydro power plant has the following details:
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.62 Qmax (Q0) 207.00 m³/s February 3.80 Q25% 18.24 m³/s March 3.55 Q45% 6.82 m³/s April 4.55 Q65% 4.7 m³/s May 3.22 Q85% 3.10 m³/s June 12.70 Q95% 2.17 m³/s July 32.98 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.00 November 7.37 December 4.80
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 200 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 25 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%
b) Select the numbers of units and installed capacity
c) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start
d) Select the type of turbine
e) Suggest the type of bus bar to be used
f) Calculate the MVA level of LV bus, MV bus and HV bus
g) Calculate the rating of circuit breaker to be used in your design
(Assume suitable data if required and the necessary graph is attached herewith)
Answer
Take riparian release as 10% of the driest monthly mean flow, net head = gross head minus 5% loss, and two generating units. The grid's fault contribution is neglected because grid data is not given (only the plant's generators feed a fault).
a) Electrical power output at
Driest month = May (3.22 m³/s), so riparian release m³/s.
Answer: generator output = 10.573 MW; power delivered to the 33 kV bus = 10.362 MW.
b) Number of units and installed capacity
- Choose 2 units. The plant runs on , so in the dry season (flow below about ) one unit can still run near its best efficiency; one unit can be maintained while the other runs; and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW.
- Generator rating: 5.3 MW at 0.85 pf, i.e. MVA → 6.25 MVA, 11 kV, 50 Hz.
- Step-up transformer: one per unit, 6.3 MVA, 11/33 kV, YNd11, 9.15% (next standard size above 6.25 MVA).
Answer: installed capacity = 2 × 5.3 MW = 10.6 MW.
c) Single line diagram
Line-1 33 kV Line-2 33 kV
(25 km) (25 km)
| |
[CB] [CB]
| |
33 kV ==+=======[BS]========+==
| |
[CB] [CB]
| |
(T1) (T2)
11/33 kV 6.3 MVA 11/33 kV 6.3 MVA
| |
[CB] [CB]
| |
11 kV ==+=====[BS]======+===+===+==
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST) 11/0.4 kV
6.25 MVA 6.25 MVA 250 kVA
|
0.4 kV aux bus ===+===+==
|
[ACB]
|
(DG) 200 kVA
BS = bus section breaker; ST = station (auxiliary) transformer; DG = diesel generator for black start. With the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting, battery chargers), so a unit can be started without outside supply.
d) Selection of turbine
m lies in both the Francis (10–350 m) and Pelton (50–1300 m) ranges, so specific speed decides. Per-unit shaft power kW; take rpm (6-pole, 50 Hz synchronous speed).
A single-jet Pelton suits – (up to about 60–70 with multiple jets); a Francis suits –. falls in the slow-to-medium Francis range, and a Francis has good efficiency at this discharge per unit (about 3.249 m³/s).
Answer: 2 × vertical-axis Francis turbines, 1000 rpm.
e) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker. Each half carries one unit, so a bus fault or maintenance takes out only one unit.
- 33 kV switchyard: single bus bar, sectionalised, with one bay for each circuit of the double-circuit line. This is simple and cheap for a 10.6 MW, 2-unit plant. A double bus or main-and-transfer bus costs more and is normally used only in larger plants or grid nodes.
f) MVA (fault) level of the LV, MV and HV buses
Take LV = 0.4 kV auxiliary bus, MV = 11 kV generator bus, HV = 33 kV switchyard bus. Base = 10 MVA. Station transformer assumed 250 kVA, 4.5%.
| Fault location | Equivalent (pu) | Fault MVA | (kA) |
|---|---|---|---|
| MV bus (11 kV) | 59.5 | 3.12 | |
| HV bus (33 kV) | 41.6 | 0.727 | |
| LV bus (0.4 kV) | 5.08 | 7.33 |
Line check (remote end): per circuit, 3.731 Ω for both circuits in parallel. , so pu. Fault level at the far end of the line is MVA (0.636 kA).
Answer: LV ≈ 5.08 MVA, MV ≈ 59.5 MVA, HV ≈ 41.6 MVA.
g) Rating of circuit breakers
Making current = (peak, IEC 62271-100). Rated current ≥ 1.25 × full-load current.
| Item | Generator CB (11 kV) | HV line/transformer CB (33 kV) |
|---|---|---|
| Full-load current | A | 110 A per transformer, 220 A total |
| Required breaking | 3.12 kA (59.5 MVA) | 0.727 kA (41.6 MVA) |
| Required making | 7.97 kA peak | 1.85 kA peak |
| Selected rating | 12 kV, 630 A, 25 kA, VCB | 36 kV, 630 A, 25 kA, SF6 |
Answer: GCB: 12 kV, 630 A, breaking capacity ≥ 59.5 MVA (3.12 kA); 33 kV CB: 36 kV, 630 A, breaking capacity ≥ 41.6 MVA (0.727 kA). Standard 25 kA breakers are chosen because they cost little more and leave margin for the grid's fault contribution and future units.
- 2070 Bhadra · 16 marks
A typical hydro power plant has the following details.
Month Discharge (m³/s) Flow duration Discharge (m³/s) January 4.9 Qmax (Q0) 207.00 m³/s February 3.86 Q25% 18.24 m³/s March 3.58 Q45% 6.87 m³/s April 4.55 Q65% 4.7 m³/s May 3.22 Q85% 3.10 m³/s June 12.77 Q95% 2.17 m³/s July 32.95 Qmin 0.64 m³/s August 40.26 September 31.23 October 15.05 November 7.38 December 4.85
Turbine type Head range (m) Kaplan 2 < H < 40 Francis 10 < H < 350 Pelton 50 < H < 1300
Parameter Value Gross head 230 m Turbine efficiency 90% Generator efficiency 97% Transformer efficiency 98% Head loss 5% Riparian release 10% Generator sub-transient reactance 21% Transformer reactance 9.15% Transmission line inductance 0.95 mH/km Transmission line length 20 km Transmission voltage level 33 kV Generator voltage level 11 kV Transmission circuit Double circuit
Design a power plant so as to obtain the following parameters:
a) Electrical power output taking design discharge as Q45%
b) Select the numbers of units and installed capacity
c) Draw the single line diagram showing number of units, generator, power transformer, station transformer and diesel generator for black start
d) Select the type of turbine
e) Suggest the type of bus bar to be used
f) Calculate the MVA level of LV bus, MV bus and HV bus.
g) Calculate the rating of circuit breaker to be used in your design
(Assume suitable data if required and the necessary graph is attached herewith)
Answer
Take riparian release as 10% of the driest monthly mean flow, net head = gross head minus 5% loss, and two generating units. The grid's fault contribution is neglected because grid data is not given (only the plant's generators feed a fault).
a) Electrical power output at
Driest month = May (3.22 m³/s), so riparian release m³/s.
Answer: generator output = 12.253 MW; power delivered to the 33 kV bus = 12.008 MW.
b) Number of units and installed capacity
- Choose 2 units. The plant runs on , so in the dry season (flow below about ) one unit can still run near its best efficiency; one unit can be maintained while the other runs; and two units keep the number of machines (and cost) low for a plant of this size.
- Per unit: m³/s, generator output MW.
- Generator rating: 6.2 MW at 0.85 pf, i.e. MVA → 7.5 MVA, 11 kV, 50 Hz.
- Step-up transformer: one per unit, 8 MVA, 11/33 kV, YNd11, 9.15% (next standard size above 7.5 MVA).
Answer: installed capacity = 2 × 6.2 MW = 12.4 MW.
c) Single line diagram
Line-1 33 kV Line-2 33 kV
(20 km) (20 km)
| |
[CB] [CB]
| |
33 kV ==+=======[BS]========+==
| |
[CB] [CB]
| |
(T1) (T2)
11/33 kV 8 MVA 11/33 kV 8 MVA
| |
[CB] [CB]
| |
11 kV ==+=====[BS]======+===+===+==
| | |
[GCB] [GCB] [CB]
| | |
(G1) (G2) (ST) 11/0.4 kV
7.5 MVA 7.5 MVA 250 kVA
|
0.4 kV aux bus ===+===+==
|
[ACB]
|
(DG) 200 kVA
BS = bus section breaker; ST = station (auxiliary) transformer; DG = diesel generator for black start. With the grid dead, the DG energises the 0.4 kV auxiliary bus (governor oil pumps, cooling water, excitation field flashing, lighting, battery chargers), so a unit can be started without outside supply.
d) Selection of turbine
m lies in both the Francis (10–350 m) and Pelton (50–1300 m) ranges, so specific speed decides. Per-unit shaft power kW; take rpm (6-pole, 50 Hz synchronous speed).
A single-jet Pelton suits – (up to about 60–70 with multiple jets); a Francis suits –. falls in the slow-to-medium Francis range, and a Francis has good efficiency at this discharge per unit (about 3.274 m³/s).
Answer: 2 × vertical-axis Francis turbines, 1000 rpm.
e) Type of bus bar
- 11 kV: single bus bar with a bus-section breaker. Each half carries one unit, so a bus fault or maintenance takes out only one unit.
- 33 kV switchyard: single bus bar, sectionalised, with one bay for each circuit of the double-circuit line. This is simple and cheap for a 12.4 MW, 2-unit plant. A double bus or main-and-transfer bus costs more and is normally used only in larger plants or grid nodes.
f) MVA (fault) level of the LV, MV and HV buses
Take LV = 0.4 kV auxiliary bus, MV = 11 kV generator bus, HV = 33 kV switchyard bus. Base = 10 MVA. Station transformer assumed 250 kVA, 4.5%.
| Fault location | Equivalent (pu) | Fault MVA | (kA) |
|---|---|---|---|
| MV bus (11 kV) | 71.4 | 3.75 | |
| HV bus (33 kV) | 50.7 | 0.887 | |
| LV bus (0.4 kV) | 5.15 | 7.44 |
Line check (remote end): per circuit, 2.985 Ω for both circuits in parallel. , so pu. Fault level at the far end of the line is MVA (0.779 kA).
Answer: LV ≈ 5.15 MVA, MV ≈ 71.4 MVA, HV ≈ 50.7 MVA.
g) Rating of circuit breakers
Making current = (peak, IEC 62271-100). Rated current ≥ 1.25 × full-load current.
| Item | Generator CB (11 kV) | HV line/transformer CB (33 kV) |
|---|---|---|
| Full-load current | A | 140 A per transformer, 280 A total |
| Required breaking | 3.75 kA (71.4 MVA) | 0.887 kA (50.7 MVA) |
| Required making | 9.56 kA peak | 2.26 kA peak |
| Selected rating | 12 kV, 630 A, 25 kA, VCB | 36 kV, 630 A, 25 kA, SF6 |
Answer: GCB: 12 kV, 630 A, breaking capacity ≥ 71.4 MVA (3.75 kA); 33 kV CB: 36 kV, 630 A, breaking capacity ≥ 50.7 MVA (0.887 kA). Standard 25 kA breakers are chosen because they cost little more and leave margin for the grid's fault contribution and future units.
Questions from Old Question Collection (EE 753) (IOE EE 753 exam papers from 2070 Magh to 2082 Shrawan), Question bank (ioesolutions) (IOE EE 753 exam papers from 2070 Bhadra to 2074 Magh) and Old questions (NCE Library) (IOE EE 753 exam papers from 2070 Bhadra to 2080 Chaitra). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗