Variable head test, two soils
Short answer
Permeability of the second soil is found by subtracting time for the first soil alone to obtain the flow resistance in series. Result: k2 = 0.0224 mm/s (2.24×10−5 m/s).
In a variable head permeability test on a soil of length , the head of water in the standpipe takes 5 seconds to fall from 900 to 135 mm above the tail water level. When another soil of length = 60 mm is placed above the first soil, the time taken for the head to fall between the same limits is 150 seconds. The permeameter has a cross sectional area of 4560 mm² and a standpipe area of 130 mm². Calculate the permeability of the second soil.
Principle
For a variable head test, , so for given , , , , the time is , proportional to . When the second soil is placed on the first, the two act in series, so the flow resistances () add and the total time is the sum of the times for each soil taken alone.
Given
mm, mm, mm², mm², mm.
- Soil 1 alone: s
- Soil 1 + soil 2: s
- Time due to soil 2 alone: s
Permeability of soil 2
Answer: mm/s m/s.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Average permeability of layered soil · Soil Mechanics, chapter 6
- Consolidation test, 90% time, k, Cc · Soil Mechanics, chapter 9
- Constant head test, k at porosity 39% · Soil Mechanics, chapter 6
- UCS test soil type and parameters · Soil Mechanics, chapter 10
- USCS classification of soils A and B · Soil Mechanics, chapter 3
- Constant head permeameter, seepage velocity · Soil Mechanics, chapter 6
- Settling basin 60 m³/s, 0.15 mm, head 300 m · Hydropower Engineering, chapter 5 · asked 2×
- Time to lower level in two-orifice tank · Fluid Mechanics, chapter 6
- Settling basin 60 m³/s, 0.15 mm, head 100 m · Hydropower Engineering, chapter 5
- River crossing: minimum clearance above water · Transmission and Distribution System Design, chapter 4