Why flow routing, time-area method of routing

Short answer

Flow routing determines outflow hydrographs for design of spillways, flood forecasting, and protection works. The Time-Area method uses isochrones to translate excess rain to the outlet, with outflow Qn = (2.78/Δt) Σ r_i A_{n-i+1}, accounting only for translation (no storage), yielding a hydrograph that is too peaked.

Why is flow routing required? Explain Time-Area method of Routing.

Why flow routing is required

Flow routing finds the outflow hydrograph from a reach, reservoir, or catchment for a given inflow, accounting for storage. It is required for:

  • designing spillways, reservoir capacity, and flood-control works (the outflow peak controls the design);
  • flood forecasting and warning at downstream points (arrival time and peak);
  • designing flood protection works such as embankments, bridges, and culverts along a river;
  • studying how a flood changes (attenuation and lag) as it moves downstream;
  • obtaining a catchment hydrograph from rainfall, as in the time-area method.

Time-area method of routing

The time-area method routes excess rain over the catchment surface to the outlet, considering only translation.

  1. Draw isochrones at interval Δt\Delta t and find the strip areas A1,A2,…,ANA_1, A_2, \dots, A_N (NΔt=tcN\Delta t = t_c).
 Outlet
   *---- A1 (0 - dt)
   *---- A2 (dt - 2dt)
   *---- A3 (2dt - 3dt)  ... up to tc
  1. Divide the effective rainfall into blocks r1,r2,…r_1, r_2, \dots of duration Δt\Delta t (cm).
  2. Rain on strip AiA_i reaches the outlet after time iΔti\Delta t at a rate 2.78 r Ai/Δt2.78\,r\,A_i/\Delta t (m³/s). The ordinate at time nΔtn\Delta t is the sum of the contributions of all blocks:
Qn=2.78Δt∑i=1nri An−i+1Q_n = \frac{2.78}{\Delta t}\sum_{i=1}^{n} r_i\,A_{n-i+1}

For example, Q1=2.78 r1A1/ΔtQ_1 = 2.78\,r_1A_1/\Delta t, Q2=2.78 (r1A2+r2A1)/ΔtQ_2 = 2.78\,(r_1A_2 + r_2A_1)/\Delta t. 4. Plot QnQ_n against time for the direct runoff hydrograph; add base flow for the total flow.

Since storage is neglected, the hydrograph is too peaked. Clark's method corrects this by routing the result through a linear reservoir.