- 2079 Bhadra · 6 marks
Why flow routing, time-area method of routing
Short answer
Flow routing determines outflow hydrographs for design of spillways, flood forecasting, and protection works. The Time-Area method uses isochrones to translate excess rain to the outlet, with outflow Qn = (2.78/Δt) Σ r_i A_{n-i+1}, accounting only for translation (no storage), yielding a hydrograph that is too peaked.
Why is flow routing required? Explain Time-Area method of Routing.
Why flow routing is required
Flow routing finds the outflow hydrograph from a reach, reservoir, or catchment for a given inflow, accounting for storage. It is required for:
- designing spillways, reservoir capacity, and flood-control works (the outflow peak controls the design);
- flood forecasting and warning at downstream points (arrival time and peak);
- designing flood protection works such as embankments, bridges, and culverts along a river;
- studying how a flood changes (attenuation and lag) as it moves downstream;
- obtaining a catchment hydrograph from rainfall, as in the time-area method.
Time-area method of routing
The time-area method routes excess rain over the catchment surface to the outlet, considering only translation.
- Draw isochrones at interval and find the strip areas ().
Outlet
*---- A1 (0 - dt)
*---- A2 (dt - 2dt)
*---- A3 (2dt - 3dt) ... up to tc
- Divide the effective rainfall into blocks of duration (cm).
- Rain on strip reaches the outlet after time at a rate (m³/s). The ordinate at time is the sum of the contributions of all blocks:
For example, , . 4. Plot against time for the direct runoff hydrograph; add base flow for the total flow.
Since storage is neglected, the hydrograph is too peaked. Clark's method corrects this by routing the result through a linear reservoir.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Meaning of flow routing · Engineering Hydrology, chapter 7 · asked 3×
- Stream flow by slope-area method · Engineering Hydrology, chapter 4 · asked 3×
- Time area method for runoff hydrograph · Engineering Hydrology, chapter 7
- Time-area method with histogram, drawbacks · Engineering Hydrology, chapter 7
- Linear reservoir and Clark UH from time-area · Engineering Hydrology, chapter 7
- Muskingum routing, K=10, x=0.20 · Engineering Hydrology, chapter 7 · asked 2×
- Maximum time step, kinematic wave routing · Computational Techniques in Civil Engineering, chapter 5
- Routing, flow control and dynamic routing · Telecommunications, chapter 8
- River flow required for 1500 population · Sanitary Engineering, chapter 6
- Steam nozzle 4 MPa: mass flow, exit velocity, area · Fundamental of Thermodynamics & Heat Transfer, chapter 4