- 2072 Chaitra · 8 marks
Muskingum routing, k=10 h, x=0.2 (table missing)
Short answer
Muskingum routing with C0=0.0909, C1=0.4545, C2=0.4545 and initial outflow 10 m³/s yields peak outflow 51.33 m³/s at 30 h, peak attenuation 8.67 m³/s, and lag 12 h.
Route the following flood hydrograph through a river reach for which Muskingum coefficient k = 10 h and x = 0.2. At the start of inflow flood, the outflow discharge is 10 m/sec. [Inflow table, time 0 to 54 h at 6 h interval, is cut off in the scan.]
Assumption: the inflow table is cut off in the question. The inflow ordinates are assumed to be the standard set for this problem (10, 20, 50, 60, 55, 45, 35, 27, 20, 15 m³/s at 6 h intervals from 0 to 54 h). If your table differs, use the same coefficients and the same steps with your values.
Method
Muskingum routing: , where
Here h, , h, so h.
Check: .
Routing table
| t (h) | I | C0·I2 | C1·I1 | C2·O1 | O (m³/s) |
|---|---|---|---|---|---|
| 0 | 10.00 | - | - | - | 10.00 |
| 6 | 20.00 | 1.82 | 4.55 | 4.55 | 10.91 |
| 12 | 50.00 | 4.55 | 9.09 | 4.96 | 18.60 |
| 18 | 60.00 | 5.45 | 22.73 | 8.45 | 36.63 |
| 24 | 55.00 | 5.00 | 27.27 | 16.65 | 48.92 |
| 30 | 45.00 | 4.09 | 25.00 | 22.24 | 51.33 |
| 36 | 35.00 | 3.18 | 20.45 | 23.33 | 46.97 |
| 42 | 27.00 | 2.45 | 15.91 | 21.35 | 39.71 |
| 48 | 20.00 | 1.82 | 12.27 | 18.05 | 32.14 |
| 54 | 15.00 | 1.36 | 9.09 | 14.61 | 25.06 |
Peak attenuation and lag
- Peak inflow = 60 m³/s at t = 18 h
- Peak outflow = 51.33 m³/s at t = 30 h
- Attenuation of peak = 60 − 51.33 = 8.67 m³/s (14.5 % of the inflow peak)
- Lag of peak = 30 − 18 = 12 h (to the nearest time step)
Related questions
- Muskingum routing at Chovar, Bagmati River · Engineering Hydrology, chapter 7
- Muskingum routing, K=10, x=0.20 · Engineering Hydrology, chapter 7 · asked 2×
- Muskingum routing, K=8 h, X=0.25 · Engineering Hydrology, chapter 7
- Muskingum routing, K=12 h, X=0.20 · Engineering Hydrology, chapter 7 · asked 2×
- Reservoir routing through spillway, 6-hr inflow · Engineering Hydrology, chapter 7
- Muskingum routing, K=36 hr, x=0.15 · Engineering Hydrology, chapter 7
- ERR from separate inflow and outflow rows · Engineering Economics, chapter 3
- Cut-off and time-current characteristics of fuse · Switchgear and Protection, chapter 3
- Prospective current, cut-off current, time delay fuse · Switchgear and Protection, chapter 3
- Gravity dam equilibrium and overtopping discharge coefficient · Hydropower Engineering, chapter 4