Hardy-Cross network discharge AB, BC, AD, CD

Short answer

Use Hardy-Cross method with Hazen-Williams equation. After iterations, final discharges: AB = 20.97 lps, BC = 0.97 lps, AD = 34.03 lps, CD = 9.03 lps from D to C.

Calculate the discharge in pipes AB, BC, AD and CD for the water distribution network given below by using Hardy-cross method. The available data of network are as follows:

PipeLength (in meter)Diameter (in mm)
AB400300
BC300200
AD500400
CD500300

Hazen Williams coefficient as 100 for all pipes. Assume other necessary data suitably.

[Figure: loop ABCD; 55 lps enters at A, 20 lps leaves at B, 10 lps leaves at C, 25 lps leaves at D.]

Hardy-Cross method balances the flows in a loop by repeatedly applying a correction until the algebraic sum of head losses around the loop is zero.

Data

Hazen-Williams h=r Q1.852h = r\,Q^{1.852} with r=10.67L/(C1.852D4.87)r = 10.67L/(C^{1.852}D^{4.87}), C = 100. Inflow 55 lps at A; outflow 20 lps at B, 10 lps at C and 25 lps at D. Correction:

ΔQ=−∑h1.852∑∣h/Q∣\Delta Q = -\frac{\sum h}{1.852\sum |h/Q|}

Take clockwise flow (A→B→C→D) as positive.

Trial flows (satisfying continuity at every node)

AB = 35 lps (A→B), BC = 15 lps (B→C), CD = 5 lps (C→D), AD = 20 lps (A→D, anticlockwise, so negative). Check: A: 35 + 20 = 55 ✓; B: 35 − 20 = 15 ✓; C: 15 − 10 = 5 ✓; D: 5 + 20 = 25 ✓.

Iteration 1

PipeQ (lps)h = rQ^1.852 (m)h/Q
AB+35.00+0.5970.0171
BC+15.00+0.6720.0448
CD+5.00+0.0200.0041
AD-20.00-0.0650.0033

∑h=+1.224\sum h = +1.224 m, ∑∣h/Q∣=0.0692\sum|h/Q| = 0.0692, so ΔQ=−1.224/(1.852×0.0692)=−9.555\Delta Q = -1.224/(1.852 \times 0.0692) = -9.555 lps. Corrected flows (the correction is added to clockwise pipes and subtracted from AD): AB = 25.45, BC = 5.45, CD = -4.55, AD = 29.55 lps.

Iteration 2

PipeQ (lps)h = rQ^1.852 (m)h/Q
AB+25.45+0.3310.0130
BC+5.45+0.1030.0189
CD-4.55-0.0170.0038
AD-29.55-0.1340.0046

∑h=+0.282\sum h = +0.282 m, ΔQ=−3.791\Delta Q = -3.791 lps.

Further iterations

Corrections: -0.662, -0.026, -0.000, -0.000 lps; the process stops when ΔQ is negligible (< 0.01 lps).

Final discharges

PipeDischarge (lps)Direction
AB20.97A → B
BC0.97B → C
AD34.03A → D
CD9.03D → C

Checks: at B, 20.97 = 20 + 0.97 ✓; at C, 0.97 + 9.03 = 10 ✓; at D, 34.03 = 25 + 9.03 ✓.

Answer: AB = 20.97 lps, BC = 0.97 lps, AD = 34.03 lps, CD = 9.03 lps (from D to C).