- 2069 Bhadra · 4 marks
Break-even volume of a cable company
Short answer
Fixed cost = Rs 8,00,000, selling price Rs 300/unit, variable cost Rs 80/unit, contribution Rs 220/unit. Break-even volume = 800,000/220 = 3,636 units (≈3,637 units).
Calculate breakeven volume of a cable manufacturing company from the following data: Total cost = 1,200,000; Variable cost = Rs. 400,000; Income from sales = 15,00,000 at production of 5000 units.
Data (at 5,000 units)
- Total cost = Rs 1,200,000
- Variable cost (total) = Rs 400,000
- Sales income = Rs 1,500,000
Step 1: Fixed cost and unit values
- Fixed cost FC = 1,200,000 − 400,000 = Rs 800,000
- Variable cost per unit v = 400,000 / 5,000 = Rs 80
- Selling price per unit p = 1,500,000 / 5,000 = Rs 300
- Contribution per unit = 300 − 80 = Rs 220
Step 2: Break-even volume
Q* = FC / (p − v) = 800,000 / 220 = 3,636.4, about 3,637 units
Break-even sales = 3,636.4 × 300 = Rs 1,090,909
Check by the ratio method: contribution ratio = 220/300 = 0.7333; FC / 0.7333 = Rs 1,090,909.
Answer: Break-even volume = about 3,637 units (sales Rs 1.09 million). The planned output of 5,000 units is 1,363 units (27%) above break-even, so the company makes a profit of 5,000×220 − 800,000 = Rs 300,000.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Break-even units and output for desired profit · Engineering Economics, chapter 1
- Break-even hours for two pumps · Engineering Economics, chapter 1
- Explain break-even analysis and its significance · Engineering Economics, chapter 1 · asked 3×
- Standard costing variances for a building company · Engineering Economics, chapter 1
- Both types of BCR, gradient income and cost · Engineering Economics, chapter 3
- BEP volume; effect of cost changes · Engineering Economics, chapter 1
- EPS; total capital Rs 15,00,000 · Project Engineering, chapter 6
- Break-even cost comparison of three sites · Industrial Engineering and Management, chapter 2
- Break-even analysis for a startup · Entrepreneurship Development, chapter 5
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6