- 2067 Mangsir · 6 marks
Hydropower project recommendation to government
Short answer
Conventional B/C ≈ 2.00, modified B/C ≈ 2.37, and NPW ≈ Rs 68 crore. The project is economically justified and should be implemented, as benefits far exceed costs.
A preliminary estimate of a multipurpose hydropower project produced the following data:
| Initial Investment | Annual Power sales | Annual irrigation benefit | Annual recreational benefit | Annual operation and maintenance | Life of the project | Salvage value |
|---|---|---|---|---|---|---|
| Rs. 50 crore | Rs. 8 crore | Rs. 1 crore | Rs. 2 crore | Rs. 1.5 crore | 60 yrs | Rs. 40 crore |
| Give your suggestion to the government about the implementation of the project. Take MARR = 8%. |
Government (public) projects are judged by the benefit–cost ratio on a social basis, taking all benefits (power, irrigation, recreation). Amounts are in Rs crore, MARR = 8%, N = 60 years.
yr 0: -50 yr 1..60: benefits +11, O&M -1.5 yr 60: +40
- Annual benefit B = 8 + 1 + 2 = Rs 11 crore
- (P/A, 8%, 60) = 12.3766; (P/F, 8%, 60) = 0.00988
- PW(B) = 11 × 12.3766 = Rs 136.14 crore
- PW(O&M) = 1.5 × 12.3766 = Rs 18.56 crore
- PW(S) = 40 × 0.00988 = Rs 0.395 crore (very small, because it comes after 60 years)
Conventional B/C = 136.14 / (50 + 18.56 − 0.40) = 136.14 / 68.17 = 2.00
Modified B/C = (136.14 − 18.56) / (50 − 0.40) = 117.58 / 49.60 = 2.37
Net present worth = 136.14 − 18.56 − 50 + 0.40 = Rs 68.0 crore (positive).
Suggestion: B/C is about 2.0 (> 1) and NPW is about Rs 68 crore, so the project is economically justified and should be implemented. Power sales alone (Rs 8 crore a year) would justify the project (B/C ≈ 1.45), and the irrigation and recreation benefits (Rs 3 crore) add further value. The project stays acceptable unless the total benefits fall by about half: at about Rs 5.5 crore a year, B/C ≈ 1.0 (break-even). Before final approval, the government should also check environmental and resettlement costs, construction delay, and the sensitivity to the MARR and to hydrological risk, which are not in the data.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- AW sensitivity to investment and net annual cash flow · Engineering Economics, chapter 6
- Sensitivity to investment, revenue and life · Engineering Economics, chapter 6
- Sensitivity on investment, revenue and life; interpret · Engineering Economics, chapter 6
- PW sensitivity to investment, income, life by ±25% · Engineering Economics, chapter 6
- IRR with varying benefit and O&M; unrecovered balance · Engineering Economics, chapter 3
- Sensitivity on initial cost and life; interpret · Engineering Economics, chapter 6
- Preliminary estimate: office, 2000 m², Rs 20000 · Estimating and Costing, chapter 3
- Define project; irrigation project estimate · Estimating and Costing, chapter 5 · asked 4×
- Preliminary estimate: five-storey office, 2500 m² · Estimating and Costing, chapter 3
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6