Preliminary estimate: office, 2000 m², Rs 20000

Short answer

Plinth area = 3,333.33 m². Civil cost Rs66,666,666.67. Adding 1% interior design,5% extra services, assumed 5% contingency,3% supervision gives total Rs76,320,000.

Prepare a preliminary estimate of a building having a total carpet area of 2000 m² for obtaining the administrative approval of the ministry. Given the following data:

  • 30% built up area will be taken up by circulation space
  • 10% built up area is occupied by walls
  • Plinth area rate is Rs 20000.00 /sqm
  • Interior design will take 1% of the building cost
  • Other extra services will cost 5% of the building cost
  • Take supervision charge as 3%

Plinth area

Plinth area=20001−0.30−0.10=3,333.33 m2\text{Plinth area} = \frac{2000}{1 - 0.30 - 0.10} = 3,333.33\ \text{m}^2

Estimate

No contingency is given; 5% is assumed (usual practice). Supervision is 3% as given.

ItemBasisAmount (Rs)
Building cost (plinth area x rate)3,333.33 m² x 20,00066,666,666.67
Interior design1% of civil cost666,666.67
Other extra services5% of civil cost3,333,333.33
Total building cost70,666,666.67
Contingency (assumed)5% of 70,666,6673,533,333.33
Supervision charge3% of 70,666,6672,120,000.00
Total estimated cost76,320,000.00

Answer: Plinth area = 3,333.33 m²; total estimated cost = Rs 76,320,000.00.