- 2078 Bhadra · 5 marks
Preliminary estimate: 4-storey office, cube rate
Short answer
Volume = 6,772.73 m³; civil cost at Rs250/m³ = Rs1,693,181.82. Adding 1% architecture,6% water,6% sanitary,8% electrification,5% contingency,3% supervision yields total Rs2,212,650.
Prepare a preliminary estimate of the four storied office building having carpet area of 250 m² per story. The height of each story is 3.5 m and on the roof floor there is parapet wall of 0.90 m height. The cube rate of the building in that locality is Rs. 250/cu.m. Take 10% built up area is covered by walls and 35% by circulation purposes. Assume other necessary suitable provisions.
Plinth area and volume
Total carpet area = 4 x 250 = 1000 m².
Plinth area per storey = 1,818.18 / 4 = 454.55 m².
Height = 4 x 3.5 + 0.90 (parapet) = 14.9 m, so volume = 454.55 x 14.9 = 6,772.73 m³.
Estimate
The cube rate is used as printed (Rs 250/m³). The provisions for architecture 1%, water supply 6%, sanitary 6%, electrification 8%, contingency 5% and supervision 3% are assumed.
| Item | Basis | Amount (Rs) |
|---|---|---|
| Civil cost (volume x cube rate) | 6,772.73 m³ x 250 | 1,693,181.82 |
| Architectural treatment (assumed) | 1% of civil cost | 16,931.82 |
| Water supply (assumed) | 6% of civil cost | 101,590.91 |
| Sanitary work (assumed) | 6% of civil cost | 101,590.91 |
| Electrification (assumed) | 8% of civil cost | 135,454.55 |
| Total building cost | 2,048,750.00 | |
| Contingency (assumed) | 5% of 2,048,750 | 102,437.50 |
| Supervision charge (assumed) | 3% of 2,048,750 | 61,462.50 |
| Total estimated cost | 2,212,650.00 |
Answer: Volume = 6,772.73 m³; total estimated cost = Rs 2,212,650.00. If the rate is in fact Rs 2,500/m³, every amount is ten times larger.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Preliminary estimate: six-storey office, 3000 m² · Estimating and Costing, chapter 3
- Preliminary estimate: two-storied VDC office · Estimating and Costing, chapter 3
- Preliminary estimate: five-storey office, 2500 m² · Estimating and Costing, chapter 3
- Preliminary estimate: office, 3275 m² carpet · Estimating and Costing, chapter 3
- Preliminary estimate: 4-storied office, 2000 m² · Estimating and Costing, chapter 3 · asked 2×
- Preliminary estimate: residential, 500 m² carpet · Estimating and Costing, chapter 3
- Capitalized value of three-storied RCC building · Construction Management, chapter 13
- Number of lifts for office building · Industrial Power Distribution and Illumination, chapter 5
- Interior cross wall design: three-storey, 150 mm slab · Concrete Technology and Masonry Structure, chapter 8 · asked 2×
- Multi-storey wall: stresses at each level · Design of Timber and Masonry Structures, chapter 5