Short answer

Plinth area = 609.76 m², volume = 2,012.20 m³. Civil cost = Rs 10,060,975.61. With 10% architecture, 6% water, 6% sanitary, 8% electrification, 5% contingency, 2.5% work-charged establishment: total Rs 14,060,213.41.

Prepare the preliminary estimate for the building project from the following data. Residential building of 4 stories having total carpet area of 500 m² and the wall is 8% of plinth area and that for circulation area occupied by passage, verandah, staircase, etc. is 10% of plinth area. The provision for architectural design is 10% of the civil cost, provision for water supply and sanitary are 6% of civil cost for each and for electrification is 8% of civil cost. The floor height of one flat of the building is 3 m and height of parapet wall on the top is 1.2 m. The rate of per cubic content is Rs. 5000 per m³. Assume suitable percentage contingencies and work charge establishment.

Assumptions

The total carpet area of 500 m² is for the whole four-storey building, and the plinth area is the same on each floor. Contingency is taken as 5% and work-charged establishment as 2.5% of the total building cost.

Plinth area and volume

Total plinth area=5001−0.08−0.10=609.76 m2\text{Total plinth area} = \frac{500}{1 - 0.08 - 0.10} = 609.76\ \text{m}^2

Plinth area per floor = 609.76 / 4 = 152.44 m².

Height of the building = 4 x 3.0 + 1.2 (parapet) = 13.2 m.

Volume=152.44×13.2=2,012.20 m3\text{Volume} = 152.44 \times 13.2 = 2,012.20\ \text{m}^3

Estimate

ItemBasisAmount (Rs)
Civil cost (volume x cube rate)2,012.20 m³ x 5,00010,060,975.61
Architectural design10% of civil cost1,006,097.56
Water supply6% of civil cost603,658.54
Sanitary work6% of civil cost603,658.54
Electrification8% of civil cost804,878.05
Total building cost13,079,268.29
Contingency (assumed)5% of 13,079,268653,963.41
Work-charged establishment (assumed)2.5% of 13,079,268326,981.71
Total estimated cost14,060,213.41

Answer: Volume = 2,012.20 m³; civil cost = Rs 10,060,975.61; total estimated cost = Rs 14,060,213.41.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 3 questions →