- 2065 Shrawan (old course) · 7 marks
Preliminary estimate: two-storied VDC office
Short answer
Plinth area = 500/(1-0.30-0.10) = 833.33 m². Civil cost = 833.33 × 10,000 = Rs 8,333,333. Add 15% for water supply/sanitary/electrification and 10% other services, then 8% departmental charge on the total yields Rs 11,250,000.
Prepare a preliminary estimate of a two storied VDC's office building to get administrative approval of district development committee having carpet area 500 m². 30% of the built up area is occupied by circulation element and 10% of built up area is occupied by walls. Plinth area rate for civil work is Rs. 10,000 per m². Cost of water supply, sanitary and electrification is 15% of civil cost. Cost of other services is 10% of civil cost. Departmental charge 8% of total cost.
Plinth area
(for the two floors together; 416.67 m² per floor.)
Estimate
| Item | Basis | Amount (Rs) |
|---|---|---|
| Civil cost | 833.33 x 10,000 | 8,333,333.33 |
| Water supply, sanitary and electrification | 15% of civil cost | 1,250,000.00 |
| Other services | 10% of civil cost | 833,333.33 |
| Total cost | 10,416,666.67 | |
| Departmental charge | 8% of total cost | 833,333.33 |
| Total estimated cost | 11,250,000.00 |
Answer: Total estimated cost = Rs 11,250,000.00.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Preliminary estimate: 4-storied office, 2000 m² · Estimating and Costing, chapter 3 · asked 2×
- Preliminary estimate: two-storied health post · Estimating and Costing, chapter 3
- Preliminary estimate: five-storey office, 2500 m² · Estimating and Costing, chapter 3
- Preliminary estimate: office, 3275 m² carpet · Estimating and Costing, chapter 3
- Preliminary estimate: office, 2000 m², Rs 20000 · Estimating and Costing, chapter 3
- Preliminary estimate: residential, 500 m² carpet · Estimating and Costing, chapter 3