- 2067 Asar (old course) · 6 marks
Preliminary estimate: two-storied health post
Short answer
Assuming a 400 m² carpet area, plinth area = 400/(1-0.30-0.10) = 666.67 m². Civil cost = 666.67 × 18,000 = Rs 12,000,000; add 1% interior, 8% electrical, 5% other services, then 5% contingency and 3% supervision gives total estimate Rs 14,774,400.
Prepare a preliminary estimate of a two storied health post building to get administrative approval of Ministry. Data are given as below. 30% built up area is occupied by circulation space. [10% built up area is occupied by walls - struck out in the paper] Plinth area rate is Rs. 18000.00/sq.m. Extra cost for interior design 1% of building cost. Extra cost for electrical installation 8% of building cost. Extra cost for other service 5% of building cost. Contingency = 5% Supervision charge = 3%
Assumptions
The question does not give the carpet area (and the wall percentage is struck out in the paper). I take an assumed total carpet area of 400 m² for the two floors (200 m² each), and the wall area as 10% of the built-up area, as in similar questions. The method is the same for any other carpet area : plinth area .
Plinth area
Estimate
| Item | Basis | Amount (Rs) |
|---|---|---|
| Building cost (plinth area x rate) | 666.67 m² x 18,000 | 12,000,000.00 |
| Interior design | 1% of civil cost | 120,000.00 |
| Electrical installation | 8% of civil cost | 960,000.00 |
| Other services | 5% of civil cost | 600,000.00 |
| Total building cost | 13,680,000.00 | |
| Contingency | 5% of 13,680,000 | 684,000.00 |
| Supervision charge | 3% of 13,680,000 | 410,400.00 |
| Total estimated cost | 14,774,400.00 |
Answer: Plinth area = 666.67 m²; total estimated cost = Rs 14,774,400.00 for the assumed 400 m² carpet area. (Cost = 1.14 x 1.08 x 18,000 x C/0.60 = Rs 36,936 per m² of carpet area.)
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Preliminary estimate: two-storied VDC office · Estimating and Costing, chapter 3
- Preliminary estimate: 4-storied office, 2000 m² · Estimating and Costing, chapter 3 · asked 2×
- Preliminary estimate: office, 2000 m², Rs 20000 · Estimating and Costing, chapter 3
- Preliminary estimate: five-storey office, 2500 m² · Estimating and Costing, chapter 3
- Preliminary estimate: school for 600 students · Estimating and Costing, chapter 3
- Preliminary estimate: 4-storey office, cube rate · Estimating and Costing, chapter 3