- Practice · 8 marks
Linear trend regression and forecast error
Short answer
Least squares trend: y = 37.6 + 4.114x (thousand units). Year7 forecast 66.4, year8 forecast 70.5. MAD = 0.72, MSE = 0.63, MAPE = 1.4%. Causal methods use regression on related variables; time-series uses only historic values of the variable itself.
Annual demand (in thousand units) for a product over six years is: Year 1: 42, Year 2: 45, Year 3: 51, Year 4: 53, Year 5: 59, Year 6: 62. (a) Fit a straight-line trend by the least squares method. (b) Forecast the demand for years 7 and 8. (c) Compute MAD, MSE and MAPE of the fitted line, and comment on the fit. Also name the causal quantitative techniques and the difference from time-series methods.
(a) Least squares line
Take = year number, .
| 1 | 42 | 42 | 1 |
| 2 | 45 | 90 | 4 |
| 3 | 51 | 153 | 9 |
| 4 | 53 | 212 | 16 |
| 5 | 59 | 295 | 25 |
| 6 | 62 | 372 | 36 |
| 21 | 312 | 1164 | 91 |
Trend line: (demand rises by about 4.1 thousand units per year).
(b) Forecasts
- Year 7: thousand units
- Year 8: thousand units
(c) Forecast error of the fit
| Actual | Fitted | Error | |
|---|---|---|---|
| 1 | 42 | 41.71 | 0.29 |
| 2 | 45 | 45.83 | -0.83 |
| 3 | 51 | 49.94 | 1.06 |
| 4 | 53 | 54.06 | -1.06 |
| 5 | 59 | 58.17 | 0.83 |
| 6 | 62 | 62.29 | -0.29 |
- MAD thousand units
- MSE
- MAPE
The errors are small and change sign, so the straight line fits the data well (correlation coefficient ). Forecasting two years ahead is reasonable, but the line should be revised as new data arrive.
Causal methods
Causal (associative) techniques forecast a variable from other variables that influence it, for example demand of cement from construction activity, using simple or multiple regression and correlation, or econometric models. Time-series methods (moving average, exponential smoothing, trend) use only the past values of the variable itself.
Answer: ; forecasts 66.4 (year 7) and 70.5 (year 8) thousand units; MAD = 0.72, MSE = 0.63, MAPE = 1.4%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- ABC analysis from annual consumption data · Industrial Engineering and Management, chapter 4
- Forecasting by moving average and smoothing · Industrial Engineering and Management, chapter 6
- Assembly line balancing with cycle time · Industrial Engineering and Management, chapter 2
- Break-even cost comparison of three sites · Industrial Engineering and Management, chapter 2
- EOQ, total cost and reorder point numerical · Industrial Engineering and Management, chapter 4
- Fit straight line: humidity and moisture · Probability and Statistics, chapter 5
- Forecast CFL demand for next five years · Engineering Economics, chapter 1
- Regression equation for demand of fish · Engineering Economics, chapter 1
- Population forecast 2021 census, 2024 base year · Water Supply Engineering, chapter 3
All Industrial Engineering and Management chapter 6 questions →