RT works, methods and guide bank components

Define river training works. Enumerate different methods of river training works. Explain the design of different components of a guide bank.

Definition (1 mark)

River training works are structures built on or along a river to guide the flow, stabilise its course, protect its banks and safeguard structures like bridges and barrages from floods and erosion.

Methods (2 marks)

  1. Guide bunds (guide banks).
  2. Spurs (groynes).
  3. Marginal embankments (levees).
  4. Bank pitching (revetment) with a launching apron.
  5. Cut-offs.
  6. Bed sills, check dams and bio-engineering.

Design of the components of a guide bank (5 marks)

Waterway: Lacey's regime width W=4.75QW = 4.75\sqrt{Q} (Q in m³/s). Silt factor f=1.76dmmf = 1.76\sqrt{d_{mm}}.

ComponentDesign
Length of guide bankUpstream shank 1.01.0 to 1.5W1.5W; downstream tail 0.20.2 to 0.5W0.5W
Curved headRadius about 0.5W0.5W (upstream), sweep 120120 to 145∘145^\circ; downstream sweep about 45∘45^\circ
Top level and widthHFL +1.5+ 1.5 m free-board; width 6 m (3 to 6 m)
Side slopes2:1 river side (3:1 around the head); 2:1 country side
PitchingThickness t=0.06Q1/3t = 0.06Q^{1/3} on 0.15 to 0.3 m graded filter
Scour depthR=0.47(Q/f)1/3R = 0.47(Q/f)^{1/3}; 2R2R below HFL at nose, 1.5R1.5R at shank
Launching apronDepth below bed D′=D' = scour depth −- flood depth; width 1.5D′1.5D'; launched thickness 1.5t1.5t (laid about 2.25t2.25t)
 Section at shank
      _6 m_
     /     \  HFL+1.5 m
 HFL/_______\ 2:1
   / pitching \
 _/___filter___\_ apron (width 1.5D', launches at 2:1)

The apron is laid at the toe of the pitching and, as the river scours the bed, the stones slide down the 2:1 slope and protect the bund against undermining.