- 2068 Chaitra (old course) · 4+4 marks
RT works for a bridge; launching apron
Short answer
River training works for a bridge include guide bunds, approach embankments, pitching, and a launching apron. A launching apron is a layer of loose stone at the toe that slides into the scour hole to prevent undermining. Design uses scour depth R=0.47(Q/f)^(1/3), depth below bed D', apron width 1.5D', and launched thickness 1.5t.
With neat sketch (plan and section), show the river training works for a bridge. What is a launching apron? How is it designed?
River training works for a bridge (4 marks)
At a bridge on an alluvial river, the river is contracted to the bridge waterway, so training works are provided to guide the flow axially and prevent flanking: guide bunds on both sides upstream, approach embankments, pitching of slopes and the river banks, launching aprons and sometimes spurs upstream.
Plan
U/S D/S
____________________ | ____
/ guide bund \ approach |=| / \
( curved head )========|=|=( )
\____________________/ embankment|=| \____/
flow ---> waterway W between abutments
Section through guide bund
__6 m__ HFL+1.5
/ \
HFL/_________\ 2:1
/ pitching \
_/__ filter ____\_ launching apron
Launching apron (2 marks)
A launching apron is a layer of loose stone (or concrete blocks or gabion) laid on the bed at the toe of the pitching. When scour develops at the toe, the stones slide into the scour hole and form a protective layer on the slope, preventing undermining of the bund.
Design of launching apron (2 marks)
- Scour depth with .
- Maximum scour below HFL: (nose) or (shank). Depth below bed scour flood depth.
- Launching slope 2H:1V, so the stone volume must cover a slope length .
- Thickness of launched apron where is pitching thickness.
- Width laid and thickness laid (about ).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Objectives of river training works · Irrigation and Drainage Engineering, chapter 6
- Guide bund with plan, section, nose; 2500 m3/s · Irrigation and Drainage Engineering, chapter 6
- Launching apron, 7000 m3/s, HFL 114 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Guide bank and launching apron, 5000 m3/s · Irrigation and Drainage Engineering, chapter 6
- Thickness of launching apron, 7 m shank · Irrigation and Drainage Engineering, chapter 6
- Objectives of RT works and spur spacing · Irrigation and Drainage Engineering, chapter 6
- Plan and vertical section of panelled door · Building Technology, chapter 6
- Bridge components sketch; river bank protection · Transportation Engineering II, chapter 5
- Bridge site factors; river bank protection structures · Transportation Engineering II, chapter 5
- Bheri river suspension bridge collapse · Engineering Professional Practice, chapter 7
All Irrigation and Drainage Engineering chapter 6 questions →