- 2074 Bhadra · 5 marks
Guide bank and launching apron, 5000 m3/s
Short answer
Lacey waterway W=336m. Upstream length 420m, downstream 84m, curved head radius 168m (120°). Pitching thickness 1.03m. Normal scour R=8.39m. Apron at shank: length 12.87m, launched thickness 1.54m (laid 2.29m). At nose: length 19.16m, same thickness.
A bridge is to be constructed across a river having the following hydraulic data: Maximum flood Discharge: 5000 m³/s; Highest flood level: 254.0 m; River bed level: 250 m; Average diameter of river sand: 0.25 m. Design and sketch a guide bank including launching apron to train the river.
Data and design basis
- The average size of the river sand is taken as 0.25 mm (0.25 m would not be sand).
- Silt factor (Lacey):
- Flood depth above bed: m
- Design discharge for scour/apron: m³/s
1. Waterway and length of guide bund
Lacey's regime waterway: m. Adopt m. Length of guide bund (Garg): upstream shank to , downstream tail to . Adopt
Curved heads: upstream radius m with sweep to (adopt ); downstream radius m with sweep about . Arc length of upstream head m, so total length on the upstream side m.
2. Thickness of stone pitching
Adopt m (pitching on the river side slope 2:1, over a 0.15 to 0.3 m graded filter).
3. Scour depth and launching apron
Lacey's normal scour depth:
Maximum scour below HFL: at the upstream nose, at the shank (straight portion). The apron must launch to the slope , so its horizontal width is and, when launched, it covers a slope length with thickness .
| Portion | Scour factor | Scour depth below HFL | Depth below bed | Apron length |
|---|---|---|---|---|
| Nose (u/s curved head) | 2.0R | 16.77 m | 12.77 m | 19.16 m |
| Shank (straight) | 1.5R | 12.58 m | 8.58 m | 12.87 m |
Thickness: pitching m, so the launched apron thickness is m. Equating volumes per metre, the thickness as laid over width is m (about ).
Summary
| Item | Value |
|---|---|
| Lacey waterway | 335.88 m (adopt 336 m) |
| Length of guide bund (u/s) | 420 m; d/s tail 84 m |
| Pitching thickness | 1.03 m |
| Apron at shank: width / thickness | 12.87 m / 1.54 m launched (2.29 m laid) |
| Apron at nose: width / thickness | 19.16 m / 1.54 m launched (2.29 m laid) |
Sketches
Plan of guide bunds:
U/S D/S
bridge / weir axis
Shank (straight) |
________________________________ | ___
/ 1.0-1.5 W upstream \ | / \ tail
\________________________________/=|=\___/ 0.25 W
curved head |
R, sweep 120 deg <-- waterway W -->
________________________________ | ___
/ \ | / \
\________________________________/=|=\___/
Section at the shank (straight portion):
top width 6 m
___________ <- HFL + 1.5 m
/ \
HFL ---/-------------\--- 2:1 slopes
/ pitching t \
bed__/__ filter ______ \___
\_ launching apron _/ (launches at 2:1)
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Launching apron, 5000 m3/s, HFL 225 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Launching apron, 6000 m3/s, HFL 330 m · Irrigation and Drainage Engineering, chapter 6
- Launching apron, 8000 m3/s, HFL 128.5 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Guide bank design, 4000 m3/s, d 0.40 mm · Irrigation and Drainage Engineering, chapter 6
- Guide bund design, 4000 m3/s, d 0.1 mm · Irrigation and Drainage Engineering, chapter 6
- Gabion guide bund and apron, 3000 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Bridge components sketch; river bank protection · Transportation Engineering II, chapter 5
- Bridge site factors; river bank protection structures · Transportation Engineering II, chapter 5
- Reciprocal levelling across river, 250 m · Surveying I, chapter 5
- Slope-area flood discharge, Marin River at Kusuntar · Engineering Hydrology, chapter 4
All Irrigation and Drainage Engineering chapter 6 questions →