- 2081 Chaitra · 8 marks
Guide bund with plan, section, nose; 2500 m3/s
Short answer
Lacey waterway 238 m; upstream guide bund 298 m, downstream tail 60 m. Pitching thickness 0.81 m. Normal scour depth R=7.75 m. Nose apron width 18.31 m, shank apron 12.50 m; launched thickness 1.22 m, laid thickness 1.82 m.
Design and sketch (plan, section at straight portion, section at nose) guide bunds including launching apron, for a bridge site with following hydraulic data: Designed discharge = 2500 m³/s; H.F.L = 78.8 m; river bed level = 75.5 m; and D50 of bed material = 0.1 mm.
Data and design basis
- Silt factor (Lacey):
- Flood depth above bed: m
- Design discharge for scour/apron: m³/s
1. Waterway and length of guide bund
Lacey's regime waterway: m. Adopt m. Length of guide bund (Garg): upstream shank to , downstream tail to . Adopt
Curved heads: upstream radius m with sweep to (adopt ); downstream radius m with sweep about . Arc length of upstream head m, so total length on the upstream side m.
2. Thickness of stone pitching
Adopt m (pitching on the river side slope 2:1, over a 0.15 to 0.3 m graded filter).
3. Scour depth and launching apron
Lacey's normal scour depth:
Maximum scour below HFL: at the upstream nose, at the shank (straight portion). The apron must launch to the slope , so its horizontal width is and, when launched, it covers a slope length with thickness .
| Portion | Scour factor | Scour depth below HFL | Depth below bed | Apron length |
|---|---|---|---|---|
| Nose (u/s curved head) | 2.0R | 15.51 m | 12.21 m | 18.31 m |
| Shank (straight) | 1.5R | 11.63 m | 8.33 m | 12.50 m |
Thickness: pitching m, so the launched apron thickness is m. Equating volumes per metre, the thickness as laid over width is m (about ).
Summary
| Item | Value |
|---|---|
| Lacey waterway | 237.50 m (adopt 238 m) |
| Length of guide bund (u/s) | 298 m; d/s tail 60 m |
| Pitching thickness | 0.81 m |
| Apron at shank: width / thickness | 12.50 m / 1.22 m launched (1.82 m laid) |
| Apron at nose: width / thickness | 18.31 m / 1.22 m launched (1.82 m laid) |
Sketches
Plan:
U/S D/S
bridge / weir axis
Shank (straight) |
________________________________ | ___
/ 1.0-1.5 W upstream \ | / \ tail
\________________________________/=|=\___/ 0.25 W
curved head |
R, sweep 120 deg <-- waterway W -->
________________________________ | ___
/ \ | / \
\________________________________/=|=\___/
Section at the straight portion (shank):
top width 6 m
___________ <- HFL + 1.5 m
/ \
HFL ---/-------------\--- 2:1 slopes
/ pitching t \
bed__/__ filter ______ \___
\_ launching apron _/ (launches at 2:1)
Section at the nose (upstream curved head):
Section at u/s curved head (nose)
______ <- HFL + 1.5 m
/ \ top 6 m, side 3:1 (flatter)
HFL ----/---------\----
/ pitching t \
bed ___/_____________\__
\_ apron: 2.0R scour, 1.5D' wide _/
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Guide bank and launching apron, 5000 m3/s · Irrigation and Drainage Engineering, chapter 6
- Guide bund design, 4000 m3/s, d 0.1 mm · Irrigation and Drainage Engineering, chapter 6
- Guide bund: length, curved head, apron; 4500 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Gabion guide bund and apron, 3000 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Guide bund and apron, 13,100 m3/s · Irrigation and Drainage Engineering, chapter 6
- Launching apron, 7000 m3/s, HFL 114 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Bridge site factors; river bank protection structures · Transportation Engineering II, chapter 5
- River discharge by mid-section method · Hydro Power, chapter 2
- River discharge from two-point current meter data · Engineering Hydrology, chapter 4
All Irrigation and Drainage Engineering chapter 6 questions →