Launching apron, 7000 m3/s, HFL 114 m
Short answer
f=1.76, t=1.15 m, R=7.45 m, D'=1.5R−3=8.17 m. Apron length=12.25 m, launched thickness=1.72 m (laid 2.57 m). Volume equality before and after launching on 2:1 slope used.
Design the length and thickness of launching apron for the straight portion of a guide bund in a river: Design flood = 7000 m³/s; Average diameter of river bed material = 1 mm; River bed level = 111.00; HFL = 114.00. Provide a neat sketch of designed apron.
Data and design basis
- Silt factor (Lacey):
- Flood depth above bed: m
- Design discharge for scour/apron: m³/s
1. Pitching thickness
2. Scour depth and launching apron
Lacey's normal scour depth:
Maximum scour below HFL: at the upstream nose, at the shank (straight portion). The apron must launch to the slope , so its horizontal width is and, when launched, it covers a slope length with thickness .
| Portion | Scour factor | Scour depth below HFL | Depth below bed | Apron length |
|---|---|---|---|---|
| Shank (straight) | 1.5R | 11.17 m | 8.17 m | 12.25 m |
Thickness: pitching m, so the launched apron thickness is m. Equating volumes per metre, the thickness as laid over width is m (about ).
Answer (straight portion): length of launching apron m, thickness m launched (about 2.57 m as laid).
pitching
____/\__
/\ apron laid: width 1.5D', T = 2.24 t
bed ___________ river bed
after launching: 2:1 slope, 1.5 t thick
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Launching apron, 8000 m3/s, HFL 128.5 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Launching apron, 5000 m3/s, HFL 225 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Guide bund: length, curved head, apron; 4500 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Launching apron, 6000 m3/s, HFL 330 m · Irrigation and Drainage Engineering, chapter 6
- Guide bund design, 4000 m3/s, d 0.1 mm · Irrigation and Drainage Engineering, chapter 6
- Gabion guide bund and apron, 3000 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Guide bank and launching apron, 5000 m3/s · Irrigation and Drainage Engineering, chapter 6
- Thickness of launching apron, 7 m shank · Irrigation and Drainage Engineering, chapter 6
All Irrigation and Drainage Engineering chapter 6 questions →