- 2068 Baisakh (old course) · 9 marks
Thickness of launching apron, 7 m shank
Short answer
With d=0.3 mm, f=0.964, R=9.52 m, D'=1.5R−5=9.27 m, t=1.20 m. Volume equality for 7 m width: T×7 = 1.5t×√5×D' → T=5.33 m. Launched thickness 1.80 m; required width 13.91 m, so 7 m apron is thick to compensate.
Calculate the thickness of a 7 m long launching apron of loosed stones for a shank portion of guide bund at a bridge site of a river having design flood of 8000 m³/s and flood depth of 5 m. Assume that average diameter of river bed material at flood time is 0.3 mm.
A launching apron of loose stone is laid at the toe of the guide bund. When scour occurs it launches down a 2H:1V slope. The laid thickness is found by equating the stone volume before and after launching.
Data
m³/s, flood depth m, mm, laid width of apron m (shank portion).
Step 1. Silt factor and scour depth
Maximum scour at the shank: m below HFL. Scour below the bed: m.
Step 2. Pitching and launched thickness
Step 3. Thickness of the 7 m apron before launching
Slope length of launched apron m.
Answer: thickness of the 7 m wide apron as laid m (it launches to 1.80 m thick on the 2:1 slope). A 7 m apron is short against a required width of m, so a thick apron is needed; it may be better to widen it to m, when m.
pitching
___\__ T = 5.33 m
bed __|<-- 7 m -->|___ river bed
after launch: 2H:1V, 1.80 m thick, D' = 9.27 m
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Launching apron, 8000 m3/s, HFL 128.5 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Guide bund design, 4000 m3/s, d 0.1 mm · Irrigation and Drainage Engineering, chapter 6
- Gabion guide bund and apron, 3000 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Guide bank and launching apron, 5000 m3/s · Irrigation and Drainage Engineering, chapter 6
- Guide bund: length, curved head, apron; 4500 m3/s · Irrigation and Drainage Engineering, chapter 6 · asked 2×
- Launching apron, 7000 m3/s, HFL 114 m · Irrigation and Drainage Engineering, chapter 6 · asked 3×
- Bridge site factors; river bank protection structures · Transportation Engineering II, chapter 5
- Gumbel design flood for highway bridge, 4% risk · Engineering Hydrology, chapter 6
All Irrigation and Drainage Engineering chapter 6 questions →