- 2072 Asoj · 8 marks
Completely mixed ASP reactor, 10,000 m³/day
Short answer
Reactor volume 2083 m³ using Lawrence-McCarty equation with θc=10 days, Y=0.5, kd=0.06; detention time 5 h; recycle ratio 0.43 assuming return sludge concentration 10,000 mg/L.
A activated sludge system is to be used for secondary treatment of 10,000 m³/day of municipal wastewater. After primary clarification, the BOD is 250 mg/l and is desired to have not more than 50 mg/l of soluble BOD in the effluent. A completely mixed reactor is to be used. MLSS concentration is of 3000 mg/l. Determine: i) The volume of reactor; ii) Detention time; iii) The recycle ratio.
Assumptions (not given, typical values)
Yield kg cells/kg BOD removed; endogenous decay /day; mean cell residence time (sludge age) days; effluent suspended solids neglected; recycled sludge concentration mg/l (SVI about 100 ml/g).
(i) Volume of the reactor
For a completely mixed reactor (Lawrence-McCarty):
(Check: /day, within the usual 0.2-0.6.)
(ii) Detention time
(iii) Recycle ratio
A balance on the biomass in the reactor (no solids in the effluent) gives, for the aeration tank, :
So the return sludge flow is m³/day. (Waste sludge: m³/day.)
Answer: (i) m³; (ii) detention time h; (iii) recycle ratio .
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Activated sludge and ASP treatment process · Sanitary Engineering, chapter 7
- 1-day BOD 300 mg/l to 5-day at 30°C · Sanitary Engineering, chapter 5
- Degree of treatment, industrial wastewater · Sanitary Engineering, chapter 6
- Conventional ASP design, population 50,000 · Sanitary Engineering, chapter 7 · asked 2×
- Is treatment necessary? Town wastewater 300 l/s · Sanitary Engineering, chapter 6
- Conventional ASP design, population 1,00,000 · Sanitary Engineering, chapter 7
- Municipal wastewater treatment plant · Environment and Pollution Control, chapter 4
- EVA; 10 days, 100,000, day 6, spi and cpi · Project Engineering, chapter 4
- Primary and secondary energy with 10% environmental flow · Hydro Power, chapter 3
- EVA; 10 days, 100,000, day 6, Rs 65,000 · Project Engineering, chapter 4