- Practice · 6 marks
Key financial indicators: burn rate and runway
Short answer
Gross burn equals total monthly expenses Rs 13,00,000; net burn is expenses minus revenue, Rs 9,00,000/month; runway is cash divided by net burn, about 13.3 months.
Explain the key financial indicators a startup should track. A startup has Rs 1.2 crore cash in the bank. Monthly revenue is Rs 4,00,000 and monthly expenses are Rs 13,00,000. Calculate the gross burn rate, net burn rate and runway. What can the founder do if the runway is too short?
Key indicators
| Indicator | Meaning |
|---|---|
| Revenue growth (MRR/ARR) | Monthly or annual recurring revenue and its growth |
| Gross margin | (Revenue - direct cost) / revenue |
| Burn rate | Cash spent per month in excess of income |
| Runway | Months the cash will last |
| CAC and LTV | Cost to win a customer; value from that customer |
| Churn | Share of customers lost per period |
| Break-even point | Sales at which profit is zero |
| Cash conversion / working capital | Speed of turning sales into cash |
Numerical
Cash = Rs 1.2 crore = Rs 1,20,00,000.
Gross burn rate = total monthly expenses = Rs 13,00,000.
Net burn rate = expenses - revenue:
Runway:
Actions if runway is short
- Cut non-essential spending; delay hiring.
- Raise sales or prices; collect receivables faster.
- Raise new funds early (rounds take 3-6 months), or take bridge finance.
- Pivot to a cheaper model.
Answer: Gross burn = Rs 13,00,000/month; net burn = Rs 9,00,000/month; runway is about 13.3 months.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- NPV and payback of a startup project · Entrepreneurship Development, chapter 5
- Break-even analysis for a startup · Entrepreneurship Development, chapter 5
- Revenue streams and cost structure · Entrepreneurship Development, chapter 4
- Customer lifetime value and CAC numerical · Entrepreneurship Development, chapter 4
- Marketing strategies, pricing and credit policy · Entrepreneurship Development, chapter 5
- Testing key business assumptions · Entrepreneurship Development, chapter 3
- EPS and book value; ABC project Rs 6,00,000 · Project Engineering, chapter 6
- Capitalised value from Rs 20,000 monthly rent · Construction Management, chapter 13
- EPS and book value; capital Rs 5,00,000 · Project Engineering, chapter 6
- EVA and S-curve; Rs 30,00,000, 24 months · Project Engineering, chapter 4