For assumed room 4.5×3.5 m: earthwork excavation 15.23 m³, woodwork for door and window frames 0.111 m³, and two-coat enamel painting over primer 10.07 m².
Estimate the quantities of the following items of work from the accompanying drawing (Figure 1): (i) Earthwork excavation in foundation (ii) Wood work for doors and windows frame (iii) Two coats enamel painting over one coat primer in doors and windows. [Figure 1 not included in the scanned paper]
No drawing is given, so a one-room building is assumed: room 4.5 m × 3.5 m clear, 230 mm walls, centre-line length 16.92 m; trench 0.90 m × 1.00 m; one door 1.0 × 2.1 m (panelled); two glazed windows 1.2 × 1.2 m; frames 100 × 75 mm.
i) Earthwork in excavation in foundation
| Item | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| Trench, all walls (centre-line) | 1 | 16.920 | 0.900 | 1.000 | 15.228 |
| Total | 15.228 |
ii) Wood work for door and window frames
| Item | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| Door frame 2×2.1 + 1.0 | 1 | 5.200 | 0.100 | 0.075 | 0.0390 |
| Window frames 2 × (2×1.2 + 2×1.2) | 2 | 4.800 | 0.100 | 0.075 | 0.0720 |
| Total | 0.1110 |
iii) Two coats of enamel paint over one coat of primer
Painted area is measured over the frame and shutter on both sides and multiplied by a coefficient for the type of shutter. The multipliers below are typical textbook values (IS 1200 style; they differ slightly between books): panelled door 1.30 per side measured, glazed window 0.80.
- Door: 1.0 × 2.1 × 2 sides × 1.30 = 5.46 m²
- Windows: 2 × 1.2 × 1.2 × 2 sides × 0.80 = 4.61 m²
- Total painted area = 10.07 m², which is taken for primer (1 coat) and enamel (2 coats).
Answer: Excavation 15.23 m³; timber frames 0.111 m³; painting 10.07 m² (assumed dimensions).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Building: excavation, second footing, wood frames · Estimating and Costing, chapter 6
- Building: excavation, brick 1:4, wood work · Estimating and Costing, chapter 6
- Building: excavation, PCC, brick, wood work · Estimating and Costing, chapter 6
- Building: PCC, brick, sal wood frame, RCC slab · Estimating and Costing, chapter 6
- Building: excavation, PCC foundation, brick · Estimating and Costing, chapter 6
- One-roomed building: earthwork, plaster, openings · Estimating and Costing, chapter 6
- Emulsion paint; painting on new woodwork · Building Technology, chapter 9
- Thermal insulation of walls, doors, windows, roofs · Building Technology, chapter 1 · asked 3×
- Purpose and sizing of doors and windows; panelled doors · Building Technology, chapter 6