For assumed room 5.0×3.5 m: earthwork excavation 16.13 m³, brickwork in second footing 1.24 m³, and woodwork for frames 0.111 m³.

Estimate the quantities of the following items of work from the accompanying building drawings: a) Earthwork in excavation in foundation b) Brick work in 2nd footing in foundation c) Wood work for doors and windows frame [Drawing not included in the scanned paper]

The drawing is not available, so a room 5.0 m × 3.5 m clear with 230 mm walls is assumed. Centre-line length = 2(5.0 + 3.5 + 0.46) = 17.92 m.

Foundation assumed: trench 0.90 m wide × 1.00 m deep, PCC 1:3:6 200 mm, first footing 0.69 m × 0.15 m, second footing 0.46 m × 0.15 m (each footing step projects 115 mm, i.e. half a brick, on each side beyond the one above), then 230 mm wall. Openings: D 1.0 × 2.1 m (1 no.), W 1.2 × 1.2 m (2 nos.); frame 100 × 75 mm.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)117.9200.9001.00016.128
Total16.128

b) Brickwork in second footing

The second footing is the upper step, 0.46 m wide:

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Second footing, 0.46 m wide117.9200.4600.1501.236
Total1.236

(If your drawing counts the lower, wider step as the "second" footing, its quantity is 1.85 m³, found the same way.)

c) Wood work for door and window frames

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Door frame 2×2.1 + 1.015.2000.1000.0750.0390
Window frames 2 × (2×1.2 + 2×1.2)24.8000.1000.0750.0720
Total0.1110

Answer: Excavation 16.13 m³; second-footing brickwork 1.24 m³; frame timber 0.111 m³ (assumed dimensions).