Skip to main content

Building: lime concrete, second footing, shutters, DPC

Short answer

Lime concrete in foundation: 4.30 m3. Brickwork in second footing: 1.10 m3. Two door shutters total: 3.24 m2. DPC 25 mm thick, net wall length after door deduction: 3.22 m2.

Estimate the quantities of the following items of work from the accompanying BUILDING drawings. i) Lime concrete in foundation ii) Brick work in second footing iii) DOOR shutters iv) 25 mm thick DPC [Drawing not included in the scanned paper]

No drawing is given, so a typical room is assumed: 4.5 m × 3.0 m clear, 230 mm walls; centre-line length = 2(4.5 + 3.0 + 0.46) = 15.92 m. Foundation: trench 0.90 m wide; lime concrete 0.30 m thick; brick footings of 0.69 m (first) and 0.46 m (second), 0.15 m high each; DPC at plinth. Doors: D1 1.0 × 2.1 m, D2 0.9 × 2.1 m; two windows 1.2 × 1.2 m. Door frame 75 mm.

i) Lime concrete in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Lime concrete bed 0.90 wide × 0.30 thick115.9200.9000.3004.298
Total4.298

ii) Brickwork in second footing

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Second footing 0.46 × 0.15115.9200.4600.1501.098
Total1.098

iii) Door shutters

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Door D1 shutter (1.0−0.15)×(2.1−0.075)10.8502.025–1.721
Door D2 shutter (0.9−0.15)×(2.1−0.075)10.7502.025–1.519
Total3.240

iv) 25 mm thick DPC

Measured in m² (length of wall × thickness of wall), not across door openings.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
DPC 25 mm, wall length115.9200.230–3.662
Deduct door openings (1.0 + 0.9)-11.9000.230–-0.437
Total3.225

Answer: Lime concrete 4.30 m³; second-footing brickwork 1.10 m³; door shutters 3.24 m²; DPC 3.22 m² (assumed dimensions).

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 6 questions →