Single room: brick foundation, DPC, superstructure

Short answer

Room 4.0×3.5 m clear, centre-line 15.92 m. Brickwork up to plinth: steps 0.69 m and 0.46 m wide (each 0.15 m) + 0.95 m wall = 6.23 m³. DPC 2 cm: 15.92×0.23 m minus door (0.23 m²) = 3.43 m². Superstructure brickwork: wall 3 m high deduct door, windows, lintels = 9.68 m³.

From the attached plan and section of single room building, estimate the quantities. i) Brickwork in foundation up to plinth with 1:6 cement mortar. ii) 2 cm DPC at plinth level. iii) Brickwork in superstructure in cement mortar. [Drawing not included in the scanned paper]

No drawing is available, so a typical single room is assumed. The standard method is the centre-line method.

Assumed data

  • Room 4.0 m × 3.5 m clear, 230 mm walls; centre-line length = 2(4.0 + 3.5 + 0.46) = 15.92 m.
  • Foundation: trench 0.90 m × 1.00 m, PCC 200 mm, two brick steps 0.69 and 0.46 m wide (150 mm each), 230 mm wall up to plinth top (0.45 m above GL); wall height from last step = 0.95 m.
  • Superstructure height 3.0 m; D 1.0 × 2.1 m (1 no.); W 1.2 × 1.2 m (2 nos.); RCC lintels 150 mm deep with 200 mm bearing each side.

i) Brickwork in foundation up to plinth, 1:6

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)115.9200.6900.1501.648
Brick footing step 2 (0.46 m wide)115.9200.4600.1501.098
Wall up to plinth115.9200.2300.9503.479
Total6.225

ii) 2 cm DPC at plinth level

DPC (cement concrete 1:2:4 with waterproofing) is measured in m² = wall length × wall width, and is not carried across door openings.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
DPC 20 mm, wall length115.9200.230–3.662
Deduct door opening-11.0000.230–-0.230
Total3.432

iii) Brickwork in superstructure

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall above plinth, full length115.9200.2303.00010.985
Deduct door 1.00×2.10-11.0000.2302.100-0.483
Deduct window 1.20×1.20-21.2000.2301.200-0.662
Deduct lintel over door (1.0 + 2 × 0.2)-11.4000.2300.150-0.048
Deduct lintels over windows (1.2 + 2 × 0.2)-21.6000.2300.150-0.110
Total9.681

Answer: Foundation and plinth brickwork 6.22 m³; DPC 3.43 m²; superstructure brickwork 9.68 m³ (assumed dimensions).