Estimate, quantity survey, estimated vs actual

Short answer

An estimate is a forecast of probable quantities and cost before construction. A quantity survey measures work items from drawings to prepare a bill of quantities. Estimated cost is approximate and used for planning, while actual cost is the exact expenditure recorded after completion.

What is an estimate? What is meant by quantity survey? Distinguish between estimated and actual cost.

Estimate

An estimate is the calculation of the probable quantities and cost of a work before construction, based on the drawings, specifications and current rates.

Quantity survey

Quantity survey (quantity surveying) is the process of measuring and calculating the quantities of the different items of work and materials from the drawings, and arranging them in a bill of quantities. It is the first step of estimating. It is also used later to measure the completed work for payment.

Estimated cost versus actual cost

Estimated costActual cost
Probable cost calculated before executionReal cost incurred after execution
Based on drawings, norms and current ratesBased on bills, vouchers and measurements
Approximate; has contingencyExact and final
Used for approval, budget, tenderingUsed for final payment and records
Can be revised before or during workCannot be changed