Skip to main content

Components of complete estimate; abstract cost

Short answer

Components: land, main building, water supply, sanitary, electrical, external works, furniture, consultancy, contingency (3–5%), VAT 13%. The abstract of cost tabulates items with quantity, unit, rate, and amount; sample shows earthwork, PCC, brickwork, etc., subtotalled and adding contingency and VAT to reach grand total.

What are the components of a complete estimate? Prepare a sample of abstract of cost.

Components of a complete estimate

A complete estimate gives the total final cost of the project, including all costs related to the building besides the main construction cost:

  1. Land cost and compensation, including legal charges.
  2. Cost of the main building (civil works), from the detailed estimate.
  3. Water supply, sanitary and drainage works.
  4. Electrical installation (wiring, fittings, earthing, lightning conductor, lift).
  5. Architectural treatment and special finishing.
  6. External works: approach road, compound wall, gate, landscaping, septic tank.
  7. Furniture, equipment and fittings.
  8. Planning, design and supervision charges (consultant fees), and establishment.
  9. Contingency (3 to 5%) and work-charged establishment.
  10. Taxes (VAT 13%), interest during construction, and price escalation provisions.

Sample abstract of cost

(Illustrative quantities and rates)

SNItemQtyUnitRate (Rs)Amount (Rs)
1Earthwork in excavation100m³60060,000
2PCC 1:3:610m³11,500115,000
3Brickwork 1:640m³15,500620,000
4RCC M20 (concrete)25m³18,000450,000
5Reinforcement Fe 5002,500kg150375,000
6Plaster 12.5 mm300m²480144,000
7Flooring100m²90090,000
Sub-total1,854,000
Contingency 5%92,700
Total1,946,700
VAT 13%253,071
Grand total2,199,771

Rates are illustrative; actual rates are taken from the District Rate.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 2 questions →