Based on centre line length 14.92 m, quantities: excavation 13.43 m³, PCC 2.01 m³, foundation brickwork 3.92 m³, net superstructure brickwork 9.48 m³, plaster 85.98 m², flooring 12 m². Abstract cost: Rs 287,293 (illustrative rates).
Prepare tables of quantity sheet and abstract of cost for a residential building.
Assumed: a single-room residential building, clear size 4 m x 3 m, 230 mm brick walls, 3.0 m high, one door 1.0 x 2.1 m and one window 1.2 x 1.2 m; trench 0.9 m wide x 1.0 m deep; centre line length m.
Quantity sheet (detailed measurement)
| Item | No. | L (m) | B (m) | H (m) | Quantity |
|---|---|---|---|---|---|
| Excavation | 1 | 14.92 | 0.90 | 1.00 | 13.43 m³ |
| PCC 1:3:6 | 1 | 14.92 | 0.90 | 0.15 | 2.01 m³ |
| Brickwork in foundation and plinth | 1 | 14.92 | 0.35 | 0.75 | 3.92 m³ |
| DPC | 1 | 14.92 | 0.23 | - | 3.43 m² |
| Brickwork in superstructure | 1 | 14.92 | 0.23 | 3.00 | 10.29 m³ |
| Deduct door | -1 | 1.00 | 0.23 | 2.10 | -0.48 m³ |
| Deduct window | -1 | 1.20 | 0.23 | 1.20 | -0.33 m³ |
| Net superstructure brickwork | 9.48 m³ | ||||
| Plaster inside 2(4+3) x 3 (no deduction, see note) | 42.00 m² | ||||
| Plaster outside 2(4.46+3.46) x 3 less openings 3.54 | 43.98 m² | ||||
| Flooring | 1 | 4.0 | 3.0 | - | 12.00 m² |
Note: both openings (2.10 m² and 1.44 m²) are between 0.5 and 3 m², so as per IS 1200 they are deducted from one face only (here the outside), and the reveals are not added. Total plaster = 42.00 + 43.98 = 85.98 m².
Abstract of cost (rates illustrative)
| SN | Item | Qty | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|---|
| 1 | Excavation | 13.43 | m³ | 600 | 8,058 |
| 2 | PCC 1:3:6 | 2.01 | m³ | 11,500 | 23,115 |
| 3 | Brickwork 1:6 in foundation | 3.92 | m³ | 14,000 | 54,880 |
| 4 | DPC | 3.43 | m² | 650 | 2,230 |
| 5 | Brickwork 1:6 in superstructure | 9.48 | m³ | 15,500 | 146,940 |
| 6 | Plaster 12.5 mm, both faces | 85.98 | m² | 480 | 41,270 |
| 7 | Flooring | 12.00 | m² | 900 | 10,800 |
| Total | 287,293 |
Contingency, VAT and the other items (RCC slab, roofing, doors, painting) would be added in the same way.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Prepare AOC, BOQ and summary of cost · Estimating and Costing, chapter 2
- Components of complete estimate; abstract cost · Estimating and Costing, chapter 2
- Bill of quantities and abstract of cost · Estimating and Costing, chapter 2 · asked 2×
- Preliminary estimate: residential, 500 m² carpet · Estimating and Costing, chapter 3
- Quantity method for load bearing brick building · Estimating and Costing, chapter 2
- Total cost of apartment building · Estimating and Costing, chapter 3
- Expansion joint in a residential building · Building Technology, chapter 10
- Sheet pile seepage quantity numerical · Soil Mechanics, chapter 7
- Prepare tender notice for commercial complex · Construction Management, chapter 5
- Final project report: title page, abstract, recommendation · Communication English, chapter 8