Based on centre line length 14.92 m, quantities: excavation 13.43 m³, PCC 2.01 m³, foundation brickwork 3.92 m³, net superstructure brickwork 9.48 m³, plaster 85.98 m², flooring 12 m². Abstract cost: Rs 287,293 (illustrative rates).

Prepare tables of quantity sheet and abstract of cost for a residential building.

Assumed: a single-room residential building, clear size 4 m x 3 m, 230 mm brick walls, 3.0 m high, one door 1.0 x 2.1 m and one window 1.2 x 1.2 m; trench 0.9 m wide x 1.0 m deep; centre line length L=2(4.23+3.23)=14.92L = 2(4.23 + 3.23) = 14.92 m.

Quantity sheet (detailed measurement)

ItemNo.L (m)B (m)H (m)Quantity
Excavation114.920.901.0013.43 m³
PCC 1:3:6114.920.900.152.01 m³
Brickwork in foundation and plinth114.920.350.753.92 m³
DPC114.920.23-3.43 m²
Brickwork in superstructure114.920.233.0010.29 m³
Deduct door-11.000.232.10-0.48 m³
Deduct window-11.200.231.20-0.33 m³
Net superstructure brickwork9.48 m³
Plaster inside 2(4+3) x 3 (no deduction, see note)42.00 m²
Plaster outside 2(4.46+3.46) x 3 less openings 3.5443.98 m²
Flooring14.03.0-12.00 m²

Note: both openings (2.10 m² and 1.44 m²) are between 0.5 and 3 m², so as per IS 1200 they are deducted from one face only (here the outside), and the reveals are not added. Total plaster = 42.00 + 43.98 = 85.98 m².

Abstract of cost (rates illustrative)

SNItemQtyUnitRate (Rs)Amount (Rs)
1Excavation13.43m³6008,058
2PCC 1:3:62.01m³11,50023,115
3Brickwork 1:6 in foundation3.92m³14,00054,880
4DPC3.43m²6502,230
5Brickwork 1:6 in superstructure9.48m³15,500146,940
6Plaster 12.5 mm, both faces85.98m²48041,270
7Flooring12.00m²90010,800
Total287,293

Contingency, VAT and the other items (RCC slab, roofing, doors, painting) would be added in the same way.