- 2079 Bhadra · 2 marks
Method of quantity estimate for road
Short answer
Take cross-sections at regular intervals, finding cut/fill depths from ground and formation levels. Calculate sectional areas using formation width and side slopes, then compute volumes by mean area or prismoidal method and add pavement layers.
Briefly explain the method of quantity estimate for road construction.
Quantities of road earthwork are found from the longitudinal section and cross-sections.
- Take cross-sections at regular intervals (e.g. 10–30 m, closer on curves) and at points where the ground changes.
- Find the depth of cutting or height of filling at the centre line from the ground level and formation level; the formation level follows the design gradients.
- For each section calculate the area of cutting and filling from the formation width and side slopes ( for level ground; side-hill formulae when the ground has a cross slope).
- Find the volume between consecutive sections by the mean sectional area method (), or the prismoidal formula for greater accuracy.
- Add the quantities of pavement layers (area × thickness), drains, culverts and protection works, and put everything in a bill of quantities.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Estimate, quantity survey, estimated vs actual · Estimating and Costing, chapter 1
- Define project; road project estimate · Estimating and Costing, chapter 5
- Components of detail estimate report (road) · Estimating and Costing, chapter 5
- Road earthwork, grades 1 in 120 and 1 in 90 (0-120) · Estimating and Costing, chapter 6 · asked 2×
- Road earthwork, chainage 0-80 (s) · Estimating and Costing, chapter 6 · asked 2×
- Road earthwork, 80 m length (v) · Estimating and Costing, chapter 6 · asked 2×
- Road construction equipment and mass haul characteristics · Transportation Engineering II, chapter 3 · asked 3×
- Short note: construction procedure of gravel road · Transportation Engineering II, chapter 3 · asked 2×
- Report on road construction in remote Nepal · Communication English, chapter 9
- Road construction equipment, paver and bitumen sprayer · Construction Management, chapter 4