Skip to main content

Road earthwork, grades 1 in 120 and 1 in 90 (0-120)

Short answer

Calculate formation levels from given grades and reference, compute cut/fill depths. Using level-section area A=(B+s h)h, determine volumes by mean area method: 1,745.94 m³ cutting and 187.07 m³ filling.

Estimate the quantity of earthwork of a portion of road from the following data: Formation width of the road = 10 m. Side slope in banking = 2:1 (H:V), side slope in cutting = 1:1. Downward grade 1 in 120 from distance 0 m to 30 m while it remains in level from distance 30 m to 90 m and has again upward grade 1 in 90 from distance 90 to 120 m. The formation level at distance 60 m = 1197.50 m. The ground levels of the centre line of the road are as under:

R.L. of ground1198.651196.401199.301200.401198.10
Distance in m0306090120

Given data and assumptions

  • Formation width B=10B = 10 m; banking slope 2:12:1, cutting slope 1:11:1. Ground is level across the road.
  • Formation levels: 1197.50 m at 60 m; level from 30 m to 90 m; falling 1 in 120 from 0 to 30 m, so the level at 0 m is 1197.50 + 30/120 = 1197.75 m; rising 1 in 90 from 90 to 120 m, so the level at 120 m is 1197.50 + 30/90 = 1197.833 m.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0001,198.6501,197.750cutting 0.900
0+0301,196.4001,197.500filling 1.100
0+0601,199.3001,197.500cutting 1.800
0+0901,200.4001,197.500cutting 2.900
0+1201,198.1001,197.833cutting 0.267

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.909.8100.000
0+030fill 1.100.00013.420
0+060cut 1.8021.2400.000
0+090cut 2.9037.4100.000
0+120cut 0.272.7380.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.066.22110.71
0+030 – 0+06030.0197.7576.36
0+060 – 0+09030.0879.750.00
0+090 – 0+12030.0602.220.00
Total120.01,745.94187.07

Answer: Earthwork in cutting = 1,745.94 m³; earthwork in filling = 187.07 m³.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 6 questions →