- Asked 8/31
- 2081 Baisakh · 6 marks
Cutting volume, 120 m, upward slope 1 in 40
Short answer
With two-level sections, centre depths 0.80–2.60 m, areas 8.562–33.714 m², spacing 30 m. Trapezoidal volume = 2597.43 m³, prismoidal = 2526.74 m³, prismoidal correction = 70.69 m³.
Find the volume in a length of 120 m with the following data for a two level section using the prismoidal and trapezoidal formula. Also calculate the prismoidal correction. Formation width = 8 m, side slope is 1.5:1, transverse slope = 6:1. The ground level at 30 m intervals are given below.
| Chainage (m) | 0 | 30 | 60 | 90 | 120 |
|---|---|---|---|---|---|
| Ground level (m) | 380.8 | 382.3 | 383.6 | 384.1 | 385.6 |
The formation has an upward slope of 1 in 40 with the formation level at 0+000 chainage being 380.00 m.
A two-level section (ground sloping across the road) is used at every chainage. Data: formation width m, side slope (horizontal : vertical), transverse ground slope , section spacing m.
Step 1: Formation levels and depths at the centre line
The formation rises at 1 in 40, so it gains m in every 30 m: . The centre depth of cut is .
| Chainage (m) | GL (m) | FL (m) | Centre depth of cut h (m) |
|---|---|---|---|
| 0 | 380.80 | 380.00 | 0.80 |
| 30 | 382.30 | 380.75 | 1.55 |
| 60 | 383.60 | 381.50 | 2.10 |
| 90 | 384.10 | 382.25 | 1.85 |
| 120 | 385.60 | 383.00 | 2.60 |
Step 2: Cross-sectional areas
Along the cross-section the ground rises on one side and falls on the other. The depths of cut at the two side slope ends (where the side slope meets the ground) are
The horizontal distances from the centre line to these points are and , and the area of the section is
(the triangle between the two side slopes extended and the ground line, minus the triangle below the formation width).
Worked section at chainage 0, m:
| Chainage (m) | h (m) | h₁ (m) | h₂ (m) | d₁ (m) | d₂ (m) | Area A (m²) |
|---|---|---|---|---|---|---|
| 0 | 0.80 | 1.956 | 0.107 | 6.933 | 4.160 | 8.562 |
| 30 | 1.55 | 2.956 | 0.707 | 8.433 | 5.060 | 17.782 |
| 60 | 2.10 | 3.689 | 1.147 | 9.533 | 5.720 | 25.687 |
| 90 | 1.85 | 3.356 | 0.947 | 9.033 | 5.420 | 21.974 |
| 120 | 2.60 | 4.356 | 1.547 | 10.533 | 6.320 | 33.714 |
Step 3: Volume by the trapezoidal formula
Step 4: Volume by the prismoidal formula
Step 5: Prismoidal correction
The trapezoidal formula overestimates the volume by 70.69 m³, so the prismoidal volume is the more accurate one.
Answer: Volume of cutting by the trapezoidal formula = 2597.43 m³; by the prismoidal formula = 2526.74 m³; prismoidal correction = 70.69 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Filling volume, 60 m, formation 1281.49 · Surveying I, chapter 9
- Cutting volume, depths 2 m, 3 m, 4 m · Surveying I, chapter 9
- Prismoidal formula for volume · Surveying I, chapter 9
- Volume from central depths 1.85, 2.15, 2.45 · Surveying I, chapter 9
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Economical trapezoidal channel side length · Hydro Power, chapter 1
- Vertical drop crest level and width, Q 30 · Irrigation and Drainage Engineering, chapter 7