- 2080 Baisakh · 6 marks
Filling volume, 60 m, formation 1281.49
Short answer
Compute formation levels and centre heights, then cross-sectional areas using two-level section formulas for embankment with side slopes 2:1, transverse slope 8:1. Trapezoidal volume = 1088.34 m³, prismoidal volume = 1114.62 m³, prismoidal correction = -26.28 m³.
Find the volume of filling in a length of 60 m with the following data for a two level section, using the trapezoidal and prismoidal formulae.
| Chainage (km) | 0+000 | 0+030 | 0+060 |
|---|---|---|---|
| RL of GL (m) | 1280.50 | 1280.80 | 1281.40 |
Formation width = 12 m, side slope = 2:1, transverse slope = 8:1. The formation has an upward gradient of 1 in 60 with the formation level at 0+000 chainage being 1281.49 m. Also compute the prismoidal correction.
A two-level section (ground sloping across the road) is used at every chainage. Data: formation width m, side slope (horizontal : vertical), transverse ground slope , section spacing m.
Step 1: Formation levels and depths at the centre line
The formation rises at 1 in 60, so it gains m per 30 m: . The centre height of fill is .
| Chainage (m) | GL (m) | FL (m) | Centre height of fill h (m) |
|---|---|---|---|
| 0 | 1280.50 | 1281.49 | 0.99 |
| 30 | 1280.80 | 1281.99 | 1.19 |
| 60 | 1281.40 | 1282.49 | 1.09 |
Step 2: Cross-sectional areas
For an embankment on cross-sloping ground, the heights of fill at the two side slope ends are
The horizontal distances from the centre line to these points are and , and the area of the section is
(the triangle between the two side slopes extended and the ground line, minus the triangle above the formation width).
Worked section at chainage 0, m:
| Chainage (m) | h (m) | h₁ (m) | h₂ (m) | d₁ (m) | d₂ (m) | Area A (m²) |
|---|---|---|---|---|---|---|
| 0 | 0.99 | 0.192 | 2.320 | 6.384 | 10.640 | 15.963 |
| 30 | 1.19 | 0.352 | 2.587 | 6.704 | 11.173 | 19.453 |
| 60 | 1.09 | 0.272 | 2.453 | 6.544 | 10.907 | 17.687 |
Step 3: Volume by the trapezoidal formula
Step 4: Volume by the prismoidal formula
Step 5: Prismoidal correction
The correction is negative here because the middle area is larger than the mean of the two end areas. The trapezoidal formula therefore underestimates the volume, and 26.28 m³ has to be added to it to get the prismoidal volume.
Answer: Volume of filling by the trapezoidal formula = 1088.34 m³; by the prismoidal formula = 1114.62 m³; prismoidal correction = -26.28 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Level book and longitudinal section, RL 525.50 · Surveying I, chapter 5
- RL of hill station P (A-B 125 m, RL B 1280.50) · Surveying II, chapter 3 · asked 2×
- Road earthwork with RL of GL and FL (0-600) · Estimating and Costing, chapter 6
- Road earthwork, chainage 0-80 (s) · Estimating and Costing, chapter 6 · asked 2×
- Road earthwork, 80 m length (v) · Estimating and Costing, chapter 6 · asked 2×