Road earthwork, 80 m length (v)

Short answer

Earthwork in cutting = 330.59 m³; earthwork in filling = 162.29 m³.

Estimate the quantity of earthwork in cutting and filling from the following data for a portion of road 80 m length. Formation width = 10 m. Side slopes in banking 2:1. Side slopes in cutting 1:1.

ChainageDepth of cutting at centre lineHeight of bankingCross slope of ground
0 m0.60—10:1
20 m0.70—12:1
40 m0.50—15:1
60 m0.3012:1
80 m0.7010:1

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in banking 2:12:1, in cutting 1:11:1.
  • Sections 20 m apart: cutting at 0, 20, 40 m and filling at 60, 80 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.606.6770.000
0+020cut 0.707.7170.000
0+040cut 0.505.3850.000
0+060fill 0.300.0893.698
0+080fill 0.700.0008.833

Working for one section:

Take chainage 0+020: centre cutting depth h=0.70h = 0.70 m, n=12n = 12, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =1.117= 1.117 m, at the downhill edge =0.283= 0.283 m.
  • Toe of the side slope on the uphill side at x=6.218x = 6.218 m from the centre line (ground above formation by 1.218 m); downhill toe at x=5.262x = 5.262 m (ground above formation by 0.262 m).
  • Area from the co-ordinates of the polygon: cutting =7.717= 7.717 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+02020.0143.940.00
0+020 – 0+04020.0131.020.00
0+040 – 0+06020.054.7436.98
0+060 – 0+08020.00.89125.31
Total80.0330.59162.29

Answer: Earthwork in cutting = 330.59 m³; earthwork in filling = 162.29 m³.