Road earthwork, 80 m length (v)
Short answer
Earthwork in cutting = 330.59 m³; earthwork in filling = 162.29 m³.
Estimate the quantity of earthwork in cutting and filling from the following data for a portion of road 80 m length. Formation width = 10 m. Side slopes in banking 2:1. Side slopes in cutting 1:1.
| Chainage | Depth of cutting at centre line | Height of banking | Cross slope of ground |
|---|---|---|---|
| 0 m | 0.60 | — | 10:1 |
| 20 m | 0.70 | — | 12:1 |
| 40 m | 0.50 | — | 15:1 |
| 60 m | 0.30 | 12:1 | |
| 80 m | 0.70 | 10:1 |
Given data and assumptions
- Formation width m; side slope in banking , in cutting .
- Sections 20 m apart: cutting at 0, 20, 40 m and filling at 60, 80 m.
Method
Ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line and the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | cut 0.60 | 6.677 | 0.000 |
| 0+020 | cut 0.70 | 7.717 | 0.000 |
| 0+040 | cut 0.50 | 5.385 | 0.000 |
| 0+060 | fill 0.30 | 0.089 | 3.698 |
| 0+080 | fill 0.70 | 0.000 | 8.833 |
Working for one section:
Take chainage 0+020: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.218 m); downhill toe at m (ground above formation by 0.262 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+020 | 20.0 | 143.94 | 0.00 |
| 0+020 – 0+040 | 20.0 | 131.02 | 0.00 |
| 0+040 – 0+060 | 20.0 | 54.74 | 36.98 |
| 0+060 – 0+080 | 20.0 | 0.89 | 125.31 |
| Total | 80.0 | 330.59 | 162.29 |
Answer: Earthwork in cutting = 330.59 m³; earthwork in filling = 162.29 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Road earthwork, chainage 0-80 (s) · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Hill road earthwork, cross slope 1 in 5 (0-60) · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×