Apply side-hill section formulas for given formation width 10 m, side slopes, and transverse slopes at 20 m intervals. Earthwork quantities are 256.73 m³ in cutting and 187.23 m³ in filling.

Estimate the quantity of earthwork in cutting and filling from the following data for a portion of road. Formation width = 10 m, side slope in banking = 2:1, side slope in cutting = 1:1.

ChainageDepth of cutting (m)Height of filling (m)Cross slope of ground
00.60—10:1
200.30—8:1
400.50—12:1
60—0.3510:1
80—0.7012:1

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in banking 2:12:1, in cutting 1:11:1.
  • Sections 20 m apart; cutting up to 40 m and filling at 60 m and 80 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.606.6770.000
0+020cut 0.303.9110.563
0+040cut 0.505.4620.000
0+060fill 0.350.1254.516
0+080fill 0.700.0008.565

Working for one section:

Take chainage 0+020: centre cutting depth h=0.30h = 0.30 m, n=8n = 8, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.925= 0.925 m, at the downhill edge =−0.325= -0.325 m.
  • Toe of the side slope on the uphill side at x=6.057x = 6.057 m from the centre line (ground above formation by 1.057 m); downhill toe at x=5.867x = 5.867 m (ground below formation by 0.433 m).
  • Area from the co-ordinates of the polygon: cutting =3.911= 3.911 m², filling =0.563= 0.563 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+02020.0105.885.63
0+020 – 0+04020.093.735.63
0+040 – 0+06020.055.8745.16
0+060 – 0+08020.01.25130.81
Total80.0256.73187.23

Answer: Earthwork in cutting = 256.73 m³; earthwork in filling = 187.23 m³.