- 2078 Kartik · 5+1 marks
Cutting volume, depths 2 m, 3 m, 4 m
Short answer
Compute cross-sectional areas for cutting with side slopes 1:1, transverse slope 6:1, formation width 8 m. Trapezoidal volume = 2094.87 m³, prismoidal volume = 2084.58 m³, prismoidal correction = 10.29 m³.
The width of formation level of a certain cutting is 8 m and the side slopes are 1:1. The surface of the ground has a transverse slope of 1 in 6. If the depths of cutting at the centre lines of three sections 30 m apart are 2 m, 3 m and 4 m respectively, determine the volume of earth work involved in this length of cutting by trapezoidal approach and prismoidal approach. Also find the prismoidal correction.
A two-level section (ground sloping across the road) is used at every chainage. Data: formation width m, side slope (horizontal : vertical), transverse ground slope , section spacing m.
Step 1: Centre heights
The centre depths of cut are given: , and m at chainages 0, 30 and 60 m. The transverse slope 1 in 6 means and the side slope 1:1 means .
Step 2: Cross-sectional areas
Along the cross-section the ground rises on one side and falls on the other. The depths of cut at the two side slope ends (where the side slope meets the ground) are
The horizontal distances from the centre line to these points are and , and the area of the section is
(the triangle between the two side slopes extended and the ground line, minus the triangle below the formation width).
Worked section at chainage 0, m:
| Chainage (m) | h (m) | h₁ (m) | h₂ (m) | d₁ (m) | d₂ (m) | Area A (m²) |
|---|---|---|---|---|---|---|
| 0 | 2.00 | 3.200 | 1.143 | 7.200 | 5.143 | 21.029 |
| 30 | 3.00 | 4.400 | 2.000 | 8.400 | 6.000 | 34.400 |
| 60 | 4.00 | 5.600 | 2.857 | 9.600 | 6.857 | 49.829 |
Step 3: Volume by the trapezoidal formula
Step 4: Volume by the prismoidal formula
Step 5: Prismoidal correction
The trapezoidal formula overestimates the volume by 10.29 m³, so the prismoidal volume is the more accurate one.
Answer: Volume of cutting by the trapezoidal formula = 2094.87 m³; by the prismoidal formula = 2084.58 m³; prismoidal correction = 10.29 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 120 m, upward slope 1 in 40 · Surveying I, chapter 9 · asked 8×
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Vertical drop crest level and width, Q 30 · Irrigation and Drainage Engineering, chapter 7