- 2073 Shrawan · 16 marks
Road earthwork, RD 0-120, gradient 1 in 150
Short answer
Using side-hill section formulas, areas at each RD are obtained. Volumes by mean area method and change-over point where cut transits to fill. Total cutting: 241.62 m³, filling: 573.42 m³.
Prepare an estimate of earthwork for a road portion from the following data: Formation width = 8 m in cutting and 10 m in banking. Side slope in cutting = 1:1, side slope in banking = 2:1 (H:V).
| RD | 0 | 30 | 60 | 90 | 120 |
|---|---|---|---|---|---|
| RLS of ground | 507.0 | 507.95 | 507.30 | 506.90 | 506.50 |
| Formation level | 507.0 and upward gradient @ 1 in 150 | ||||
| Cross slope of ground | 1:10 | 1:12 | 1:10 | 1:12 | 1:10 |
Given data and assumptions
- Formation width m in cutting and m in banking; side slope in cutting , in banking (H:V).
- Formation level 507.00 m at RD 0, rising 1 in 150: 507.00, 507.20, 507.40, 507.60, 507.80 m. The section at RD 0 has zero centre height and is taken with the cutting width of 8 m.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
| Chainage | GL (m) | FL (m) | Depth of cutting / height of filling (m) |
|---|---|---|---|
| 0+000 | 507.000 | 507.000 | 0.000 |
| 0+030 | 507.950 | 507.200 | cutting 0.750 |
| 0+060 | 507.300 | 507.400 | filling 0.100 |
| 0+090 | 506.900 | 507.600 | filling 0.700 |
| 0+120 | 506.500 | 507.800 | filling 1.300 |
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | 0.00 | 0.889 | 1.000 |
| 0+030 | cut 0.75 | 6.720 | 0.000 |
| 0+060 | fill 0.10 | 0.889 | 2.250 |
| 0+090 | fill 0.70 | 0.000 | 8.565 |
| 0+120 | fill 1.30 | 0.000 | 17.583 |
Working for one section:
Take chainage 0+000: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 0.444 m); downhill toe at m (ground below formation by 0.500 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between RD 30 (wholly in cutting, 0.75 m) and RD 60 (filling 0.10 m at the centre): the zero point is m from RD 30, leaving m in filling.
- Cutting is present at both ends (6.720 and 0.889 m²), so the mean area is used: m³
- Filling is zero at RD 30, so it is taken over the 3.53 m only: m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 114.14 | 15.00 |
| 0+030 – 0+060 | 30.0 (filling over 3.53) | 114.14 | 3.97 |
| 0+060 – 0+090 | 30.0 | 13.33 | 162.23 |
| 0+090 – 0+120 | 30.0 | 0.00 | 392.23 |
| Total | 120.0 | 241.61 | 573.43 |
Answer: Earthwork in cutting = 241.61 m³; earthwork in filling = 573.43 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Road earthwork, grades 1 in 120 and 1 in 90 (0-120) · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, 0 m to 90 m, 10/8 m widths · Estimating and Costing, chapter 6 · asked 2×
- Road earthwork, rising 1 in 200, falling 1 in 120 · Estimating and Costing, chapter 6
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 120 m, upward slope 1 in 40 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×