Road earthwork, rising 1 in 200, falling 1 in 120

Short answer

Using level section formula A=(B+sh)h with B=10m and side slopes 1:1 cutting, 2:1 filling, compute areas from centre heights and then mean-area volumes. Earthwork: cutting 1623.40 m³, filling 137.02 m³.

Estimate quantities of earthwork of a portion of road from the following data: (i) Formation width of road is 10 m. (ii) Side slope in cutting and filling (1:1) and (2:1) (H:V) respectively.

Distance0306090120150180
R.L. of ground102.60103.00102.65102.20101.50101.20100.65
R.L. of formation101102.15
GradientRising gradient 1 in 200Falling gradient 1 in 120

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in filling 2:12:1. Ground is level across the road.
  • Formation level at 0 m is 101.00 m, rising 1 in 200 up to 120 m (101.60 m) and falling 1 in 120 from 120 m to 180 m (101.10 m). The printed 102.15 at 120 m does not fit a 1 in 200 gradient, so the stated gradients are used.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000102.600101.000cutting 1.600
0+030103.000101.150cutting 1.850
0+060102.650101.300cutting 1.350
0+090102.200101.450cutting 0.750
0+120101.500101.600filling 0.100
0+150101.200101.350filling 0.150
0+180100.650101.100filling 0.450

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 1.6018.5600.000
0+030cut 1.8521.9220.000
0+060cut 1.3515.3230.000
0+090cut 0.758.0620.000
0+120fill 0.100.0001.020
0+150fill 0.150.0001.545
0+180fill 0.450.0004.905

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0607.240.00
0+030 – 0+06030.0558.680.00
0+060 – 0+09030.0350.780.00
0+090 – 0+12030.0106.711.80
0+120 – 0+15030.00.0038.47
0+150 – 0+18030.00.0096.75
Total180.01,623.40137.02

Answer: Earthwork in cutting = 1,623.40 m³; earthwork in filling = 137.02 m³.